Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija Project
Long Lead Material 532 19-Sep-22 06-Jul-24 06-Jul-24, Long Lead Material
Material Submittal 418 19-Sep-22 07-Feb-24 07-Feb-24, Material Submittal
Mechanical Materials 330 19-Sep-22 28-Oct-23 28-Oct-23, Mechanical Materials
Landscape & Arch. Materials 86 11-Sep-23 21-Dec-23 21-Dec-23, Landscape & Arch. Materials
Electrical Materials 96 18-Oct-23 07-Feb-24 07-Feb-24, Electrical Materials
Material Approval 418 04-Oct-22 21-Feb-24 21-Feb-24, Material Approval
Mechanical Materials 330 04-Oct-22 11-Nov-23 11-Nov-23, Mechanical Materials
Landscape & Arch. Materials 80 03-Oct-23 04-Jan-24 04-Jan-24, Landscape & Arch. Materials
Electrical Materials 96 01-Nov-23 21-Feb-24 21-Feb-24, Electrical Materials
PO Issuance 412 18-Oct-22 28-Feb-24 28-Feb-24, PO Issuance
Mechanical Materials 324 18-Oct-22 18-Nov-23 18-Nov-23, Mechanical Materials
Landscape & Arch. Materials 74 17-Oct-23 11-Jan-24 11-Jan-24, Landscape & Arch. Materials
Electrical Materials 36 17-Jan-24 28-Feb-24 28-Feb-24, Electrical Materials
Material Delivery 502 25-Oct-22 06-Jul-24 06-Jul-24, Material Delivery
Mechanical Materials 438 25-Oct-22 17-Apr-24 17-Apr-24, Mechanical Materials
Landscape & Arch. Materials 140 24-Oct-23 11-Apr-24 11-Apr-24, Landscape & Arch. Materials
Electrical Materials 126 24-Jan-24 06-Jul-24 06-Jul-24, Electrical Materials
Bulk Material 469 08-Sep-22 01-Apr-24 01-Apr-24, Bulk Material
Material Submittal 403 08-Sep-22 10-Jan-24 10-Jan-24, Material Submittal
Mechanical Materials 327 08-Sep-22 14-Oct-23 14-Oct-23, Mechanical Materials
Landscape & Arch. Materials 168 05-Nov-22 31-May-23 31-May-23, Landscape & Arch. Materials
Electrical Materials 18 20-Dec-23 10-Jan-24 10-Jan-24, Electrical Materials
Material Approval 403 24-Sep-22 24-Jan-24 24-Jan-24, Material Approval
Mechanical Materials 327 24-Sep-22 28-Oct-23 28-Oct-23, Mechanical Materials
Landscape & Arch. Materials 165 22-Nov-22 14-Jun-23 14-Jun-23, Landscape & Arch. Materials
Electrical Materials 21 31-Dec-23 24-Jan-24 24-Jan-24, Electrical Materials
PO Issuance 397 08-Oct-22 31-Jan-24 31-Jan-24, PO Issuance
Mechanical Materials 321 08-Oct-22 04-Nov-23 04-Nov-23, Mechanical Materials
Landscape & Arch. Materials 159 06-Dec-22 21-Jun-23 21-Jun-23, Landscape & Arch. Materials
Electrical Materials 15 14-Jan-24 31-Jan-24 31-Jan-24, Electrical Materials
Material Delivery 439 15-Oct-22 01-Apr-24 01-Apr-24, Material Delivery
Mechanical Materials 339 15-Oct-22 02-Dec-23 02-Dec-23, Mechanical Materials
Landscape & Arch. Materials 333 13-Dec-22 23-Jan-24 23-Jan-24, Landscape & Arch. Materials
Electrical Materials 57 21-Jan-24 01-Apr-24 01-Apr-24, Electrical Materials
Permit / Authority Approval 510 08-Oct-22 27-Jun-24 27-Jun-24, Permit /Authority Approval
Testing & Commissioning of Electrical and Mechanical Systems 156 04-Jul-24 04-Jan-25 04-Jan-25, Testing & Commiss
Sector 1 111 04-Jul-24 12-Nov-24 12-Nov-24, Sector 1
GR-TAC-S01-1000 Testing & Commissioning for Zone 01 18 06-Oct-24 26-Oct-24 Testing & Commissioning for Zone 01
GR-TAC-S01-1001 Testing & Commissioning for Zone 02 18 04-Jul-24 25-Jul-24 Testing & Commissioning for Zone 02
GR-TAC-S01-1002 Testing & Commissioning for Zone 03 18 25-Aug-24 15-Sep-24 Testing & Commissioning for Zone 03
GR-TAC-S01-1003 Testing & Commissioning for Zone 04 18 05-Oct-24 26-Oct-24 Testing & Commissioning for Zone 04
GR-TAC-S01-1004 Testing & Commissioning for Zone 05 18 21-Jul-24 10-Aug-24 Testing & Commissioning for Zone 05
GR-TAC-S01-1005 Testing & Commissioning for Zone 06 18 23-Oct-24 12-Nov-24 Testing & Commissioning for Zone 06
