You are on page 1of 1

MASTER S CURVE WWTP PT.

ADISH DIMENSION FOOTWEAR


TIM E PERIO DE
2023 - 2024
BULAN NOVEMBER BULAN DESEMBER BULAN JANUARI BULAN FEBRUARI BULAN MARET BULAN APRIL
NO ITEMS OF WORK WEIGHT
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23 Week 24

PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT
ITEM PEKERJAAN
DESIGN SERVICE
1 Design Engineering 3,64% 0,91% 0,91% 0,91% 0,91% 100,00% 100,00% 100,00% 100,00%
2 Supervisi 9,01% 2,25% 2,25% 2,25% 2,25%
100,00%
PEKERJAAN SIPIL
I BASEPLATE ANAEROBIK
A PEKERJAAN PERSIAPAN
Penebangan Pohon Eksisting + pembuangan, qty = 2 Pohon sedang 2 pohon
1 1,44% 0,72% 0,72%
kecil
B PEKERJAAN KONSTRUKSI BETON BERTULANG 94,92%
1 Pek. Urugan pasir (10 cm) 0,18% 0,09% 0,09%
2 Pekerjaan lantai kerja, t = 5 cm, beton tumbuk adukan 1:3:5 0,51% 0,25% 0,25%
3 Sloof Beton Bertulang Uk. 20cm x 40cm
- Beton Ready Mix, Mutu K-300 0,66% 0,33% 0,33%
Pembesian, Tulangan utama D13, Sengkang D10-200, Deformed, Fy 400Mpa
- 2,75% 1,38% 1,38%

- Bekisting 1,28% 0,64% 0,64%


4 Balok Beton Bertulang Uk. 20cm x 40cm - kantilever
- Beton Ready Mix, Mutu K-300 0,14% 0,07% 0,07%
Pembesian, Tulangan utama D13, Sengkang D10-175, Deformed, Fy 400Mpa
- 0,57% 0,28% 0,28%

- Bekisting 0,37% 0,18% 0,18% 86,36%


5 Plat Lantai Beton Bertulang, tebal 15cm - Lt. Utama
- Beton Ready Mix, Mutu K-300 1,18% 0,59% 0,59%
- Pembesian Wiremesh M8-150, U-50, 2 lapis 0,12% 0,06% 0,06%
- Bondek, 0.75 0,80% 0,40% 0,40%
Plat Lantai Beton Bertulang, tebal 15cm - Lt. Trap Tangga & Perataan Level
6
- Beton Ready Mix, Mutu K-300 0,21% 0,11% 0,11%
- Pembesian Wiremesh M8-150, U-50, 1 lapis 0,02% 0,01% 0,01%
7 79,93%
Finishing Beton
- Pekerjaan Acian Floor Beton 0,47% 0,23% 0,23%
- Pekerjaan Cat Lantai Solventbase AVIPEN Dark Green 2 lapis 0,85% 0,43% 0,43%
8 Handrail
- Pek. Bongkar Handrail 0,22% 0,11% 0,11%
- Pek. Pasang kembali Handrail, sudah termasuk modifikasi & Repaint 0,42% 0,21% 0,21%
9 Perkuatan Pagar 1,22% 0,61% 0,61%
II BASEPLATE POST TREATMENT
A PEKERJAAN PERSIAPAN
Penebangan Pohon Eksisting + pembuangan, qty = 1 pohon sedang 2 pohon
1 1,80% 0,90% 0,90%
sedang + 2 pohon kecil
B PEKERJAAN KONSTRUKSI BETON BERTULANG
71,39%
1 Pek. Pondasi Precast Mini Pile 20 x 20 x 300 cm, termasuk bobok kepala 0,72% 0,36% 0,36%
2 Pekerjaan lantai kerja, t = 5 cm, beton tumbuk adukan 1:3:5 0,96% 0,48% 0,48%
3 Sloof Beton Bertulang Uk. 25cm x 35cm
- Beton Ready Mix, Mutu K-300 0,88% 0,29% 0,29% 0,29%
Pembesian, Tulangan utama D13, Sengkang D10-175, Deformed, Fy 400Mpa
- 3,70% 1,23% 1,23% 1,23%

- Bekisting 1,38% 0,46% 0,46% 0,46%


4 Balok Beton Bertulang Uk. 25cm x 35cm - menerus
- Beton Ready Mix, Mutu K-300 0,22% 0,07% 0,07% 0,07%
Pembesian, Tulangan utama D13, Sengkang D10-175, Deformed, Fy 400Mpa
- 0,94% 0,31% 0,31% 0,31%

