You are on page 1of 11

 

 
Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija Project

Activity ID Activity Name Original Start Finish 2023 2024 2025


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec JanFeb
752 08-Aug-22
Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija06-Feb-25
Project 02 Crushing
Milestones 752 08-Aug-22 06-Feb-25

Contractor Milestones 752 08-Aug-22 06-Feb-25


Client Milestones 196 10-Jan-24 11-Sep-24 11-Sep-24, Client Milestones
Mobilization 752 08-Aug-22 06-Feb-25
GR-MOB-GEN-1000 Staff Mobilization 27 08-Aug-22 07-Sep-22 Staff Mobilization
GR-MOB-GEN-1011 Site Office Mobilization 27 08-Aug-22 07-Sep-22 Site Office Mobilization
Demobilization 11 26-Jan-25 06-Feb-25
GR-DMB-GEN-1001 Site Demobilization 11 26-Jan-25 06-Feb-25
Project Management Plans 70 08-Sep-22 29-Nov-22 29-Nov-22, Project Management Plans

Engineering 370 08-Sep-22 03-Dec-23 03-Dec-23, Engineering

Topographic Drawings 290 08-Sep-22 30-Aug-23 30-Aug-23, Topographic Drawings


Shop Drawing 358 24-Sep-22 03-Dec-23 03-Dec-23, Shop Drawing
Shop Drawing Submission 346 24-Sep-22 19-Nov-23 19-Nov-23, Shop Drawing Submission
General Landscape Drawings Submission 278 24-Sep-22 30-Aug-23 30-Aug-23, General Landscape Drawings Submission
Grading & Levels Drawings Submission 278 26-Sep-22 02-Sep-23 02-Sep-23, Grading & Levels Drawings Submission
Structural Drawings Submission 48 24-Sep-22 17-Nov-22 17-Nov-22, Structural Drawings Submission
Mechanical Drawings Submission 311 22-Oct-22 06-Nov-23 06-Nov-23, Mechanical Drawings Submission
Electrical Drawings Submission 48 08-Oct-22 01-Dec-22 01-Dec-22, Electrical Drawings Submission
Traffic Management Plans Submission 334 08-Oct-22 19-Nov-23 19-Nov-23, Traffic Management Plans Submission
Demolishing Plan & Existing Trees Removal Plans Submission 287 22-Oct-22 09-Oct-23 09-Oct-23, Demolishing Plan & Existing Trees Removal Plans Submission
Existing Utility Layouts Submission 312 08-Oct-22 24-Oct-23 24-Oct-23, Existing Utility Layouts Submission
Hardscape Layouts Submission 326 08-Oct-22 09-Nov-23 09-Nov-23, Hardscape Layouts Submission
Softscape Layouts Submission 322 08-Oct-22 05-Nov-23 05-Nov-23, Softscape Layouts Submission
Dimensions and coordinates Layouts Submission 278 08-Oct-22 13-Sep-23 13-Sep-23, Dimensions and coordinates Layouts Submission
Trees Coordinates Layouts Submission 318 08-Oct-22 31-Oct-23 31-Oct-23, Trees Coordinates Layouts Submission
Shop Drawing Approval 346 08-Oct-22 03-Dec-23 03-Dec-23, Shop Drawing Approval
General Landscape Drawings Approval 278 08-Oct-22 13-Sep-23 13-Sep-23, General Landscape Drawings Approval
Grading & Levels Drawings Approval 278 10-Oct-22 16-Sep-23 16-Sep-23, Grading & Levels Drawings Approval
Structural Drawings Approval 48 08-Oct-22 01-Dec-22 01-Dec-22, Structural Drawings Approval
Mechanical Drawings Approval 311 05-Nov-22 20-Nov-23 20-Nov-23, Mechanical Drawings Approval
Electrical Drawings Approval 48 22-Oct-22 15-Dec-22 15-Dec-22, Electrical Drawings Approval
Traffic Management Plans Approval 334 22-Oct-22 03-Dec-23 03-Dec-23, Traffic Management Plans Approval
Demolishing Plan & Existing Trees Removal Plans Approval 287 05-Nov-22 23-Oct-23 23-Oct-23, Demolishing Plan & Existing Trees Removal Plans Approval
Existing Utility Layouts Approval 312 22-Oct-22 07-Nov-23 07-Nov-23, Existing Utility Layouts Approval
Hardscape Layouts Approval 326 22-Oct-22 23-Nov-23 23-Nov-23, Hardscape Layouts Approval
Softscape Layouts Approval 322 22-Oct-22 19-Nov-23 19-Nov-23, Softscape Layouts Approval
Dimensions and coordinates Layouts Approval 278 22-Oct-22 28-Sep-23 28-Sep-23, Dimensions and coordinates Layouts Approval
Trees Coordinates Layouts Approval 318 22-Oct-22 14-Nov-23 14-Nov-23, Trees Coordinates Layouts Approval
Method Statement 333 08-Oct-22 18-Nov-23 18-Nov-23, Method Statement
Method Statement Submission 324 08-Oct-22 07-Nov-23 07-Nov-23, Method Statement Submission
GR-ENG-MTH-1000 Submit of Method Statement for Civil Works 24 08-Oct-22 03-Nov-22 Submit of Method Statement for Civil Works
GR-ENG-MTH-1001 Submit of Method Statement for Landscape Works 24 04-Feb-23 02-Mar-23 Submit of Method Statement for Landscape Works
GR-ENG-MTH-1002 Submit of Method Statement forArchitecture Works 24 05-Nov-22 01-Dec-22 Submit of Method Statement forArchitecture Works
GR-ENG-MTH-1003 Submit of Method Statement for Mechanical Works 24 25-Sep-23 23-Oct-23 Submit of Method Statement for Mechanical Works
GR-ENG-MTH-1004 Submit of Method Statement for Electrical Works 24 10-Oct-23 07-Nov-23 Submit of Method Statement for Electrical Works
Method Statement Approval 324 18-Oct-22 18-Nov-23 18-Nov-23, Method StatementApproval
GR-ENG-MTH-1005 Approval of Method Statement for Civil Works 24 18-Oct-22 14-Nov-22 Approval of Method Statement for Civil Works

Actual Level of Effort Remaining Work Milestone    


Actual Work Critical Remaining Work summary
Page 1 of 11 Data Date : 08-Aug-22
 
 
Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija Project

Activity ID Activity Name Original Start Finish 2023 2024 2025


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec JanFeb
GR-ENG-MTH-1006 Approval of Method Statement for Landscape Works 24 14-Feb-23 13-Mar-23 Approval of Method Statement for Landscape Works
GR-ENG-MTH-1007 Approval of Method Statement forArchitecture Works 24 15-Nov-22 12-Dec-22 Approval of Method Statement forArchitecture Works
GR-ENG-MTH-1008 Approval of Method Statement for Mechanical Works 24 05-Oct-23 02-Nov-23 Approval of Method Statement for Mechanical Works
GR-ENG-MTH-1009 Approval of Method Statement for Electrical Works 24 21-Oct-23 18-Nov-23 Approval of Method Statement for Electrical Works
Procurement 541 08-Sep-22 06-Jul-24 06-Jul-24, Procurement

