FIRE SUPPRESION SYSTEM JAKARTA INTERNATIONAL STADIUM Page 1

SCHEDULE PELAKSANAAN PEKERJAAN FIRE SUPPRESSION JAKARTA INTERNATIONAL STADIUM

JUNI 2021 JULI 2021 AGUSTUS 2021

No KETERANGAN Minggu -1 Minggu -2 Minggu -3 Minggu -4 Minggu -5 Minggu -6 Minggu -7 Minggu -8 Minggu -9 Minggu -10 Minggu -11 Minggu -12
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

1 Penerimaan PO                                                                                                                                                                        

2 Material Approval & Detail Drawing                                                                                                                                                                        

  2.1 Shop Drawing Approval                                                                                                                                                                        

  2.2 Equipment & Instalasi Approval                                                                                                                                                                        

  2.3 As Built Drawing                                                                                                                                                                        

3 Procurement                                                                                                                                                                        

  3.1 Pengadaan Material Instalasi                                                                                                                                                                        

  3.2 Pengadaan Main Equipment                                                                                                                                                                        

4 Mobilisasi & Demobilisasi (Man Power)                                                                                                                                                                        

5 Delivery Material                                                                                                                                                                        

  5.1 Material Instalasi                                                                                                                                                                        

  5.2 Material Equipment Fire Alarm                                                                                                                                                                        

  5.3 Material Equipment Fire Suppression                                                                                                                                                                        

6 Instalasi Elektrik:                                                                                                                                                                        

  6.1 Smoke Detector                                                                                                                                                                        

  6.2 Manual Release                                                                                                                                                                        

  6.3 Abort Switch                                                                                                                                                                        

  6.4 Alarm Bell dan Horn                                                                                                                                                                        

  6.5 Evacuate dan Gas Discharge                                                                                                                                                                        

  6.6 Low pressure Switch                                                                                                                                                                        

  6.7 Electric Solenoid                                                                                                                                                                        

  6.8 Power 220Vac                                                                                                                                                                        

  6.9 Instalasi Shutdown AC                                                                                                                                                                        

7 Instalasi Mekanik                                                                                                                                                                        

  7.1 Fabrikasi Support                                                                                                                                                                        

  7.2 Fabrikasi Pipa                                                                                                                                                                        

  7.3 Pemasangan Instalasi Pipa                                                                                                                                                                        

8 Pemasangan Material Equipment                                                                                                                                                                        

  8.1 Material Elektrik                                                                                                                                                                        

  8.2 Material Mekanik                                                                                                                                                                        

9 Internal Test & Trouble Shooting                                                                                                                                                                        

10 Testing & Commisioning ,Training                                                                                                                                                                        

FIRE SUPPRESION SYSTEM JAKARTA INTERNATIONAL STADIUM Page 2


SCHEDULE PELAKSANAAN PEKERJAAN FIRE SUPPRESSION JAKARTA INTERNATIONAL STADIUM

SEPTEMBER 2021 OKTOBER 2021 NOVEMBER 2021

No KETERANGAN Minggu -13 Minggu -14 Minggu -15 Minggu -16 Minggu -17 Minggu -18 Minggu -19 Minggu -20 Minggu -21 Minggu -22 Minggu -23 Minggu -24
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

