PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT PLAN ACT
ITEM PEKERJAAN
DESIGN SERVICE
1 Design Engineering 3,64% 0,91% 0,91% 0,91% 0,91% 100,00% 100,00% 100,00% 100,00%
2 Supervisi 9,01% 2,25% 2,25% 2,25% 2,25%
100,00%
PEKERJAAN SIPIL
I BASEPLATE ANAEROBIK
A PEKERJAAN PERSIAPAN
Penebangan Pohon Eksisting + pembuangan, qty = 2 Pohon sedang 2 pohon
1 1,44% 0,72% 0,72%
kecil
B PEKERJAAN KONSTRUKSI BETON BERTULANG 94,92%
1 Pek. Urugan pasir (10 cm) 0,18% 0,09% 0,09%
2 Pekerjaan lantai kerja, t = 5 cm, beton tumbuk adukan 1:3:5 0,51% 0,25% 0,25%
3 Sloof Beton Bertulang Uk. 20cm x 40cm
- Beton Ready Mix, Mutu K-300 0,66% 0,33% 0,33%
Pembesian, Tulangan utama D13, Sengkang D10-200, Deformed, Fy 400Mpa
- 2,75% 1,38% 1,38%
Nok, Steel Flashing t = 0.4 mm, L = 60cm, termasuk cutting, bending &
- 0,40% 0,20% 0,20%
sealant joint 8,93%
V BREAK TANK
A Pekerjaan Ground Tank, uk. Sisi dalam 3200 X 1500 X 1500, ( 1 unit )
- -
1 Pembongkaran & bobokan lantai lama 0,14% 0,07% 0,07%
2 Galian tanah, termasuk bongkar pembuangan 0,21% 0,10% 0,10%
3 Urugan sirdam, dipadatkan dengan stamper 0,08% 0,03% 0,03% 0,03%
4 Pekerjaan lantai kerja, t = 5 cm, beton tumbuk adukan 1:3:5 0,09% 4,07% 0,04% 0,04%
5 Bekisting dengan pasangan bata 1,43% 0,72% 0,72%
6 Bekisting multipleks 12 mm + stoot werk 1,08% 0,54% 0,54%
7 Beton Ready Mix, Mutu K-300 1,36% 0,68% 0,68%
8 Pembesian, Mutu Fy 400Mpa, Ulir 5,27% 2,64% 2,64%
0,91%
9 Finishing exposed beton 0,14% 0,07% 0,07%
10 Tutup Manhole, Swing, ukuran 80cm x 80cm 1,20% 0,00% 1
0,00%
2
0,00%
3 4 5 6 7 8 9
0,60%
10
0,60%
11 12 13 14 15 16 17 18 19 20 21 22 23 24
Total 100,00%
Rencana ( Planing ) 0,00% 0,00% 0,00% 0,91% 3,16% 4,85% 5,33% 4,36% 6,99% 6,54% 1,79% 3,50% 5,02% 5,13% 8,97% 14,81% 8,54% 6,43% 8,56% 5,08% 0,00% 0,00% 0,00% 0,00%
Progress ( Aktual ) 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Akumulasi Rencana (Planing Acumulate) 0,00% 0,00% 0,00% 0,91% 4,07% 8,93% 14,26% 18,62% 25,61% 32,15% 33,95% 37,45% 42,47% 47,60% 56,58% 71,39% 79,93% 86,36% 94,92% 100,00% 100,00% 100,00% 100,00% 100,00%
Akumulasi Progres ( Actual Acumulate ) 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Standar Deviasi 0,00% 0,00% 0,00% -0,91% -4,07% -8,93% -14,26% -18,62% -25,61% -32,15% -33,95% -37,45% -42,47% -47,60% -56,58% -71,39% -79,93% -86,36% -94,92% -100,00% -100,00% -100,00% -100,00% -100,00%
ITEM PEKERJAAN
DURASI PEKERJAAN
Project Manager …………………….
`