CONSTRUCTION OF EMPTY QUARTERS PHASE 1

Activity ID Activity Name Original Start Finish Total Month


Duration Float
-6 -5 -4 -3 -2 -1 1
Total 573 22-Sep-21 21-Mar-23 0

CONSTRUCTION OF EMPTY QUARTERS PHASE 1 573 22-Sep-21 21-Mar-23 0

Milestones 467 22-Sep-21 21-Mar-23 0 Project Start Milestone


PRELIMINARIES 450 22-Sep-21 15-Dec-22 95
General 450 22-Sep-21 15-Dec-22 95
Mobilization 60 27-Sep-21 05-Dec-21 385 Mobilization
Camp 60 27-Sep-21 05-Dec-21 385 Camp
Site Office 57 27-Sep-21 01-Dec-21 385 Site Office
Play Grounds 30 26-Oct-21 29-Nov-21 383 Play Grounds
Other Facilities 54 27-Sep-21 28-Nov-21 381 Other Facilities
FIELD ENGINEERING 305 22-Sep-21 09-Jul-22 230
NEW BUILDINGS/CONSTRUCTION WORKS 229 22-Sep-21 23-Apr-22 189
B-55 External Security Point 44 27-Sep-21 16-Nov-21 90 B-55 External Security Point
B-54 Internal Security Point 44 22-Sep-21 11-Nov-21 286 B-54 Internal Security Point
B-50 Road Gantry Signage 37 22-Sep-21 03-Nov-21 115 B-50 Road Gantry Signage
B-48 Electrical Operating Gate 15 06-Apr-22 23-Apr-22 105
GT1,2,3 Toilets 44 27-Oct-21 16-Dec-21 269 GT1,2,3 Toilets
Control Room 44 09-Dec-21 29-Jan-22 209 Control Room
Land Ports Security forces 44 22-Sep-21 11-Nov-21 213 Land Ports Security forces
N-01 Customs & Immigration Booths With Canopy 0 0
N-02 Clearance Booth With Canopy 0 0
N-03 Fixed X-Ray : Trucks 0 0
N-04 Incinerator 0 0
N-06 Fixed X-Ray :Cars 0 0
N07 Customs & Immigration Booths With Canopy 0 0
N-08 Clearance Booth With Canopy 0 0
N-17 Welcome Centre 0 0
N-09 Employees Reception & Security Check 0 0
COMPLETION /REPAIR OF EXISTING BUILDINGS 172 26-Sep-21 13-Apr-22 262
Men Toilets 44 14-Dec-21 02-Feb-22 311 Men Toilets
Women Toilets 44 01-Nov-21 21-Dec-21 34 Women Toilets
Prayer Mosque Men & Women 44 26-Jan-22 17-Mar-22 160
B-04a Animal &Agricultural Quarantine Office 44 07-Dec-21 26-Jan-22 236 B-04a Animal & Agricultural Quarantine Office
B-09 Mosque 44 09-Nov-21 29-Dec-21 137 B-09 Mosque
B-08 & 41 Truck Drivers Lounge 44 11-Jan-22 02-Mar-22 164
B-05 Custom Release Hall 44 09-Nov-21 29-Dec-21 266 B-05 Custom Release Hall
B-07 Freeze Store 44 14-Dec-21 02-Feb-22 322 B-07 Freeze Store
B-06 Laboratory 44 23-Dec-21 12-Feb-22 250 B-06 Laboratory
B-04 Agricultural Quarantine Office 44 02-Jan-22 21-Feb-22 256 B-04 Agricultural Quarantine O
B-03a&09a WC Near Mosque 44 22-Dec-21 10-Feb-22 245 B-03a&09a WC Near Mosque
B-02, B-02A, B-2B Custome Security Office Building 111 26-Sep-21 01-Feb-22 67 B-02, B-02A, B-2B Custome Security Office Bu
B-01& 42 Truck Passport Building 44 10-Jan-22 01-Mar-22 243
B-38 Smuggled Car & Goods Building 44 01-Jan-22 20-Feb-22 253 B-38 Smuggled Car & Goods B
B-40 Mosque 44 14-Dec-21 02-Feb-22 252 B-40 Mosque
B-40a WC Near Mosque B40 44 18-Jan-22 09-Mar-22 242
B-39 Custom Security Unit 44 22-Feb-22 13-Apr-22 116
SHADES 247 25-Sep-21 09-Jul-22 162
SH-1,2,3&12 Canopy and Booths for Transit Trucks 44 04-Nov-21 25-Dec-21 156 SH-1,2,3&12 Canopy and Booths for Transit Trucks
SH-6- A&B Custom Shade Unit For Truck Type (1) 44 02-Mar-22 21-Apr-22 205
SH-6 B Enclosed Shutter 44 06-Apr-22 26-May-22 165
SH-9 Fish Shade 44 11-May-22 30-Jun-22 164

