Compressor Readiness
06 Jan 2022
Marunda 2.0
17:00
17:00 17:00
12:00
13:00
16:00
17:00
New Filling Building – Overall Target Schedule
MC : 17 Jan 21
JWT
26 Dec 21 Slab Done
53-N-B-001 Civil and Structure in New Filling Building (31 Dec 2021) include Sewer and Drainage
53-N-B-002 Architecture in New Filling Building (16 Jan 2022) OFFICE Building, FORKLIFT Room, Label Printing Room)
53-N-B-004 Fire Alarm in New Filling Building (15 Jan 2022)
53-N-B-007 HVAC in New Filling Building (30-Jan-2022) Panel HVAC New Filling ETA 15 Jan 22
U-3352
10 Nov 21 04 Dec 21Installation ,Wiring ,Loop test ( 01 Dec),
U-3352 Production (Commissioning)
17 Jan 22 29 Jan 22
U-3352 Production: 01 February 2022
U-3360 Pail
29 Nov 21 16 Dec 21 Installation ,Wiring ,Loop test,
U-3360 Production (Commissioning)
05 Feb 22 22 Feb 22
FAT 21 Dec , ETA 28 Dec 21
02 Dec21 EDSS Installation
18 Jan 22
29 Dec 21
TBC EDSS Testing
U-3351 Existing Drum 2
Legend : 03 Feb 22 25 Feb 22 Epoxy New Filling Line
Baseline 17 Jan 22 24 Apr 22 05 May 22
24 Dec 21
Forecast U-3350 Existing Drum 1 Installation
SAT Workshop & Compressor Epoxy) 24 Jan 22 31 Jan 22 U-3351 Commissioning
Re-baseline 15 Mar 22
U-3350 Commissioning
01 Feb 22 04 Feb 22 26 Feb 22
Meeting Outline
Readiness Building for New Filling Building and Compressor Area
Compressor Update
04 Update Construction, interface issue, Material delivery update
risk update .
ITEM Concern
No Item Concern Follow up Target Status PIC
1 Epoxy Painting Plan and detail will explain in Friday-Interface Meeting 07 Jan 22 Open Andy K
2 Line Marking drawing Final drawing already submitted 04 Jan 22 Close Subekti
3 Design and site Connection roof flashing between staging and new filling not provide 05 Jan 22 Close Dafit
installation issue yet,
Update 05/01/22 : SI for Cover the Gap between Roofing Staging and
Cladding NFB already issued to GSB
EDSS Platform vs Cable tray 10 Jan 22 Open Site : Nugroho
Update 06/01/22 : FS under preparation Eng : Mahfud
Lead : Subekti
Door relocation in East side EDSS 07 Jan 22 Open Site : Dafid
Update 06/01/22 : FS under preparation Eng : AndyK
Lead : Suekti
Mechanical Handling Hoist Crane Compressor House 07 Jan 22 Open Site : Junaedi
Update 06/01/22 : internal Discussion JGC Eng : Jun & Heery
Lead Subekti
4 Dismantling scaffolding Update Maps list for remaining work and target plan schedule 07 Jan 22 Open Agus
vs remaining work in
parameter BLD and PR
18 & 19
5 MAS for Booster Pump Waiting review from shell 07 Jan 22 Open Cipta
6 PPR for Service water to Internal discussion and Engineering check, due to Velocity and 07 Jan 22 Open Subekti/Indri
New Office BLD Booster pump calculation (from 1 inch to 1,5 inch)
SEWER NEW FILLING BUILDING AREA
Lighting DR-04
Pole
M 06 Jan 2022
PEDESTRIAN
WALWAY Pro g re ss U-Dit c h
Are a Q t y (m ) To t a l In st a lle d (m ) Re m a in in g (m ) Ta rg e t Fin ish
DR-1 79,34 72,00 7,34 08 Ja n 22
DR-2 101,628 95,60 6,03 DO NE
DR-05 DR-3 32,81 32,81 0,00 DO NE
88,25%
DR-01
DR-02
DR-06
Legend
Boundary
Soil Relocation
Handover
Concrete Apron
Remaining Road access
Hydrant Paving
Pedestrian walkway
2 Lighting Pole Foundation in - Precast installation, Pulling cable HANDRIANSYAH 05 Jan 22 Open
east side Fence
03 Roll Up Door,
Steel Door,
Aziz
03 single Swing 13 Nos 7 6 Nos 15 Jan 22
/Raya
Door: ETA 5
JAN 22
Remaining
Will explain Aziz
04 Epoxy Work 2429 m2 1669 m2 760 m2
6,2 03
friday /Raya
Line Marking
03 North Side 15 Jan 22
05 in Staging As per drawing
(migration area) Aziz/Raya
Area
As per drawing
06 Hard Barrier 0
15 Jan 22 Aziz/Raya
03
Convective
07 Mirror and 14 0 14
15 Jan 22 Dafid
Signage
03
HVAC Installation
06 Jan 2022
LEGEND
-FAT 15 Jan 22
-Installation 2 week
-SAT Complete 31 Jan 22
9
53-N-M-201 DOCK LEVELER READINESS 06 Jan 22
Cleaning all
Readiness Area for
H-3320 2 4 Nos material, install
SAT
Grating
H-3319
3 ITR Close 4 ITR 0 4 ITR 10 Jan 22
H-3318
H-3317 03
53-N-M-201 EDSS READINESS
06 Jan 22
01
01
04
03
03
BUILDING WORK _ NEW FILLING BUILDING AREA 06 Jan 2022
InstallationRG