Long Lead Material 532 19-Sep-22 06-Jul-24 06-Jul-24, Long Lead Material
Material Submittal 418 19-Sep-22 07-Feb-24 07-Feb-24, Material Submittal
Mechanical Materials 330 19-Sep-22 28-Oct-23 28-Oct-23, Mechanical Materials
Landscape & Arch. Materials 86 11-Sep-23 21-Dec-23 21-Dec-23, Landscape & Arch. Materials
Electrical Materials 96 18-Oct-23 07-Feb-24 07-Feb-24, Electrical Materials
Material Approval 418 04-Oct-22 21-Feb-24 21-Feb-24, Material Approval
Mechanical Materials 330 04-Oct-22 11-Nov-23 11-Nov-23, Mechanical Materials
Landscape & Arch. Materials 80 03-Oct-23 04-Jan-24 04-Jan-24, Landscape & Arch. Materials
Electrical Materials 96 01-Nov-23 21-Feb-24 21-Feb-24, Electrical Materials
PO Issuance 412 18-Oct-22 28-Feb-24 28-Feb-24, PO Issuance
Mechanical Materials 324 18-Oct-22 18-Nov-23 18-Nov-23, Mechanical Materials
Landscape & Arch. Materials 74 17-Oct-23 11-Jan-24 11-Jan-24, Landscape & Arch. Materials
Electrical Materials 36 17-Jan-24 28-Feb-24 28-Feb-24, Electrical Materials
Material Delivery 502 25-Oct-22 06-Jul-24 06-Jul-24, Material Delivery
Mechanical Materials 438 25-Oct-22 17-Apr-24 17-Apr-24, Mechanical Materials
Landscape & Arch. Materials 140 24-Oct-23 11-Apr-24 11-Apr-24, Landscape & Arch. Materials
Electrical Materials 126 24-Jan-24 06-Jul-24 06-Jul-24, Electrical Materials
Bulk Material 469 08-Sep-22 01-Apr-24 01-Apr-24, Bulk Material
Material Submittal 403 08-Sep-22 10-Jan-24 10-Jan-24, Material Submittal
Mechanical Materials 327 08-Sep-22 14-Oct-23 14-Oct-23, Mechanical Materials
Landscape & Arch. Materials 168 05-Nov-22 31-May-23 31-May-23, Landscape & Arch. Materials
Electrical Materials 18 20-Dec-23 10-Jan-24 10-Jan-24, Electrical Materials
Material Approval 403 24-Sep-22 24-Jan-24 24-Jan-24, Material Approval
Mechanical Materials 327 24-Sep-22 28-Oct-23 28-Oct-23, Mechanical Materials
Landscape & Arch. Materials 165 22-Nov-22 14-Jun-23 14-Jun-23, Landscape & Arch. Materials
Electrical Materials 21 31-Dec-23 24-Jan-24 24-Jan-24, Electrical Materials
PO Issuance 397 08-Oct-22 31-Jan-24 31-Jan-24, PO Issuance
Mechanical Materials 321 08-Oct-22 04-Nov-23 04-Nov-23, Mechanical Materials
Landscape & Arch. Materials 159 06-Dec-22 21-Jun-23 21-Jun-23, Landscape & Arch. Materials
Electrical Materials 15 14-Jan-24 31-Jan-24 31-Jan-24, Electrical Materials
Material Delivery 439 15-Oct-22 01-Apr-24 01-Apr-24, Material Delivery
Mechanical Materials 339 15-Oct-22 02-Dec-23 02-Dec-23, Mechanical Materials
Landscape & Arch. Materials 333 13-Dec-22 23-Jan-24 23-Jan-24, Landscape & Arch. Materials
Electrical Materials 57 21-Jan-24 01-Apr-24 01-Apr-24, Electrical Materials
Permit / Authority Approval 510 08-Oct-22 27-Jun-24 27-Jun-24, Permit /Authority Approval

Sector 1 406 08-Oct-22 11-Feb-24 11-Feb-24, Sector 1


Sector 2 498 22-Oct-22 27-Jun-24 27-Jun-24, Sector 2
Sector 3 401 16-Jan-23 27-May-24 27-May-24, Sector 3
Construction 425 18-Jul-23 14-Dec-24 14-Dec-24, Construction

Sector 1 380 18-Jul-23 22-Oct-24 22-Oct-24, Sector 1


Irrigation Network System and Tank 355 24-Jul-23 29-Sep-24 29-Sep-24, Irrigation Network System and Tank
Irrigation Tank - PS 01 355 24-Jul-23 29-Sep-24 29-Sep-24, Irrigation Tank - PS 01
Irrigation Network Works 271 16-Oct-23 12-Sep-24 12-Sep-24, Irrigation Network Works
Zone 08 313 18-Jul-23 04-Aug-24 04-Aug-24, Zone 08
Future Neighborhood Park FNP-22 274 18-Jul-23 15-Jun-24 15-Jun-24, Future Neighborhood Park FNP-22

Actual Level of Effort Remaining Work Milestone    


Actual Work Critical Remaining Work summary
Page 2 of 11 Data Date : 08-Aug-22
 
 
Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija Project

Activity ID Activity Name Original Start Finish 2023 2024 2025


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec JanFeb
Future Neighborhood Park FNP-02 263 24-Jul-23 08-Jun-24 08-Jun-24, Future Neighborhood Park FNP-02
Mosque M-38 288 29-Jul-23 16-Jul-24 16-Jul-24, Mosque M-38
Mosque M-04 284 02-Aug-23 16-Jul-24 16-Jul-24, Mosque M-04
Parking P-48 247 05-Aug-23 01-Jun-24 01-Jun-24, Parking P-48
Street SS-113 268 12-Aug-23 07-Jul-24 07-Jul-24, Street SS-113
Street SS-02 259 19-Sep-23 04-Aug-24 04-Aug-24, Street SS-02
Street SS-85 226 01-Oct-23 07-Jul-24 07-Jul-24, Street SS-85
Street SS-86 217 11-Oct-23 07-Jul-24 07-Jul-24, Street SS-86
Street SS-96 193 08-Nov-23 07-Jul-24 07-Jul-24, Street SS-96
Zone 04 345 10-Aug-23 05-Oct-24 05-Oct-24, Zone 04
Future Neighborhood Park FNP-06 242 10-Aug-23 01-Jun-24 01-Jun-24, Future Neighborhood Park FNP-06
Future Neighborhood Park FNP-07 237 19-Aug-23 03-Jun-24 03-Jun-24, Future Neighborhood Park FNP-07
Mosque M-11 256 28-Aug-23 09-Jul-24 09-Jul-24, Mosque M-11
Mosque M-12 249 05-Sep-23 09-Jul-24 09-Jul-24, Mosque M-12
Parking P-28 212 07-Sep-23 25-May-24 25-May-24, Parking P-28
Parking P-29 208 12-Sep-23 25-May-24 25-May-24, Parking P-29
Parking P-30 204 17-Sep-23 25-May-24 25-May-24, Parking P-30
Street SS-102 225 25-Sep-23 30-Jun-24 30-Jun-24, Street SS-102
Street SS-104 221 30-Sep-23 30-Jun-24 30-Jun-24, Street SS-104
Street SS-12 241 04-Oct-23 28-Jul-24 28-Jul-24, Street SS-12
Street SS-44 211 11-Oct-23 30-Jun-24 30-Jun-24, Street SS-44
Street SS-46 207 16-Oct-23 30-Jun-24 30-Jun-24, Street SS-46
Street SS-49 203 21-Oct-23 30-Jun-24 30-Jun-24, Street SS-49
Street SS-05.1 223 25-Oct-23 28-Jul-24 28-Jul-24, Street SS-05.1
Street SS-90 193 01-Nov-23 30-Jun-24 30-Jun-24, Street SS-90
Toilet - 03 271 06-Nov-23 05-Oct-24 05-Oct-24, Toilet - 03
Zone 07 355 14-Aug-23 20-Oct-24 20-Oct-24, Zone 07
Future Neighborhood Park FNP-01a 208 15-Aug-23 27-Apr-24 27-Apr-24, Future Neighborhood Park FNP-01a
Mosque M-01a 233 20-Aug-23 30-May-24 30-May-24, Mosque M-01a
Mosque M-02a 229 24-Aug-23 30-May-24 30-May-24, Mosque M-02a
Mosque M-03 225 29-Aug-23 30-May-24 30-May-24, Mosque M-03
Parking P-15 186 03-Sep-23 20-Apr-24 20-Apr-24, Parking P-15
Street SS-01 209 07-Sep-23 21-May-24 21-May-24, Street SS-01
Street SS-39 205 12-Sep-23 21-May-24 21-May-24, Street SS-39
Street SS-04 225 17-Sep-23 18-Jun-24 18-Jun-24, Street SS-04
Street SS-40 195 25-Sep-23 21-May-24 21-May-24, Street SS-40
Street SS-42 230 14-Aug-23 21-May-24 21-May-24, Street SS-42
Street SS-05 245 24-Aug-23 18-Jun-24 18-Jun-24, Street SS-05
Street SS-78 212 04-Sep-23 21-May-24 21-May-24, Street SS-78
Street SS-79 203 14-Sep-23 21-May-24 21-May-24, Street SS-79
Street SS-81 193 27-Sep-23 21-May-24 21-May-24, Street SS-81
Street SS-82 183 09-Oct-23 21-May-24 21-May-24, Street SS-82
Street SS-83 178 15-Oct-23 21-May-24 21-May-24, Street SS-83
Street SS-84 173 21-Oct-23 21-May-24 21-May-24, Street SS-84
School S-01a 164 26-Oct-23 16-May-24 16-May-24, School S-01a
Toilet - 01 288 01-Nov-23 20-Oct-24 20-Oct-24, Toilet - 01
Zone 01 317 12-Sep-23 05-Oct-24 05-Oct-24, Zone 01
Future Neighborhood Park FNP-01 248 12-Sep-23 15-Jul-24 15-Jul-24, Future Neighborhood Park FNP-01
Mosque M-01 241 16-Sep-23 10-Jul-24 10-Jul-24, Mosque M-01
Mosque M-02 276 19-Sep-23 24-Aug-24 24-Aug-24, Mosque M-02
Parking P-01 237 25-Sep-23 14-Jul-24 14-Jul-24, Parking P-01
Parking P-11 235 27-Sep-23 14-Jul-24 14-Jul-24, Parking P-11