Actual Work Milestone Page 1 of 6


Remaining Work Summary
© Oracle Corporation
Critical Remaining Work
CONSTRUCTION OF EMPTY QUARTERS PHASE 1

Month
2 3 4 5 6 7 8 9 10 11 12 13 14 15
Total

CONSTRUCTION OF EMPTY QUA


Project Finish Milestone
Milestones
PRELIMINARIES
General

FIELD ENGINEERING
NEW BUILDINGS/CONSTRUCTION WORKS

B-48 Electrical Operating Gate

COMPLETION /REPAIR OF EXISTING BUILDINGS

Prayer Mosque Men & Women


& Agricultural Quarantine Office

B-08 & 41 Truck Drivers Lounge

B-06 Laboratory
B-04 Agricultural Quarantine Office
-03a&09a WC Near Mosque
02A, B-2B Custome Security Office Building
B-01& 42 Truck Passport Building
B-38 Smuggled Car & Goods Building

B-40a WC Near Mosque B40


B-39 Custom Security Unit
SHADES

SH-6-A&B Custom Shade Unit For Truck Type (1)


SH-6 B Enclosed Shutter
SH-9 Fish Shade

Actual Work Milestone Page 2 of 6


Remaining Work Summary
© Oracle Corporation
Critical Remaining Work
CONSTRUCTION OF EMPTY QUARTERS PHASE 1

Activity ID Activity Name Original Start Finish Total Month


Duration Float
-6 -5 -4 -3 -2 -1 1
SH-4 Parking Canopy 44 19-May-22 09-Jul-22 154
SH-8 Sheep Shade 44 25-Sep-21 14-Nov-21 352 SH-8 Sheep Shade
SH-5 Custom Shade Unit For Truck Type (2) 44 19-Mar-22 08-May-22 121
SH-13 Custom Shade Unit For Truck Norm 44 25-Sep-21 14-Nov-21 327 SH-13 Custom Shade Unit For Truck Norm
SH-13 Enclosed Shutter 44 27-Sep-21 16-Nov-21 363 SH-13 Enclosed Shutter
K9- FACILITES 79 22-Sep-21 22-Dec-21 340 K9- FACILITES
B-36C - Housing for Dog's Catetaker 44 22-Sep-21 11-Nov-21 238 B-36C - Housing for Dog's Catetaker
B-36H - Dormitories Dogs Building 44 30-Sep-21 20-Nov-21 190 B-36H - Dormitories Dogs Building
B-36A - Recreation Building 44 05-Oct-21 24-Nov-21 282 B-36A - Recreation Building
B-36D - Department Building 44 10-Oct-21 29-Nov-21 282 B-36D - Department Building
B-36K - Workshop & Watchman room 44 14-Oct-21 04-Dec-21 4 B-36K - Workshop & Watchman room
B-36G&J - Dog's Rest area & Training 44 19-Oct-21 08-Dec-21 166 B-36G&J - Dog's Rest area & Training
B-36E - Drugs Store 44 24-Oct-21 13-Dec-21 260 B-36E - Drugs Store
B-36F - Explosion Store 44 28-Oct-21 18-Dec-21 312 B-36F - Explosion Store
B-36B - Dormitories Inspectors Rest House 44 02-Nov-21 22-Dec-21 288 B-36B - Dormitories Inspectors Rest House
K9 Fire Alarm System 37 02-Nov-21 14-Dec-21 347 K9 Fire Alarm System
K9 General Works 67 22-Sep-21 08-Dec-21 201 K9 General Works
BUILDING WILL BE REPORPOSED (Adapting) 44 17-Jan-22 08-Mar-22 223
B-10 Operational Center 44 17-Jan-22 08-Mar-22 183
B-03 X-Ray Monitering Room 44 17-Jan-22 08-Mar-22 223
EXTERNAL WORKS 125 22-Sep-21 14-Feb-22 177 EXTERNAL WORKS
External works 85 22-Sep-21 29-Dec-21 86 External works
External Lighting 40 30-Dec-21 14-Feb-22 177 External Lighting
Irrigation System 40 16-Oct-21 30-Nov-21 1 Irrigation System
Passenger Area Works 40 02-Nov-21 18-Dec-21 100 Passenger Area Works
Civil and electromechanical works for special equipment 67 25-Nov-21 10-Feb-22 177 Civil and electromechanical works for s
PROCUREMENT 176 13-Oct-21 05-May-22 268
CIVIL 71 13-Oct-21 03-Jan-22 296 CIVIL
Submission 6 13-Oct-21 19-Oct-21 74 Submission
Approval 8 17-Oct-21 25-Oct-21 326 Approval
Delivery 63 23-Oct-21 03-Jan-22 296 Delivery
ARCH 176 13-Oct-21 05-May-22 240
Submission 21 13-Oct-21 06-Nov-21 305 Submission
Approval 23 17-Oct-21 11-Nov-21 360 Approval
Delivery 168 23-Oct-21 05-May-22 240
MECHANICAL 154 13-Oct-21 10-Apr-22 277
Submission 24 13-Oct-21 09-Nov-21 315 Submission
Approval 26 17-Oct-21 15-Nov-21 387 Approval
Manufacturing & Delivery 146 23-Oct-21 10-Apr-22 277
ELECTRICAL 139 13-Oct-21 23-Mar-22 305
Submission 15 13-Oct-21 30-Oct-21 330 Submission
Approval 17 17-Oct-21 04-Nov-21 394 Approval
Manufacturing & Delivery 131 23-Oct-21 23-Mar-22 305
CONSTRUCTION 549 14-Oct-21 20-Mar-23 0
Cargo inbound area 513 16-Oct-21 15-Feb-23 35
Completion/Repair of Existing Buildings/Construction works 405 01-Nov-21 15-Feb-23 8
New Buildings 480 15-Nov-21 15-Feb-23 0
External Works 510 16-Oct-21 13-Feb-23 38
Building will be demolished/ Cancelled 189 23-Jun-22 29-Jan-23 15
Building will be Repurposed (adapting) 335 30-Mar-22 15-Feb-23 0
Cargo outbound area 514 14-Oct-21 15-Feb-23 35
Completion/Repair of Existing Buildings/Construction works 453 20-Nov-21 15-Feb-23 0