Suyitno
01 S Conduit PR 165 m 165 0m 28 Dec 21
/Andy K
19
Tray Suyitno
02 475 m 475 m 0m 16 Dec 21
Installation /Andy K
Lighting fixture
256 Siswanto /
04 installation(pr1 251 Nos 05 Nos 05 Jan 22
Nos Andy K
9)
Panel
Siswanto /
05 installation & 4 Nos 4 Nos 0 Nos 20 Dec 21
Andy K
energize
Switch Installed
LEGEND
lighting fixture installed included
lighting fixture installed
termination
Fire Alarm
Conduit Siswanto /
02 216 m 66 m 150 m 10 Jan 22
Installation Andy K
RGS)
LEGEND
Remaining Tray
13
53-N-B-005-PIPING WORK _ NEW FILLING BUILDING AREA
Hose reel installation
Update as of 06 Jan 22
Pipe
01 270 ID 270 ID 0 DONE Sunaryo
Installation
Open(Modifica
Hose rail tion during
02 4 Nos 4 Nos 0 Sunaryo
installation Traffic Meeting
with OPS)
Hydrotest- Sunaryo
03 270 ID 0 270ID 09 Jan 22
Closing Punch /Nurul
Desktop
04 46 Nos 5 41 Nos 12 Jan 22 Baktiar
Readinrss
6,1
6,2
Legend :
: Cable Tray & cable Installed
: LCP Panel Installed
: Socket Battery charging include pulling cable
termination Done
Instrument Work in New Filling Building
Update as of 05 Jan 22
Remaining for
Relocated Drum
2 Perforated Tray (M) 754 704 50
Line (U3350 &
U3351)
3 Remote IO (unit) 3 3 0
4 Install JB (unit) 4 4 0
5 JB-PLS & JB-DVP (unit) 12 12 0
6 Control Box (unit) 4 2 2 (*)
Will be installed
12 Install DPI (***) 12 0 12 after filter
handover
8,1 – 8,6
13 Install Lubcel PC (****) 2 0 2
Note :
1. (*) Remaining Control Box for Relocated Drum Line (U-3350 & U-3351)
2. (**) Cable for Relocated Drum Line (U-3350 & U-3351) already pulled and coiled on pipe rack, will be termination after drum lines
relocated
3. (***) Priority for U3352 & U3360 (5 ea) and remaining (U3350 & U3351 will be installed after the filling line relocated
4. (****) Will be installed after filling line completed (Lubcel PC supplied by Shell)
5. Loop check for Drum Line on progress (by ABB)
(#) Priority for Drum Line (U-3352)
Cleaning Area & Dismantling Scaffolding New Filling Building
Legend
Scaffolding area
5,2 Touch-up paint FW line Touch-up paint FW line
Cover tray (Electrical & FA BLD Cover tray (Electrical & FA BLD)
Install Beam Detector & Termination MCP Scaffolding dismantle
Cleaning Area
6,2
2 Rool Up door RD 7Unit 05-Jan-22 22-Dec-21 2 nos for Workshop & south side, 5 Nos ETA :
4 Conveyor, Bulk material,Panel 06 Jan 22 31 Dec 21 05 Jan 22 Beam Delivery : 14 Nos Beam
Item Concern
COMPRESSOR_ NEW FILLING BUILDING AREA
Update as of 06 Jan 22
SPV /SI
NO DESCRIPTION QTY INSTALLED REMAINING TARGET FINISH
01 Paving 1 SECTION 0 0
11 Jan 22
PAGA System:
1. Horn 1 ea 0 ea 1 ea
Speaker 1 ea 0 ea 1 ea
02 2. JB Speaker 1 ea 0 ea 1 ea
3. Telephone 1 ea 0 ea 1 ea
Analog
4. SAT
Fire Alarm:
6 ea 6 ea 0 ea
1. HD
Installation
1 ea 1 ea 0 ea
03 2. MCP
1 ea 1 ea 0 ea
3. AAF/VAF
1 ea 0 ea 1 ea
4. JB (460-JE-
306)
New Filling Strategy Handover
Handover 17 Jan 22
21
Thank You
53-N-B-005-PIPING WORK _ NEW FILLING BUILDING AREA
Update as of 22 Dec 21
D17
2
6
FAT PLAN: EDSS SYSTEM
SIMULATION SCENARIO
b. Scenario Storing
Process b1. 5 drums in a row b2. Stacking 3-2-1
D17
2
8
FAT PLAN: SCHEDULE
21-22 Dec 21 : FAT Conveyor System
28 Dec 21 : PO new servo motor
27-31 Dec 21 : Continue trial program with old servo motor
03-07 Jan 22 : Repair girder box
17 Jan 22 : new servo motor arrived at IMK workshop
17-20 Jan 22 : Install new servo & preparation FAT
21 Jan 22 : FAT Gantry System
22-28 Jan 22 : Closing Punch list
29 Jan 22 : Delivery remaining EDSS
Conveyor system installation and SAT No
1
Description
28 Dec 21
Finish
15 Jan 2022
1 Remaining Conveyor
Delivery
2 Panel delivery
4 Installation EI
5 Testing
Legend
Remaining Conveyor
Installation of gantry system
1. 1.The Access coming from East side door new filling Building
2. Material and erection by TMC 6 tons
1. Before installation QC Check padding installation
2. 2.Erection for column start from East Side
No Description Start Finish
6,2
Legend :
: Cable Tray & cable Installed
: LCP Panel Installed
: Socket Battery charging include pulling cable
termination Done