Actual Level of Effort Remaining Work Milestone    


Actual Work Critical Remaining Work summary
Page 3 of 11 Data Date : 08-Aug-22
 
 
Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija Project

Activity ID Activity Name Original Start Finish 2023 2024 2025


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec JanFeb
Parking P-12 231 02-Oct-23 14-Jul-24 14-Jul-24, Parking P-12
Parking P-02 227 07-Oct-23 14-Jul-24 14-Jul-24, Parking P-02
Street SS-02 271 14-Oct-23 10-Sep-24 10-Sep-24, Street SS-02
Street SS-27 285 21-Oct-23 05-Oct-24 05-Oct-24, Street SS-27
Street SS-71 247 30-Oct-23 29-Aug-24 29-Aug-24, Street SS-71
Street SS-90 230 04-Nov-23 14-Aug-24 14-Aug-24, Street SS-90
Street SS-92 226 08-Nov-23 14-Aug-24 14-Aug-24, Street SS-92
Street SS-93 222 13-Nov-23 14-Aug-24 14-Aug-24, Street SS-93
Street SS-94 218 18-Nov-23 14-Aug-24 14-Aug-24, Street SS-94
School S-01 194 11-Dec-23 10-Aug-24 10-Aug-24, School S-01
Zone 05 249 16-Sep-23 20-Jul-24 20-Jul-24, Zone 05
Future Neighborhood Park FNP-08 164 16-Sep-23 31-Mar-24 31-Mar-24, Future Neighborhood Park FNP-08
Mosque M-13 189 20-Sep-23 11-May-24 11-May-24, Mosque M-13
Street SS-12.1 177 26-Sep-23 01-May-24 01-May-24, Street SS-12.1
Street SS-14 173 01-Oct-23 01-May-24 01-May-24, Street SS-14
Street SS-15 233 05-Oct-23 20-Jul-24 20-Jul-24, Street SS-15
School S-04 99 21-Dec-23 27-Apr-24 27-Apr-24, School S-04
School S-05 94 27-Dec-23 27-Apr-24 27-Apr-24, School S-05
Zone 03 276 20-Sep-23 25-Aug-24 25-Aug-24, Zone 03
Future Neighborhood Park FNP-34 212 20-Sep-23 06-Jun-24 06-Jun-24, Future Neighborhood Park FNP-34
Mosque M-04 237 26-Sep-23 15-Jul-24 15-Jul-24, Mosque M-04
Mosque M-05 233 01-Oct-23 15-Jul-24 15-Jul-24, Mosque M-05
Parking P-28 194 05-Oct-23 30-May-24 30-May-24, Parking P-28
Parking P-03 190 10-Oct-23 30-May-24 30-May-24, Parking P-03
Parking P-05 186 15-Oct-23 30-May-24 30-May-24, Parking P-05
Parking P-06 182 19-Oct-23 30-May-24 30-May-24, Parking P-06
Street SS-25 248 24-Oct-23 25-Aug-24 25-Aug-24, Street SS-25
Street SS-33 197 02-Nov-23 06-Jul-24 06-Jul-24, Street SS-33
Street SS-34 193 07-Nov-23 06-Jul-24 06-Jul-24, Street SS-34
Street SS-04 213 12-Nov-23 03-Aug-24 03-Aug-24, Street SS-04
Street SS-05 207 19-Nov-23 03-Aug-24 03-Aug-24, Street SS-05
School S-04 173 26-Nov-23 01-Jul-24 01-Jul-24, School S-04
Zone 06 321 26-Sep-23 22-Oct-24 22-Oct-24, Zone 06
Future Neighborhood Park FNP-09 252 26-Sep-23 01-Aug-24 01-Aug-24, Future Neighborhood Park FNP-09
Mosque M-14 277 01-Oct-23 04-Sep-24 04-Sep-24, Mosque M-14
Mosque M-15 273 05-Oct-23 04-Sep-24 04-Sep-24, Mosque M-15
Parking P-18 234 10-Oct-23 25-Jul-24 25-Jul-24, Parking P-18
Parking P-34 230 15-Oct-23 25-Jul-24 25-Jul-24, Parking P-34
Street SS-109 253 19-Oct-23 26-Aug-24 26-Aug-24, Street SS-109
Street SS-110 245 29-Oct-23 26-Aug-24 26-Aug-24, Street SS-110
Street SS-111 236 08-Nov-23 26-Aug-24 26-Aug-24, Street SS-111
Street SS-14.1 227 19-Nov-23 26-Aug-24 26-Aug-24, Street SS-14.1
Street SS-25 260 06-Dec-23 22-Oct-24 22-Oct-24, Street SS-25
Street SS-54 203 17-Dec-23 26-Aug-24 26-Aug-24, Street SS-54
School S-06 175 14-Jan-24 21-Aug-24 21-Aug-24, School S-06
Existing Neighborhood Park ENP-07 141 11-Feb-24 10-Aug-24 10-Aug-24, Existing Neighborhood Park ENP-07
Zone 02 208 19-Oct-23 04-Jul-24 04-Jul-24, Zone 02
Mosque M-03 193 19-Oct-23 12-Jun-24 12-Jun-24, Mosque M-03
Parking P-25 156 22-Oct-23 02-May-24 02-May-24, Parking P-25
Parking P-26 152 26-Oct-23 02-May-24 02-May-24, Parking P-26
Parking P-27 148 31-Oct-23 02-May-24 02-May-24, Parking P-27
Street SS-03 192 07-Nov-23 04-Jul-24 04-Jul-24, Street SS-03