1 Penerimaan PO                                                                                                                                                                        

2 Material Approval & Detail Drawing                                                                                                                                                                        

  2.1 Shop Drawing Approval                                                                                                                                                                        

  2.2 Equipment & Instalasi Approval                                                                                                                                                                        

  2.3 As Built Drawing                                                                                                                                                                        

3 Procurement                                                                                                                                                                        

  3.1 Pengadaan Material Instalasi                                                                                                                                                                        

  3.2 Pengadaan Main Equipment                                                                                                                                                                        

4 Mobilisasi & Demobilisasi (Man Power)                                                                                                                                                                        

5 Delivery Material                                                                                                                                                                        

  5.1 Material Instalasi                                                                                                                                                                        

  5.2 Material Equipment Fire Alarm                                                                                                                                                                        

  5.3 Material Equipment Fire Suppression                                                                                                                                                                        

6 Instalasi Elektrik:                                                                                                                                                                        

  6.1 Smoke Detector                                                                                                                                                                        

  6.2 Manual Release                                                                                                                                                                        

  6.3 Abort Switch                                                                                                                                                                        

  6.4 Alarm Bell dan Horn                                                                                                                                                                        

  6.5 Evacuate dan Gas Discharge                                                                                                                                                                        

  6.6 Low pressure Switch                                                                                                                                                                        

  6.7 Electric Solenoid                                                                                                                                                                        

  6.8 Power 220Vac                                                                                                                                                                        

  6.9 Instalasi Shutdown AC                                                                                                                                                                        

7 Instalasi Mekanik                                                                                                                                                                        

  7.1 Fabrikasi Support                                                                                                                                                                        

  7.2 Fabrikasi Pipa                                                                                                                                                                        

  7.3 Pemasangan Instalasi Pipa                                                                                                                                                                        

8 Pemasangan Material Equipment                                                                                                                                                                        

  8.1 Material Elektrik                                                                                                                                                                        

  8.2 Material Mekanik                                                                                                                                                                        

9 Internal Test & Trouble Shooting                                                                                                                                                                        

10 Testing & Commisioning ,Training                                                                                                                                                                        

Dibuat Oleh,

PT MAHAWIRA PUTRA TEKNIK

FIRE SUPPRESION SYSTEM JAKARTA INTERNATIONAL STADIUM Page 3


METODE PELAKSANAAN

1. Nama Proyek : Jakarta International Stadium


2. Paket Pekerjaan : Fire Suppression
3. Lokasi : Jakarta Utara

Ruang Lingkup Pekerjaan :


a. Pengadaan dan pemasangan instalasi Fire Suppression System
b. Pekerjaan Testing Commissioning & Training
c. Masa Garansi selama 12 (dua belas) bulan
4. Waktu Pelaksanaan : 6 Bulan

5. Metode Pelaksanaan Pekerjaan :


1. Pekerjaan Persiapan

Pelaksanaan Pekerjaan Persiapan, meliputi :


- Pengurusan kontrak
- Peninjauan ke lokasi proyek dan pengurusan perijinan dan administrasi umum.
- Penyediaan tenaga kerja beserta peralatan kerja
-Pengecekan ulang Bill of Quantity gambar tender serta gambar-gambar untuk pekerjaan lain yang
berhubungan dengan pekerjaan ini.
- Pembuatan system monitoring proyek
- Approval Material
- Pembuatan Shop-Drawing
- Mobilisasi dan demobilisasi

FIRE SUPPRESION SYSTEM JAKARTA INTERNATIONAL STADIUM Page 4


2. Pekerjaan Engineering Kontruksi

Sebelum pelaksanaan pekerjaan maka kontraktor akan membuat gambar detail dan gambar connection serta Metode
Instalasi yang digunakan sebagai dasar untuk pelaksanaan dengan cara meneliti kembali kondisi lapangan agar sesuai
rencana. Semua referensi untuk pembuatan detail pelaksanaan pekerjaan harus sesuai dengan standard yang disetujui
pihak PT. WG JAKON PP – KSO
Pekerjaan Engineering Konstruksi meliputi :
- Detail Jadwal Proyek
- Gambar detail, gambar instalasi dan prosedur commissioning
- Laporan Kemajuan Pekerjaan
- Spesifikasi peralatan yang akan dipasang

- Gambar / brosur detail spesifikasi peralatanData/buku/katalog asli/copy dari pabrikan


- Certificate Of Origin dari pabrikan
- Pabrikasi material untuk keperluan pekerjaan perbaikan instalasi
- Dokumentasi teknis termasuk as built drawing dan sertifikasi
- Standar prosedur operasional dalam versi bahasa Indonesia atau bahasa Inggris
- FAT (Factory Acceptance Test)
- Training pengoperasian, maintenance dan trouble shooting