- Bekisting 0,70% 0,23% 0,23% 0,23%


5 Plat Lantai Beton Bertulang, tebal 15cm - Lt. Utama
- Beton Ready Mix, Mutu K-300 4,41% 1,47% 1,47% 1,47%
- Pembesian Wiremesh M8-150, U-50, 2 lapis 0,46% 0,15% 0,15% 0,15%
- Bondek, 0.75 1,97% 0,66% 0,66% 0,66%
6 Plat Lantai Beton Bertulang, tebal 15cm - Lt. pejalan kaki
- Beton Ready Mix, Mutu K-300 1,04% 0,35% 0,35% 0,35%
- Pembesian Wiremesh M8-150, U-50, 1 lapis 0,11% 0,04% 0,04% 0,04%
7 Finishing Beton
- Pekerjaan Acian Floor Beton 1,66% 56,58% 0,83% 0,83%
- Pekerjaan Cat Lantai Solventbase AVIPEN Dark Green 2 lapis 3,03% 1,52% 1,52%
8 Handrail
- Pek. Bongkar Handrail 0,44% 0,22% 0,22%
- Pek. Pasang kembali Handrail, sudah termasuk modifikasi & Repaint 0,21% 0,11% 0,11%
9 Plaster & Acian Tanggul Penahan Tanah 0,22% 0,11% 0,11%
10 Pengecatan dinding bata exterior dengan Dulux Catylac Exterior 0,17% 0,09% 0,09%
C PEKERJAAN KONSTRUKSI BAJA & ATAP
1 Pedestal kolom Atas, Beton Bertulang Uk. 25cm x 25cm
- Beton Ready Mix, Mutu K-300 0,06% 0,03% 0,03%
Pembesian, Tulangan utama 4 D13 + Sengkang D10-200, mutu Fy 400Mpa,
- 0,22% 0,11% 0,11%
Ulir
- Bekisting 0,18% 0,09% 0,09%
47,60%
2 Pekerjaan Konstruksi Baja
- Non-shrinkage grouting di bawah base plate ex Sika Grout GP t=25 mm 0,00% 0,00% 0,00%
Kolom, Box 2CNP 125.50.20.2,3 + Pengecatan Zinchromate 1 lapis + Ftalit 2
- 1,68% 0,84% 0,84%
lapis
Rafter & Strut, Box 2CNP 100.50.20.2,3 + Pengecatan Zinchromate 1 lapis +
- 3,69% 1,85% 1,85%
Ftalit 2 lapis
Gording CNP 100.50.20.2,3 + Pengecatan Zinchromate 1 lapis + Ftalit 2 lapis
- 2,83% 42,47% 1,42% 1,42%

- Trekstang, Besi Behel polos Ø8 mm 0,06% 0,03% 0,03%


- Ikatan Angin, Besi Behel Polos Ø8 mm 0,15% 0,08% 0,08%
- Turn buckle M8 Galvanis 1,22% 0,61% 0,61%
- Baseplate Embedded, angkur, Rib & Stiffner 0,52% 0,26% 0,26%
III CORING BAK AERASI- SEDIMENTASI
1 PEKERJAAN CORING BAK AERASI DAN SEDIMENTASI 4,32% 2,16% 2,16%
2 Pek. Fasilitas Pendukung (Area Anoxic). Berupa scaffolding 3,84% 37,45% 1,92% 1,92%
3 Pek. Coring 4 Titik 6 " (2" X 3) 3,06% 1,53% 1,53%
4 Pek. Pemasangan Sparing Pipa 6" 0,96% 0,48% 0,48%
5 Pek. Pemasangan Sparing Pipa 8" 4,32% 2,16% 2,16%
IV ATAP MULTI DISC SCREW PRESS (2m x 5m)
33,95%
1 Pekerjaan Lantai Bak Kolam
- Bobok Beton s.d ketemu permukaan beton kasar 0,24% 0,12% 0,12%
- Boring lubang rebar D13 + grouting ex Sika Grout, kedalaman 45cm 2,08% 32,15% 1,04% 1,04%
- Beton Ready Mix, Mutu K-300 0,45% 0,22% 0,22%
- Pembesian Wiremesh M8-150, U-50, 2 lapis 0,04% 0,02% 0,02%
Pembesian, Tulangan tegak D13-200, Tulangan horisontal 6 D13, mutu Fy
- 1,14% 0,57% 0,57%
400Mpa, Ulir
- Bondek, 0.75 0,48% 0,24% 0,24%
- Bekisting 0,32% 0,16% 0,16%
- Finishing exposed beton 0,31% 0,16% 0,16%
- Pekerjaan Cat Lantai Solventbase AVIPEN Dark Green 2 lapis 0,22% 0,11% 0,11%
- Pengecatan exterior dengan Dulux Catylac Exterior 0,09% 25,61% 0,05% 0,05%
- Tutup Manhole, Swing, ukuran 80cm x 80cm 0,52% 0,26% 0,26%
2 Pedestal kolom Atas, Beton Bertulang Uk. 25cm x 25cm
- Beton Ready Mix, Mutu K-300 0,02% 0,01% 0,01%
Pembesian, Tulangan utama 4 D13 + Sengkang D10-200, mutu Fy 400Mpa,
- 0,11% 0,05% 0,05%
Ulir
- Bekisting 0,08% 0,04% 0,04%
3 Pekerjaan Konstruksi Baja
- Non-shrinkage grouting di bawah base plate ex Sika Grout GP t=25 mm 0,00% 0,00% 0,00%
Kolom, Box 2CNP 100.50.20.2,3 + Pengecatan Zinchromate 1 lapis + Ftalit 2
- 0,47%
18,62%
0,24% 0,24%
lapis
Rafter & Strut, Box 2CNP 100.50.20.2,3 + Pengecatan Zinchromate 1 lapis +
- 1,20% 0,60% 0,60%
Ftalit 2 lapis
Gording CNP 100.50.20.2,3 + Pengecatan Zinchromate 1 lapis + Ftalit 2 lapis
- 0,84% 0,42% 0,42%