Actual Level of Effort Remaining Work Milestone    


Actual Work Critical Remaining Work summary
Page 4 of 11 Data Date : 08-Aug-22
 
 
Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija Project

Activity ID Activity Name Original Start Finish 2023 2024 2025


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec JanFeb
Street SS-30.1 163 14-Nov-23 03-Jun-24 03-Jun-24, Street SS-30.1
School S-02 127 21-Dec-23 29-May-24 29-May-24, School S-02
School S-03 122 27-Dec-23 29-May-24 29-May-24, School S-03
Sector 2 420 24-Jul-23 14-Dec-24 14-Dec-24, Sector 2
Irrigation Network System and Tank 315 29-Jul-23 17-Aug-24 17-Aug-24, Irrigation Network System and Tank
Irrigation Tank - PS 02 315 29-Jul-23 17-Aug-24 17-Aug-24, Irrigation Tank - PS 02
Irrigation Network Works 215 12-Nov-23 05-Aug-24 05-Aug-24, Irrigation Network Works
Zone 10 420 24-Jul-23 14-Dec-24 14-Dec-24, Zone 10
Future Neighborhood Park FNP-05 374 24-Jul-23 21-Oct-24 21-Oct-24, Future Neighborhood Park FNP-05
Future Neighborhood Park FNP-33 371 29-Jul-23 22-Oct-24 22-Oct-24, Future Neighborhood Park FNP-33
Future Neighborhood Park FNP-22 373 02-Aug-23 29-Oct-24 29-Oct-24, Future Neighborhood Park FNP-22
Mosque M-10 337 11-Oct-23 25-Nov-24 25-Nov-24, Mosque M-10
Mosque M-12 300 23-Nov-23 25-Nov-24 25-Nov-24, Mosque M-12
Mosque M-06 295 29-Nov-23 25-Nov-24 25-Nov-24, Mosque M-06
Parking P-18 214 22-Jan-24 15-Oct-24 15-Oct-24, Parking P-18
Parking P-31 210 27-Jan-24 15-Oct-24 15-Oct-24, Parking P-31
Parking P-14 191 18-Feb-24 15-Oct-24 15-Oct-24, Parking P-14
Parking P-22 187 22-Feb-24 15-Oct-24 15-Oct-24, Parking P-22
Parking P-24 181 29-Feb-24 15-Oct-24 15-Oct-24, Parking P-24
Street SS-09 230 03-Mar-24 14-Dec-24 14-Dec-24, Street SS-09
Street SS-39 196 16-Mar-24 16-Nov-24 16-Nov-24, Street SS-39
Street SS-68 192 21-Mar-24 16-Nov-24 16-Nov-24, Street SS-68
Street SS-72 188 27-Mar-24 16-Nov-24 16-Nov-24, Street SS-72
Street SS-73 184 03-Apr-24 16-Nov-24 16-Nov-24, Street SS-73
Street SS-75 180 09-Apr-24 16-Nov-24 16-Nov-24, Street SS-75
Street SS-76 176 20-Apr-24 16-Nov-24 16-Nov-24, Street SS-76
Street SS-77 172 24-Apr-24 16-Nov-24 16-Nov-24, Street SS-77
Street SS-87 168 29-Apr-24 16-Nov-24 16-Nov-24, Street SS-87
Existing Neighborhood Park ENP-01 137 29-Apr-24 10-Oct-24 10-Oct-24, Existing Neighborhood Park ENP-01
Zone 14 396 29-Jul-23 20-Nov-24 20-Nov-24, Zone 14
Future Neighborhood Park FNP-04 297 29-Jul-23 27-Jul-24 27-Jul-24, Future Neighborhood Park FNP-04
Future Neighborhood Park FNP-11 180 05-Aug-23 03-Mar-24 03-Mar-24, Future Neighborhood Park FNP-11
Mosque M-23 193 10-Aug-23 27-Mar-24 27-Mar-24, Mosque M-23
Mosque M-24 189 15-Aug-23 27-Mar-24 27-Mar-24, Mosque M-24
Mosque M-08 185 20-Aug-23 27-Mar-24 27-Mar-24, Mosque M-08
Parking P-24 148 22-Aug-23 12-Feb-24 12-Feb-24, Parking P-24
Parking P-05 144 27-Aug-23 12-Feb-24 12-Feb-24, Parking P-05
Parking P-36 140 31-Aug-23 12-Feb-24 12-Feb-24, Parking P-36
Parking P-42 136 05-Sep-23 12-Feb-24 12-Feb-24, Parking P-42
Parking P-43 132 10-Sep-23 12-Feb-24 12-Feb-24, Parking P-43
Street SS-19.1 177 17-Sep-23 23-Apr-24 23-Apr-24, Street SS-19.1
Street SS-32 147 25-Sep-23 14-Mar-24 14-Mar-24, Street SS-32
Street SS-33 143 30-Sep-23 14-Mar-24 14-Mar-24, Street SS-33
Street SS-61 139 04-Oct-23 14-Mar-24 14-Mar-24, Street SS-61
Street SS-62 135 09-Oct-23 14-Mar-24 14-Mar-24, Street SS-62
Street SS-89 131 14-Oct-23 14-Mar-24 14-Mar-24, Street SS-89
Street SS-93 122 24-Oct-23 14-Mar-24 14-Mar-24, Street SS-93
School S-12 94 21-Nov-23 10-Mar-24 10-Mar-24, School S-12
Toilet - 02 293 27-Nov-23 20-Nov-24 20-Nov-24, Toilet - 02
Zone 09 364 05-Aug-23 21-Oct-24 21-Oct-24, Zone 09
Future Neighborhood Park FNP-11B 321 05-Aug-23 31-Aug-24 31-Aug-24, Future Neighborhood Park FNP-11B
Future Neighborhood Park FNP-23 297 02-Sep-23 31-Aug-24 31-Aug-24, Future Neighborhood Park FNP-23