GR-TAC-S01-1006 Testing & Commissioning for Zone 07 18 21-Oct-24 10-Nov-24 Testing & Commissioning for Zone 07
GR-TAC-S01-1007 Testing & Commissioning for Zone 08 18 29-Sep-24 20-Oct-24 Testing & Commissioning for Zone 08
Sector 2 97 11-Sep-24 04-Jan-25 04-Jan-25, Sector 2
GR-TAC-S02-1000 Testing & Commissioning for Zone 09 18 11-Nov-24 01-Dec-24 Testing & Commissioning for Zone 09
GR-TAC-S02-1001 Testing & Commissioning for Zone 10 18 14-Dec-24 04-Jan-25 Testing & Commissioning for Z
GR-TAC-S02-1002 Testing & Commissioning for Zone 11 18 25-Nov-24 16-Dec-24 Testing & Commissioning for Zone
GR-TAC-S02-1003 Testing & Commissioning for Zone 12 18 19-Nov-24 09-Dec-24 Testing & Commissioning for Zone 1
GR-TAC-S02-1004 Testing & Commissioning for Zone 13 18 11-Sep-24 03-Oct-24 Testing & Commissioning for Zone 13
GR-TAC-S02-1005 Testing & Commissioning for Zone 14 18 20-Nov-24 11-Dec-24 Testing & Commissioning for Zone 1
Sector 3 141 07-Jul-24 19-Dec-24 19-Dec-24, Sector 3
GR-TAC-S03-1000 Testing & Commissioning for Zone 15 18 18-Nov-24 09-Dec-24 Testing & Commissioning for Zone 1
GR-TAC-S03-1001 Testing & Commissioning for Zone 16 18 09-Nov-24 30-Nov-24 Testing & Commissioning for Zone 16
GR-TAC-S03-1002 Testing & Commissioning for Zone 17 18 07-Jul-24 28-Jul-24 Testing & Commissioning for Zone 17
GR-TAC-S03-1003 Testing & Commissioning for Zone 18 18 18-Jul-24 08-Aug-24 Testing & Commissioning for Zone 18
GR-TAC-S03-1004 Testing & Commissioning for Zone 19 18 07-Nov-24 27-Nov-24 Testing & Commissioning for Zone 19
GR-TAC-S03-1005 Testing & Commissioning for Zone 20 18 30-Nov-24 19-Dec-24 Testing & Commissioning for Zone
Testing & Commissioning of Irrigation networks 262 01-Jan-24 19-Nov-24 19-Nov-24, Testing & Commissioning of I
Sector 1 194 01-Jan-24 31-Aug-24 31-Aug-24, Sector 1
GR-TAC-S01-1017 Testing & Commissioning for Zone 01 18 16-Jul-24 05-Aug-24 Testing & Commissioning for Zone 01
GR-TAC-S01-1027 Testing & Commissioning for Zone 02 18 12-Jun-24 08-Jul-24 Testing & Commissioning for Zone 02
GR-TAC-S01-1037 Testing & Commissioning for Zone 03 18 15-Jul-24 05-Aug-24 Testing & Commissioning for Zone 03
GR-TAC-S01-1047 Testing & Commissioning for Zone 04 18 13-Feb-24 05-Mar-24 Testing & Commissioning for Zone 04
GR-TAC-S01-1057 Testing & Commissioning for Zone 05 18 12-May-24 01-Jun-24 Testing & Commissioning for Zone 05
GR-TAC-S01-1067 Testing & Commissioning for Zone 06 18 11-Aug-24 31-Aug-24 Testing & Commissioning for Zone 06
GR-TAC-S01-1077 Testing & Commissioning for Zone 07 18 01-Jan-24 22-Jan-24 Testing & Commissioning for Zone 07
GR-TAC-S01-1087 Testing & Commissioning for Zone 08 18 17-Jul-24 06-Aug-24 Testing & Commissioning for Zone 08
Sector 2 209 03-Mar-24 19-Nov-24 19-Nov-24, Sector 2
GR-TAC-S02-1015 Testing & Commissioning for Zone 09 18 03-Oct-24 23-Oct-24 Testing & Commissioning for Zone 09
GR-TAC-S02-1025 Testing & Commissioning for Zone 10 18 29-Oct-24 19-Nov-24 Testing & Commissioning for Zone 10
GR-TAC-S02-1035 Testing & Commissioning for Zone 11 18 20-Aug-24 10-Sep-24 Testing & Commissioning for Zone 11
GR-TAC-S02-1045 Testing & Commissioning for Zone 12 18 28-Sep-24 17-Oct-24 Testing & Commissioning for Zone 12
GR-TAC-S02-1055 Testing & Commissioning for Zone 13 18 24-Aug-24 14-Sep-24 Testing & Commissioning for Zone 13
GR-TAC-S02-1065 Testing & Commissioning for Zone 14 18 03-Mar-24 27-Mar-24 Testing & Commissioning for Zone 14
Sector 3 127 10-Jun-24 11-Nov-24 11-Nov-24, Sector 3
Actual Level of Effort Remaining Work Milestone
Actual Work Critical Remaining Work summary
Page 9 of 11 Data Date : 08-Aug-22
Landscape Construction of Neighborhoods Olaisaha And Middle Al Uraija Project