- Trekstang, Besi Behel polos Ø8 mm 0,02% 0,01% 0,01%


- Ikatan Angin, Besi Behel Polos Ø8 mm 0,07% 14,26% 0,03% 0,03%
- Turn buckle M8 Galvanis 0,61% 0,30% 0,30%
- Baseplate Embedded, angkur, Rib & Stiffner 0,16% 0,08% 0,08%
4 Pekerjaan Atap & Talang
Penutup atap, zinc-aluminium, Kobatrim 1030 tebal 0.45 TCT, Ex SARANA
- 0,93% 0,46% 0,46%

Nok, Steel Flashing t = 0.4 mm, L = 60cm, termasuk cutting, bending &
- 0,40% 0,20% 0,20%
sealant joint 8,93%
V BREAK TANK
A Pekerjaan Ground Tank, uk. Sisi dalam 3200 X 1500 X 1500, ( 1 unit )
- -
1 Pembongkaran & bobokan lantai lama 0,14% 0,07% 0,07%
2 Galian tanah, termasuk bongkar pembuangan 0,21% 0,10% 0,10%
3 Urugan sirdam, dipadatkan dengan stamper 0,08% 0,03% 0,03% 0,03%
4 Pekerjaan lantai kerja, t = 5 cm, beton tumbuk adukan 1:3:5 0,09% 4,07% 0,04% 0,04%
5 Bekisting dengan pasangan bata 1,43% 0,72% 0,72%
6 Bekisting multipleks 12 mm + stoot werk 1,08% 0,54% 0,54%
7 Beton Ready Mix, Mutu K-300 1,36% 0,68% 0,68%
8 Pembesian, Mutu Fy 400Mpa, Ulir 5,27% 2,64% 2,64%
0,91%
9 Finishing exposed beton 0,14% 0,07% 0,07%
10 Tutup Manhole, Swing, ukuran 80cm x 80cm 1,20% 0,00% 1
0,00%
2
0,00%
3 4 5 6 7 8 9
0,60%
10
0,60%
11 12 13 14 15 16 17 18 19 20 21 22 23 24

Total 100,00%

Rencana ( Planing ) 0,00% 0,00% 0,00% 0,91% 3,16% 4,85% 5,33% 4,36% 6,99% 6,54% 1,79% 3,50% 5,02% 5,13% 8,97% 14,81% 8,54% 6,43% 8,56% 5,08% 0,00% 0,00% 0,00% 0,00%
Progress ( Aktual ) 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Akumulasi Rencana (Planing Acumulate) 0,00% 0,00% 0,00% 0,91% 4,07% 8,93% 14,26% 18,62% 25,61% 32,15% 33,95% 37,45% 42,47% 47,60% 56,58% 71,39% 79,93% 86,36% 94,92% 100,00% 100,00% 100,00% 100,00% 100,00%
Akumulasi Progres ( Actual Acumulate ) 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Standar Deviasi 0,00% 0,00% 0,00% -0,91% -4,07% -8,93% -14,26% -18,62% -25,61% -32,15% -33,95% -37,45% -42,47% -47,60% -56,58% -71,39% -79,93% -86,36% -94,92% -100,00% -100,00% -100,00% -100,00% -100,00%

Dibuat Oleh, Disetujui Oleh,


LEGEND
Kontraktor
PT. TATA TIRTA UTAMA
PEKERJAAN UTAMA

ITEM PEKERJAAN

SUB ITEM PEKERJAAN

DURASI PEKERJAAN
Project Manager …………………….
`

You might also like