Actual Level of Effort Remaining Work Milestone    


Actual Work Critical Remaining Work summary
Page 5 of 11 Data Date : 08-Aug-22
 
 
Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija Project

Activity ID Activity Name Original Start Finish 2023 2024 2025


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec JanFeb
Mosque M-11 299 02-Oct-23 02-Oct-24 02-Oct-24, Mosque M-11
Mosque M-07 275 30-Oct-23 02-Oct-24 02-Oct-24, Mosque M-07
Parking P-23 263 03-Oct-23 21-Aug-24 21-Aug-24, Parking P-23
Parking P-07 254 14-Oct-23 21-Aug-24 21-Aug-24, Parking P-07
Parking P-08 245 24-Oct-23 21-Aug-24 21-Aug-24, Parking P-08
Street SS-41 246 23-Nov-23 22-Sep-24 22-Sep-24, Street SS-41
Street SS-46 222 21-Dec-23 22-Sep-24 22-Sep-24, Street SS-46
Street SS-74 198 18-Jan-24 22-Sep-24 22-Sep-24, Street SS-74
Street SS-04.1 218 23-Jan-24 21-Oct-24 21-Oct-24, Street SS-04.1
Street SS-43.1 190 28-Jan-24 22-Sep-24 22-Sep-24, Street SS-43.1
Street SS-45 170 20-Feb-24 22-Sep-24 22-Sep-24, Street SS-45
Street SS-50 166 25-Feb-24 22-Sep-24 22-Sep-24, Street SS-50
Street SS-07 146 21-Mar-24 22-Sep-24 22-Sep-24, Street SS-07
Street SS-78 142 27-Mar-24 22-Sep-24 22-Sep-24, Street SS-78
Street SS-79 122 29-Apr-24 22-Sep-24 22-Sep-24, Street SS-79
School S-05 94 27-May-24 17-Sep-24 17-Sep-24, School S-05
Zone 12 320 24-Oct-23 18-Nov-24 18-Nov-24, Zone 12
Future Neighborhood Park FNP-10 275 24-Oct-23 26-Sep-24 26-Sep-24, Future Neighborhood Park FNP-10
Future Neighborhood Park FNP-20 271 29-Oct-23 26-Sep-24 26-Sep-24, Future Neighborhood Park FNP-20
Mosque M-18 296 02-Nov-23 30-Oct-24 30-Oct-24, Mosque M-18
Mosque M-19 292 07-Nov-23 30-Oct-24 30-Oct-24, Mosque M-19
Mosque M-06 288 12-Nov-23 30-Oct-24 30-Oct-24, Mosque M-06
Mosque M-20 284 16-Nov-23 30-Oct-24 30-Oct-24, Mosque M-20
Parking P-04 247 19-Nov-23 18-Sep-24 18-Sep-24, Parking P-04
Parking P-44 243 23-Nov-23 18-Sep-24 18-Sep-24, Parking P-44
Parking P-50 239 28-Nov-23 18-Sep-24 18-Sep-24, Parking P-50
Street SS-18 246 21-Dec-23 21-Oct-24 21-Oct-24, Street SS-18
Street SS-34 237 01-Jan-24 21-Oct-24 21-Oct-24, Street SS-34
Street SS-55 232 07-Jan-24 21-Oct-24 21-Oct-24, Street SS-55
Street SS-56 223 17-Jan-24 21-Oct-24 21-Oct-24, Street SS-56
Street SS-58 219 22-Jan-24 21-Oct-24 21-Oct-24, Street SS-58
Street SS-07 215 27-Jan-24 21-Oct-24 21-Oct-24, Street SS-07
Street SS-07.1 235 31-Jan-24 18-Nov-24 18-Nov-24, Street SS-07.1
School S-08 94 29-Jun-24 16-Oct-24 16-Oct-24, School S-08
Zone 13 314 07-Nov-23 25-Nov-24 25-Nov-24, Zone 13
Mosque M-21 235 07-Nov-23 24-Aug-24 24-Aug-24, Mosque M-21
Parking P-21 196 12-Nov-23 14-Jul-24 14-Jul-24, Parking P-21
Parking P-25 167 16-Dec-23 14-Jul-24 14-Jul-24, Parking P-25
Parking P-35 145 10-Jan-24 14-Jul-24 14-Jul-24, Parking P-35
Street SS-18.1 146 10-Feb-24 14-Aug-24 14-Aug-24, Street SS-18.1
Street SS-19 165 15-Feb-24 11-Sep-24 11-Sep-24, Street SS-19
Street SS-08 159 22-Feb-24 11-Sep-24 11-Sep-24, Street SS-08
Street SS-08.1 153 29-Feb-24 11-Sep-24 11-Sep-24, Street SS-08.1
School S-10 119 07-Mar-24 10-Aug-24 10-Aug-24, School S-10
School S-09 113 14-Mar-24 10-Aug-24 10-Aug-24, School S-09
Zone 11 288 07-Dec-23 25-Nov-24 25-Nov-24, Zone 11
Sector 3 368 07-Sep-23 28-Nov-24 28-Nov-24, Sector 3
Irrigation Network System 113 07-Dec-23 29-Apr-24 29-Apr-24, Irrigation Network System
Piping Works 105 07-Dec-23 20-Apr-24 20-Apr-24, Piping Works
Pipe Works Specialties 91 02-Jan-24 29-Apr-24 29-Apr-24, Pipe Works Specialties
Zone 19 349 07-Sep-23 06-Nov-24 06-Nov-24, Zone 19
Future Neighborhood Park FNP-17 289 07-Sep-23 27-Aug-24 27-Aug-24, Future Neighborhood Park FNP-17

Actual Level of Effort Remaining Work Milestone    


Actual Work Critical Remaining Work summary
Page 6 of 11 Data Date : 08-Aug-22
 
 
Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija Project

Activity ID Activity Name Original Start Finish 2023 2024 2025


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec JanFeb
Future Neighborhood Park FNP-18 253 13-Nov-23 19-Sep-24 19-Sep-24, Future Neighborhood Park FNP-18
Future Neighborhood Park FNP-19 210 17-Jan-24 06-Oct-24 06-Oct-24, Future Neighborhood Park FNP-19
Mosque M-31 186 10-Feb-24 01-Oct-24 01-Oct-24, Mosque M-31
Parking P-20 149 12-Feb-24 20-Aug-24 20-Aug-24, Parking P-20
Parking P-37 145 17-Feb-24 20-Aug-24 20-Aug-24, Parking P-37
Street SS-20.2 166 24-Feb-24 21-Sep-24 21-Sep-24, Street SS-20.2
Street SS-27 201 28-Feb-24 06-Nov-24 06-Nov-24, Street SS-27
Street SS-74 154 09-Mar-24 21-Sep-24 21-Sep-24, Street SS-74
Street SS-75 150 13-Mar-24 21-Sep-24 21-Sep-24, Street SS-75
Street SS-76 146 19-Mar-24 21-Sep-24 21-Sep-24, Street SS-76
Existing Neighborhood Park ENP-04 111 26-Mar-24 15-Aug-24 15-Aug-24, Existing Neighborhood Park ENP-04
Zone 17 190 12-Nov-23 07-Jul-24 07-Jul-24, Zone 17
Future Neighborhood Park FNP-15 145 12-Nov-23 11-May-24 11-May-24, Future Neighborhood Park FNP-15
Mosque M-27 170 16-Nov-23 13-Jun-24 13-Jun-24, Mosque M-27
Parking P-11 133 19-Nov-23 04-May-24 04-May-24, Parking P-11
Parking P-40 129 23-Nov-23 04-May-24 04-May-24, Parking P-40
Parking P-9 109 17-Dec-23 04-May-24 04-May-24, Parking P-9
Street SS-11.1 153 25-Dec-23 07-Jul-24 07-Jul-24, Street SS-11.1
Street SS-19.3 123 01-Jan-24 04-Jun-24 04-Jun-24, Street SS-19.3
Street SS-20 114 11-Jan-24 04-Jun-24 04-Jun-24, Street SS-20
Street SS-21 109 17-Jan-24 04-Jun-24 04-Jun-24, Street SS-21
School S-15 100 23-Jan-24 30-May-24 30-May-24, School S-15
School S-16 95 29-Jan-24 30-May-24 30-May-24, School S-16
Zone 18 196 16-Nov-23 18-Jul-24 18-Jul-24, Zone 18
Future Neighborhood Park FNP-16 167 16-Nov-23 10-Jun-24 10-Jun-24, Future Neighborhood Park FNP-16
Future Neighborhood Park FNP-23 163 21-Nov-23 10-Jun-24 10-Jun-24, Future Neighborhood Park FNP-23
Mosque M-30 188 26-Nov-23 18-Jul-24 18-Jul-24, Mosque M-30
Parking P-12 151 28-Nov-23 03-Jun-24 03-Jun-24, Parking P-12
Parking P-13 135 17-Dec-23 03-Jun-24 03-Jun-24, Parking P-13
Parking P-14 111 14-Jan-24 03-Jun-24 03-Jun-24, Parking P-14
Street SS-20.1 131 22-Jan-24 09-Jul-24 09-Jul-24, Street SS-20.1
Street SS-69 126 28-Jan-24 09-Jul-24 09-Jul-24, Street SS-69
Street SS-71 116 08-Feb-24 09-Jul-24 09-Jul-24, Street SS-71
Street SS-97 111 14-Feb-24 09-Jul-24 09-Jul-24, Street SS-97
Street SS-98 107 19-Feb-24 09-Jul-24 09-Jul-24, Street SS-98
Street SS-99 103 24-Feb-24 09-Jul-24 09-Jul-24, Street SS-99
School S-17 95 28-Feb-24 04-Jul-24 04-Jul-24, School S-17
Zone 20 305 21-Nov-23 28-Nov-24 28-Nov-24, Zone 20
Future Neighborhood Park FNP-31 238 21-Nov-23 10-Sep-24 10-Sep-24, Future Neighborhood Park FNP-31
Future Neighborhood Park FNP-26 234 26-Nov-23 10-Sep-24 10-Sep-24, Future Neighborhood Park FNP-26
Future Neighborhood Park FNP-32 243 30-Nov-23 26-Sep-24 26-Sep-24, Future Neighborhood Park FNP-32
Mosque M-22 255 05-Dec-23 15-Oct-24 15-Oct-24, Mosque M-22
Mosque M-24 251 10-Dec-23 15-Oct-24 15-Oct-24, Mosque M-24
Mosque M-25 247 14-Dec-23 15-Oct-24 15-Oct-24, Mosque M-25
Mosque M-26 243 19-Dec-23 15-Oct-24 15-Oct-24, Mosque M-26
Mosque M-28 239 24-Dec-23 15-Oct-24 15-Oct-24, Mosque M-28
Mosque M-29 261 28-Nov-23 15-Oct-24 15-Oct-24, Mosque M-29
Parking P-16 213 13-Dec-23 03-Sep-24 03-Sep-24, Parking P-16
Parking P-21 207 20-Dec-23 03-Sep-24 03-Sep-24, Parking P-21
Parking P-29 219 06-Dec-23 03-Sep-24 03-Sep-24, Parking P-29
Street SS-18 226 30-Dec-23 06-Oct-24 06-Oct-24, Street SS-18
Street SS-19 221 04-Jan-24 06-Oct-24 06-Oct-24, Street SS-19