Actual Work Milestone Page 3 of 6


Remaining Work Summary
© Oracle Corporation
Critical Remaining Work
CONSTRUCTION OF EMPTY QUARTERS PHASE 1

Month
2 3 4 5 6 7 8 9 10 11 12 13 14 15
SH-4 Parking Canopy

SH-5 Custom Shade Unit For Truck Type (2)

BUILDING WILL BE REPORPOSED (Adapting)


B-10 Operational Center
B-03 X-Ray Monitering Room
EXTERNAL WORKS

External Lighting

ivil and electromechanical works for special equipment


PROCUREMENT

ARCH

Delivery
MECHANICAL

Manufacturing & Delivery


ELECTRICAL

Manufacturing & Delivery


CONSTRUCTION
Cargo inbound area
Completion/Repair of Existing Buildings/Construction works
New Buildings
External Works
Building will be demolished/ Cancelled
Building will be Repurposed (adapting)
Cargo outbound area
Completion/Repair of Existing Buildings/Construction works

Actual Work Milestone Page 4 of 6


Remaining Work Summary
© Oracle Corporation
Critical Remaining Work
CONSTRUCTION OF EMPTY QUARTERS PHASE 1

Activity ID Activity Name Original Start Finish Total Month


Duration Float
-6 -5 -4 -3 -2 -1 1
New Buildings 199 18-Dec-21 25-Jun-22 246
External Works. 409 14-Oct-21 02-Feb-23 39
Building will be demolished / Cancelled 182 14-Jul-22 11-Feb-23 4
Building will be Repurposed (adapting) 0 0
Passengers Area 521 14-Oct-21 22-Feb-23 28
New Buildings/Construction Works 299 01-Jan-22 16-Oct-22 131
Completion/Repair of Existing Buildings/Construction works 30 05-Jan-23 08-Feb-23 6
External Works 426 14-Oct-21 22-Feb-23 22
Building will be cancelled 206 21-Jun-22 15-Feb-23 28
Administration Area 549 14-Oct-21 20-Mar-23 0
Completion/Repair of Existing Buildings/Construction works 354 30-Dec-21 15-Feb-23 28
New Buildings/Construction Works 481 16-Dec-21 20-Mar-23 0
Externa Works 419 14-Oct-21 14-Feb-23 1
Building will be cancelled 89 05-Nov-22 15-Feb-23 0
K9 Facilities 479 16-Nov-21 15-Feb-23 8
Completion/Repair of Existing Buildings/Construction works 475 20-Nov-21 15-Feb-23 0
External Works 392 16-Nov-21 15-Feb-23 6
TESTING & COMMISSIONING 28 16-Feb-23 21-Mar-23 0
Demobilization 18 28-Feb-23 21-Mar-23 0

Actual Work Milestone Page 5 of 6


Remaining Work Summary
© Oracle Corporation
Critical Remaining Work
CONSTRUCTION OF EMPTY QUARTERS PHASE 1

Month
2 3 4 5 6 7 8 9 10 11 12 13 14 15
New Buildings
External Works.
Building will be demolished / Cancelled

Passengers Area
New Buildings/Construction Works
Completion/Repair of Existing Buildings/Construction works
External Works
Building will be cancelled
Administration Area
Completion/Repair of Existing Buildings/Construction works
New Buildings/Construction Works
Externa Works
Building will be cancelled
K9 Facilities
Completion/Repair of Existing Buildings/Construction works
External Works
TESTING & COMMISSIONING
Demobilization

Actual Work Milestone Page 6 of 6


Remaining Work Summary
© Oracle Corporation
Critical Remaining Work