FIRE SUPPRESION SYSTEM JAKARTA INTERNATIONAL STADIUM Page 5


3. Pengadaan Peralatan Utama
Sebelum peralatan utama dipesan kepada principal/pabrik kontraktor akan mengajukan daftar peralatan utama lengkap
dengan brosur/datasheet kepada PT WG JAKON PP - KSO untuk mendapatkan persetujuan terlebih dahulu.
Khusus untuk material bantu dan instalasi yang terdiri dari pipa, fitting dan lainnya kontraktor akan mengajukan
contoh material yang akan dipasang guna mendapatkan persetujuan dari Pengawas Lapangan. Pemesanan material dan
fabrikasi baru dilakukan apabila contoh material telah disetujui. Pada contoh material yang telah disetujui akan
dibubuhkan tanda bukti persetujuan.
Semua alat kerja yang digunakan akan disediakan oleh kontraktor dengan jalan mengirim alat tersebut ke lokasi
proyek, menyewa ataupun pembelian baru.
4. Pelaksanaan Pekerjaan
Semua pelaksanaan pekerjaan akan mengikuti standard dan spesifikasi teknis yang telah ditentukan, serta didasarkan
pada shop drawing yang telah disetujui oleh pihak PT. WG JAKON PP - KSO
Shop Drawing
Pembuatan shop drawing akan dilakukan secara bertahap sesuai dengan urutan pekerjaan dan kebutuhan. Shop
drawing akan dibuat dalam beberapa rangkap sesuai dengan ketentuan.
Penyimpangan-penyimpangan yang terjadi dari shop drawing akibat kondisi lapangan yang tidak memungkinkan akan
dibicarakan terlebih dahulu dengan pihak PT WG JAKON PP - KSO termasuk segi-segi yang berkaitan dengan
pekerjaan lain.
Sistem Monitoring Proyek
Untuk memonitor pelaksanaan proyek dibuat laporan-laporan yang terdiri dari :
1. laporan harian/mingguan tentang kemajuan prestasi pekerjaan
2. dokumentasi / foto pelaksanaan proyek
3. cash flow (keperluan intern kontraktor)
4. laporan performance proyek (keperluan intern kontraktor)

FIRE SUPPRESION SYSTEM JAKARTA INTERNATIONAL STADIUM Page 6


Laporan harian/mingguan akan diserahkan kepada pihak Pengawas Lapangan guna menentukan prestasi
kerja termasuk beberapa laporan lain serta dilaporkan ke kantor pusat kontraktor. Kantor pusat akan
memonitor secara rutin semua perkembangan pekerjaan dan laporan yang masuk.
Metode Kerja :
1. Persiapan Safety di lokasi Kerja
Sebelum dilaksanakan pekerjaan-pekerjaan pemasangan instalasi baru (cabling & piping) sampai dengan
pengetesan harus :
- Ada surat ijin kerja dari pihak PT. WG JAKON PP - KSO untuk lokasi/area yang akan dikerjakan
- Dipasang pagar pengaman/pelindung sekeliling panel, samping kiri-kanan, dan sebelah atas panel
agar pekerja / alat-alat tidak menyentuh peralatan panel yang bisa berakibat trip.
- Pengunaan alat safety diri yang terdiri dari :
Safety Helmet, Safety Shoes, Masker/Aspirator, Vest Body Glow
2. Pekerjaan Instalasi
Guna memudahkan pemasangan dilapangan kontraktor akan membuat pengukuran / marking terlebih
dahulu dilokasi kerja, dari hasil pengukuran disesuaikan dengan Bill of Quantity yang telah ada, bila
sesuai dengan Bill of Quantity dan material telah disetujui, maka kami akan segera pemesanan dan
pengadaan material tersebut untuk pemasangan instalasi.
Bila ada penyimpangan jalur instalasi akan dikoordinasikan terlebih dahulu dengan Pengawas Lapangan
setelah itu baru dituangkan di dalam shop drawing, setelah hasil dari shop drawing dilaksanakan hingga
selesai ditest, langsung dibuatkan as-built drawing sebagai acuan untuk commissioning.
3. Serah Terima Pekerjaan
Setelah Commissioning dan Training kepada pihak PT WG JAKON PP - KSO, maka pihak PT WG
JAKON PP - KSO menandatangani Berita Acara Serah Terima Pertama.

FIRE SUPPRESION SYSTEM JAKARTA INTERNATIONAL STADIUM


Page 7
4. Masa Garansi
Masa garansi adalah 12 (dua belas) bulan sejak tanggal serah terima pertama. Kontraktor
berkewajiban untuk memperbaiki atau mengganti atas biaya sendiri bila peralatan yang
mempunyai garansi dari manufacturer yang ternyata belum sempurna/belum berfungsi dengan
baik.
5. Penutup
Berdasarkan uraian mengenai metode pelaksanaan dalam kaitannya dengan pelaksanaan
pekerjaan ini kami yakin bahwa kami akan dapat melaksanakan pekerjaan ini dengan sebaik-
baiknya sesuai dengan jadwal waktu yang telah ditetapkan.

FIRE SUPPRESION SYSTEM JAKARTA INTERNATIONAL STADIUM Page 8