Actual Level of Effort Remaining Work Milestone    


Actual Work Critical Remaining Work summary
Page 7 of 11 Data Date : 08-Aug-22
 
 
Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija Project

Activity ID Activity Name Original Start Finish 2023 2024 2025


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec JanFeb
Street SS-26 237 01-Feb-24 21-Nov-24 21-Nov-24, Street SS-26
Street SS-63 145 09-Apr-24 06-Oct-24 06-Oct-24, Street SS-63
Street SS-65 134 28-Apr-24 06-Oct-24 06-Oct-24, Street SS-65
Street SS-16 175 04-May-24 28-Nov-24 28-Nov-24, Street SS-16
Street SS-67 130 02-May-24 06-Oct-24 06-Oct-24, Street SS-67
Street SS-84 126 07-May-24 06-Oct-24 06-Oct-24, Street SS-84
Street SS-85 122 12-May-24 06-Oct-24 06-Oct-24, Street SS-85
Zone 16 278 03-Dec-23 09-Nov-24 09-Nov-24, Zone 16
Future Neighborhood Park FNP-24 233 03-Dec-23 16-Sep-24 16-Sep-24, Future Neighborhood Park FNP-24
Mosque M-25 258 07-Dec-23 21-Oct-24 21-Oct-24, Mosque M-25
Mosque M-26 254 12-Dec-23 21-Oct-24 21-Oct-24, Mosque M-26
Mosque M-37 250 17-Dec-23 21-Oct-24 21-Oct-24, Mosque M-37
Parking P-22 213 19-Dec-23 09-Sep-24 09-Sep-24, Parking P-22
Parking P-23 209 24-Dec-23 09-Sep-24 09-Sep-24, Parking P-23
Parking P-39 205 28-Dec-23 09-Sep-24 09-Sep-24, Parking P-39
Parking P-41 201 02-Jan-24 09-Sep-24 09-Sep-24, Parking P-41
Parking P-06 197 07-Jan-24 09-Sep-24 09-Sep-24, Parking P-06
Parking P-08 176 31-Jan-24 09-Sep-24 09-Sep-24, Parking P-08
Street SS-19.2 221 07-Feb-24 09-Nov-24 09-Nov-24, Street SS-19.2
Street SS-28 191 14-Feb-24 12-Oct-24 12-Oct-24, Street SS-28
Street SS-30 187 19-Feb-24 12-Oct-24 12-Oct-24, Street SS-30
Street SS-63 183 24-Feb-24 12-Oct-24 12-Oct-24, Street SS-63
Street SS-65 161 23-Mar-24 12-Oct-24 12-Oct-24, Street SS-65
Street SS-66 157 28-Mar-24 12-Oct-24 12-Oct-24, Street SS-66
Street SS-67 153 04-Apr-24 12-Oct-24 12-Oct-24, Street SS-67
Street SS-68 149 10-Apr-24 12-Oct-24 12-Oct-24, Street SS-68
Street SS-09 169 20-Apr-24 09-Nov-24 09-Nov-24, Street SS-09
Street SS-09.1 163 27-Apr-24 09-Nov-24 09-Nov-24, Street SS-09.1
School S-14 113 22-May-24 07-Oct-24 07-Oct-24, School S-14
Existing Neighborhood Park ENP-03 81 28-May-24 04-Sep-24 04-Sep-24, Existing Neighborhood Park ENP-03
Zone 15 276 14-Dec-23 18-Nov-24 18-Nov-24, Zone 15
Future Neighborhood Park FNP-25 181 14-Dec-23 29-Jul-24 29-Jul-24, Future Neighborhood Park FNP-25
Mosque M-13 189 21-Dec-23 14-Aug-24 14-Aug-24, Mosque M-13
Mosque M-18 185 26-Dec-23 14-Aug-24 14-Aug-24, Mosque M-18
Mosque M-20 181 31-Dec-23 14-Aug-24 14-Aug-24, Mosque M-20
Mosque M-21 177 04-Jan-24 14-Aug-24 14-Aug-24, Mosque M-21
Parking P-30 138 09-Jan-24 04-Jul-24 04-Jul-24, Parking P-30
Parking P-17 134 14-Jan-24 04-Jul-24 04-Jul-24, Parking P-17
Parking P-20 130 18-Jan-24 04-Jul-24 04-Jul-24, Parking P-20
Parking P-09 126 23-Jan-24 04-Jul-24 04-Jul-24, Parking P-09
Street SS-11 149 28-Jan-24 05-Aug-24 05-Aug-24, Street SS-11
Street SS-15 234 01-Feb-24 18-Nov-24 18-Nov-24, Street SS-15
Street SS-50.1 139 08-Feb-24 05-Aug-24 05-Aug-24, Street SS-50.1
Street SS-54 135 13-Feb-24 05-Aug-24 05-Aug-24, Street SS-54
Street SS-55 131 18-Feb-24 05-Aug-24 05-Aug-24, Street SS-55
Street SS-56 127 22-Feb-24 05-Aug-24 05-Aug-24, Street SS-56
Street SS-57 123 27-Feb-24 05-Aug-24 05-Aug-24, Street SS-57
Street SS-58 119 03-Mar-24 05-Aug-24 05-Aug-24, Street SS-58
Street SS-80 115 07-Mar-24 05-Aug-24 05-Aug-24, Street SS-80
Street SS-81 111 12-Mar-24 05-Aug-24 05-Aug-24, Street SS-81
Street SS-82 107 18-Mar-24 05-Aug-24 05-Aug-24, Street SS-82
Street SS-83 103 24-Mar-24 05-Aug-24 05-Aug-24, Street SS-83

Actual Level of Effort Remaining Work Milestone    


Actual Work Critical Remaining Work summary
Page 8 of 11 Data Date : 08-Aug-22
 
 
Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija Project

Activity ID Activity Name Original Start Finish 2023 2024 2025


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec JanFeb
School S-06 95 31-Mar-24 31-Jul-24 31-Jul-24, School S-06
Toilet - 05 250 26-Dec-23 30-Oct-24 30-Oct-24, Toilet - 05
Health H-02 145 01-Jan-24 04-Jul-24 04-Jul-24, Health H-02
Existing Neighborhood Park ENP-04 144 07-Jan-24 09-Jul-24 09-Jul-24, Existing Neighborhood Park ENP-04
Existing Neighborhood Park ENP-05 113 24-Jan-24 16-Jun-24 16-Jun-24, Existing Neighborhood Park ENP-05
Testing & Commissioning 301 01-Jan-24 04-Jan-25 04-Jan-25, Testing & Commiss

Testing & Commissioning of Electrical and Mechanical Systems 156 04-Jul-24 04-Jan-25 04-Jan-25, Testing & Commiss
Sector 1 111 04-Jul-24 12-Nov-24 12-Nov-24, Sector 1
GR-TAC-S01-1000 Testing & Commissioning for Zone 01 18 06-Oct-24 26-Oct-24 Testing & Commissioning for Zone 01
GR-TAC-S01-1001 Testing & Commissioning for Zone 02 18 04-Jul-24 25-Jul-24 Testing & Commissioning for Zone 02
GR-TAC-S01-1002 Testing & Commissioning for Zone 03 18 25-Aug-24 15-Sep-24 Testing & Commissioning for Zone 03
GR-TAC-S01-1003 Testing & Commissioning for Zone 04 18 05-Oct-24 26-Oct-24 Testing & Commissioning for Zone 04
GR-TAC-S01-1004 Testing & Commissioning for Zone 05 18 21-Jul-24 10-Aug-24 Testing & Commissioning for Zone 05
GR-TAC-S01-1005 Testing & Commissioning for Zone 06 18 23-Oct-24 12-Nov-24 Testing & Commissioning for Zone 06
GR-TAC-S01-1006 Testing & Commissioning for Zone 07 18 21-Oct-24 10-Nov-24 Testing & Commissioning for Zone 07
GR-TAC-S01-1007 Testing & Commissioning for Zone 08 18 29-Sep-24 20-Oct-24 Testing & Commissioning for Zone 08
Sector 2 97 11-Sep-24 04-Jan-25 04-Jan-25, Sector 2
GR-TAC-S02-1000 Testing & Commissioning for Zone 09 18 11-Nov-24 01-Dec-24 Testing & Commissioning for Zone 09
GR-TAC-S02-1001 Testing & Commissioning for Zone 10 18 14-Dec-24 04-Jan-25 Testing & Commissioning for Z
GR-TAC-S02-1002 Testing & Commissioning for Zone 11 18 25-Nov-24 16-Dec-24 Testing & Commissioning for Zone
GR-TAC-S02-1003 Testing & Commissioning for Zone 12 18 19-Nov-24 09-Dec-24 Testing & Commissioning for Zone 1
GR-TAC-S02-1004 Testing & Commissioning for Zone 13 18 11-Sep-24 03-Oct-24 Testing & Commissioning for Zone 13
GR-TAC-S02-1005 Testing & Commissioning for Zone 14 18 20-Nov-24 11-Dec-24 Testing & Commissioning for Zone 1
Sector 3 141 07-Jul-24 19-Dec-24 19-Dec-24, Sector 3
GR-TAC-S03-1000 Testing & Commissioning for Zone 15 18 18-Nov-24 09-Dec-24 Testing & Commissioning for Zone 1
GR-TAC-S03-1001 Testing & Commissioning for Zone 16 18 09-Nov-24 30-Nov-24 Testing & Commissioning for Zone 16
GR-TAC-S03-1002 Testing & Commissioning for Zone 17 18 07-Jul-24 28-Jul-24 Testing & Commissioning for Zone 17
GR-TAC-S03-1003 Testing & Commissioning for Zone 18 18 18-Jul-24 08-Aug-24 Testing & Commissioning for Zone 18
GR-TAC-S03-1004 Testing & Commissioning for Zone 19 18 07-Nov-24 27-Nov-24 Testing & Commissioning for Zone 19
GR-TAC-S03-1005 Testing & Commissioning for Zone 20 18 30-Nov-24 19-Dec-24 Testing & Commissioning for Zone
Testing & Commissioning of Irrigation networks 262 01-Jan-24 19-Nov-24 19-Nov-24, Testing & Commissioning of I
Sector 1 194 01-Jan-24 31-Aug-24 31-Aug-24, Sector 1
GR-TAC-S01-1017 Testing & Commissioning for Zone 01 18 16-Jul-24 05-Aug-24 Testing & Commissioning for Zone 01
GR-TAC-S01-1027 Testing & Commissioning for Zone 02 18 12-Jun-24 08-Jul-24 Testing & Commissioning for Zone 02
GR-TAC-S01-1037 Testing & Commissioning for Zone 03 18 15-Jul-24 05-Aug-24 Testing & Commissioning for Zone 03
GR-TAC-S01-1047 Testing & Commissioning for Zone 04 18 13-Feb-24 05-Mar-24 Testing & Commissioning for Zone 04
GR-TAC-S01-1057 Testing & Commissioning for Zone 05 18 12-May-24 01-Jun-24 Testing & Commissioning for Zone 05
GR-TAC-S01-1067 Testing & Commissioning for Zone 06 18 11-Aug-24 31-Aug-24 Testing & Commissioning for Zone 06
GR-TAC-S01-1077 Testing & Commissioning for Zone 07 18 01-Jan-24 22-Jan-24 Testing & Commissioning for Zone 07
GR-TAC-S01-1087 Testing & Commissioning for Zone 08 18 17-Jul-24 06-Aug-24 Testing & Commissioning for Zone 08
Sector 2 209 03-Mar-24 19-Nov-24 19-Nov-24, Sector 2
GR-TAC-S02-1015 Testing & Commissioning for Zone 09 18 03-Oct-24 23-Oct-24 Testing & Commissioning for Zone 09
GR-TAC-S02-1025 Testing & Commissioning for Zone 10 18 29-Oct-24 19-Nov-24 Testing & Commissioning for Zone 10
GR-TAC-S02-1035 Testing & Commissioning for Zone 11 18 20-Aug-24 10-Sep-24 Testing & Commissioning for Zone 11
GR-TAC-S02-1045 Testing & Commissioning for Zone 12 18 28-Sep-24 17-Oct-24 Testing & Commissioning for Zone 12
GR-TAC-S02-1055 Testing & Commissioning for Zone 13 18 24-Aug-24 14-Sep-24 Testing & Commissioning for Zone 13
GR-TAC-S02-1065 Testing & Commissioning for Zone 14 18 03-Mar-24 27-Mar-24 Testing & Commissioning for Zone 14
Sector 3 127 10-Jun-24 11-Nov-24 11-Nov-24, Sector 3
Actual Level of Effort Remaining Work Milestone    
Actual Work Critical Remaining Work summary
Page 9 of 11 Data Date : 08-Aug-22
 
 
Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija Project

Activity ID Activity Name Original Start Finish 2023 2024 2025


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec JanFeb
GR-TAC-S03-1015 Testing & Commissioning for Zone 15 18 29-Jul-24 19-Aug-24 Testing & Commissioning for Zone 15
GR-TAC-S03-1025 Testing & Commissioning for Zone 16 18 21-Oct-24 11-Nov-24 Testing & Commissioning for Zone 16
GR-TAC-S03-1035 Testing & Commissioning for Zone 17 18 13-Jun-24 09-Jul-24 Testing & Commissioning for Zone 17
GR-TAC-S03-1045 Testing & Commissioning for Zone 18 18 10-Jun-24 06-Jul-24 Testing & Commissioning for Zone 18
GR-TAC-S03-1055 Testing & Commissioning for Zone 19 18 07-Oct-24 27-Oct-24 Testing & Commissioning for Zone 19
GR-TAC-S03-1065 Testing & Commissioning for Zone 20 18 28-Sep-24 17-Oct-24 Testing & Commissioning for Zone 20
As-Built 150 25-Jul-24 18-Jan-25 18-Jan-25,As-Built

Sector 1 105 25-Jul-24 26-Nov-24 26-Nov-24, Sector 1


GR-ASB-S01-1000 As-Built for Zone 01 12 27-Oct-24 09-Nov-24 As-Built for Zone 01
GR-ASB-S01-1001 As-Built for Zone 02 12 25-Jul-24 08-Aug-24 As-Built for Zone 02
GR-ASB-S01-1002 As-Built for Zone 03 12 15-Sep-24 30-Sep-24 As-Built for Zone 03
GR-ASB-S01-1003 As-Built for Zone 04 12 26-Oct-24 09-Nov-24 As-Built for Zone 04
GR-ASB-S01-1004 As-Built for Zone 05 12 11-Aug-24 24-Aug-24 As-Built for Zone 05
GR-ASB-S01-1005 As-Built for Zone 06 12 13-Nov-24 26-Nov-24 As-Built for Zone 06
GR-ASB-S01-1006 As-Built for Zone 07 12 11-Nov-24 24-Nov-24 As-Built for Zone 07
GR-ASB-S01-1007 As-Built for Zone 08 12 20-Oct-24 03-Nov-24 As-Built for Zone 08
Sector 2 91 03-Oct-24 18-Jan-25 18-Jan-25, Sector 2
GR-ASB-S02-1000 As-Built for Zone 09 12 02-Dec-24 15-Dec-24 As-Built for Zone 09
GR-ASB-S02-1001 As-Built for Zone 10 12 04-Jan-25 18-Jan-25 As-Built for Zone 10
GR-ASB-S02-1002 As-Built for Zone 11 12 16-Dec-24 30-Dec-24 As-Built for Zone 11
GR-ASB-S02-1003 As-Built for Zone 12 12 10-Dec-24 23-Dec-24 As-Built for Zone 12
GR-ASB-S02-1004 As-Built for Zone 13 12 03-Oct-24 17-Oct-24 As-Built for Zone 13
GR-ASB-S02-1005 As-Built for Zone 14 12 11-Dec-24 25-Dec-24 As-Built for Zone 14
Sector 3 141 28-Jul-24 09-Jan-25 09-Jan-25, Sector 3
GR-ASB-S03-1000 As-Built for Zone 15 12 09-Dec-24 23-Dec-24 As-Built for Zone 15
GR-ASB-S03-1001 As-Built for Zone 16 12 30-Nov-24 14-Dec-24 As-Built for Zone 16
GR-ASB-S03-1002 As-Built for Zone 17 12 28-Jul-24 11-Aug-24 As-Built for Zone 17
GR-ASB-S03-1003 As-Built for Zone 18 12 08-Aug-24 22-Aug-24 As-Built for Zone 18
GR-ASB-S03-1004 As-Built for Zone 19 12 07-Dec-24 19-Dec-24 As-Built for Zone 19
GR-ASB-S03-1005 As-Built for Zone 20 12 28-Dec-24 09-Jan-25 As-Built for Zone 20
Closeout / Handover 142 11-Aug-24 25-Jan-25 25-Jan-25, Closeout / Han

Sector 1 48 10-Nov-24 04-Jan-25 04-Jan-25, Sector 1


GR-CLO-S01-1000 Closeout / Handover Works for Zone 01 6 10-Nov-24 16-Nov-24 Closeout / Handover Works for Zone 01
GR-CLO-S01-1001 Closeout / Handover Works for Zone 02 6 17-Nov-24 23-Nov-24 Closeout / Handover Works for Zone 02
GR-CLO-S01-1002 Closeout / Handover Works for Zone 03 6 24-Nov-24 30-Nov-24 Closeout / Handover Works for Zone 0
GR-CLO-S01-1003 Closeout / Handover Works for Zone 04 6 01-Dec-24 07-Dec-24 Closeout / Handover Works for Zone
GR-CLO-S01-1004 Closeout / Handover Works for Zone 05 6 08-Dec-24 14-Dec-24 Closeout / Handover Works for Zon
GR-CLO-S01-1005 Closeout / Handover Works for Zone 06 6 15-Dec-24 21-Dec-24 Closeout / Handover Works for Zo
GR-CLO-S01-1006 Closeout / Handover Works for Zone 07 6 22-Dec-24 28-Dec-24 Closeout / Handover Works for Z
GR-CLO-S01-1007 Closeout / Handover Works for Zone 08 6 29-Dec-24 04-Jan-25 Closeout / Handover Works for
Sector 2 26 25-Dec-24 25-Jan-25 25-Jan-25, Sector 2
GR-CLO-S02-1000 Closeout / Handover Works for Zone 09 6 05-Jan-25 11-Jan-25 Closeout / Handover Works fo
GR-CLO-S02-1001 Closeout / Handover Works for Zone 10 6 18-Jan-25 25-Jan-25 Closeout / Handover Work
GR-CLO-S02-1002 Closeout / Handover Works for Zone 11 6 31-Dec-24 06-Jan-25 Closeout / Handover Works for
GR-CLO-S02-1003 Closeout / Handover Works for Zone 12 6 12-Jan-25 18-Jan-25 Closeout / Handover Works
GR-CLO-S02-1004 Closeout / Handover Works for Zone 13 6 19-Jan-25 25-Jan-25 Closeout / Handover Work

Actual Level of Effort Remaining Work Milestone    


Actual Work Critical Remaining Work summary
Page 10 of 11 Data Date : 08-Aug-22
 
 
Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija Project

Activity ID Activity Name Original Start Finish 2023 2024 2025


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec JanFeb
GR-CLO-S02-1005 Closeout / Handover Works for Zone 14 6 25-Dec-24 01-Jan-25 Closeout / Handover Works for Z
Sector 3 141 11-Aug-24 23-Jan-25 23-Jan-25, Sector 3
GR-CLO-S03-1000 Closeout / Handover Works for Zone 15 6 18-Jan-25 23-Jan-25 Closeout / Handover Works
GR-CLO-S03-1001 Closeout / Handover Works for Zone 16 6 14-Dec-24 21-Dec-24 Closeout / Handover Works for Zo
GR-CLO-S03-1002 Closeout / Handover Works for Zone 17 6 11-Aug-24 18-Aug-24 Closeout / Handover Works for Zone 17
GR-CLO-S03-1003 Closeout / Handover Works for Zone 18 6 22-Aug-24 29-Aug-24 Closeout / Handover Works for Zone 18
GR-CLO-S03-1004 Closeout / Handover Works for Zone 19 6 21-Dec-24 28-Dec-24 Closeout / Handover Works for Z
GR-CLO-S03-1005 Closeout / Handover Works for Zone 20 6 11-Jan-25 16-Jan-25 Closeout / Handover Works f

Actual Level of Effort Remaining Work Milestone    


Actual Work Critical Remaining Work summary
Page 11 of 11 Data Date : 08-Aug-22