New Filling Building &

Compressor Readiness
06 Jan 2022

Marunda 2.0
17:00
17:00 17:00
12:00

13:00
16:00
17:00
New Filling Building – Overall Target Schedule
MC : 17 Jan 21
JWT
26 Dec 21 Slab Done
53-N-B-001 Civil and Structure in New Filling Building (31 Dec 2021) include Sewer and Drainage

53-N-B-002 Architecture in New Filling Building (16 Jan 2022) OFFICE Building, FORKLIFT Room, Label Printing Room)
53-N-B-004 Fire Alarm in New Filling Building (15 Jan 2022)

53-N-B-003 Electrical in New Filling Building (31-Dec-21)

53-N-B-005 Fire Fighting in New Filling Building (16-Jan-22)


53-N-B-006 Plumbing in New Filling Building (31-Dec-21)
ETA Panel 15 Jan22

53-N-B-007 HVAC in New Filling Building (30-Jan-2022) Panel HVAC New Filling ETA 15 Jan 22

53-N-E-003 Electrical in New Filling Building (31-Dec-21)

53-N-E-009,012,010,011,008 Telecom Work(15 Jan 2022)

52-N-I-103, 52-N-I-101,102, Instrument Work (31-Dec-21)

33-P-P-301, Piping Work IA Line (around U-3352 & 3360) (31-Dec-21)

54-N-M-301, Dock Leveler Installation (15-Jan-22)

U-3352
10 Nov 21 04 Dec 21Installation ,Wiring ,Loop test ( 01 Dec),
U-3352 Production (Commissioning)
17 Jan 22 29 Jan 22
U-3352 Production: 01 February 2022
U-3360 Pail
29 Nov 21 16 Dec 21 Installation ,Wiring ,Loop test,
U-3360 Production (Commissioning)
05 Feb 22 22 Feb 22
FAT 21 Dec , ETA 28 Dec 21
02 Dec21 EDSS Installation
18 Jan 22
29 Dec 21
TBC EDSS Testing
U-3351 Existing Drum 2
Legend : 03 Feb 22 25 Feb 22 Epoxy New Filling Line
Baseline 17 Jan 22 24 Apr 22 05 May 22
24 Dec 21
Forecast U-3350 Existing Drum 1 Installation
SAT Workshop & Compressor Epoxy) 24 Jan 22 31 Jan 22 U-3351 Commissioning
Re-baseline 15 Mar 22
U-3350 Commissioning
01 Feb 22 04 Feb 22 26 Feb 22
Meeting Outline
Readiness Building for New Filling Building and Compressor Area

New Filling Update


01 Update New Filling Building for Construction progress.

02 Item Concern &Risk Update


Risk update in per sub-system

Material Delivery Update


03 ETA Material update for Building Section.

Compressor Update
04 Update Construction, interface issue, Material delivery update
risk update .
ITEM Concern
No Item Concern Follow up Target Status PIC
1 Epoxy Painting Plan and detail will explain in Friday-Interface Meeting 07 Jan 22 Open Andy K
2 Line Marking drawing Final drawing already submitted 04 Jan 22 Close Subekti
3 Design and site Connection roof flashing between staging and new filling not provide 05 Jan 22 Close Dafit
installation issue yet,
Update 05/01/22 : SI for Cover the Gap between Roofing Staging and
Cladding NFB already issued to GSB
EDSS Platform vs Cable tray 10 Jan 22 Open Site : Nugroho
Update 06/01/22 : FS under preparation Eng : Mahfud
Lead : Subekti
Door relocation in East side EDSS 07 Jan 22 Open Site : Dafid
Update 06/01/22 : FS under preparation Eng : AndyK
Lead : Suekti
Mechanical Handling Hoist Crane Compressor House 07 Jan 22 Open Site : Junaedi
Update 06/01/22 : internal Discussion JGC Eng : Jun & Heery
Lead Subekti
4 Dismantling scaffolding Update Maps list for remaining work and target plan schedule 07 Jan 22 Open Agus
vs remaining work in
parameter BLD and PR
18 & 19
5 MAS for Booster Pump Waiting review from shell 07 Jan 22 Open Cipta
6 PPR for Service water to Internal discussion and Engineering check, due to Velocity and 07 Jan 22 Open Subekti/Indri
New Office BLD Booster pump calculation (from 1 inch to 1,5 inch)
SEWER NEW FILLING BUILDING AREA
Lighting DR-04
Pole
M 06 Jan 2022

PEDESTRIAN
WALWAY Pro g re ss U-Dit c h
Are a Q t y (m ) To t a l In st a lle d (m ) Re m a in in g (m ) Ta rg e t Fin ish
DR-1 79,34 72,00 7,34 08 Ja n 22
DR-2 101,628 95,60 6,03 DO NE
DR-05 DR-3 32,81 32,81 0,00 DO NE

DR-4 132,2 122,95 9,25 DO NE


DR-5 107,136 98,00 9,14 10 Ja n 22
DR-6 98,015 65,00 33,02 15 Ja n 22
TO TAL 551,13 486,36 64,77

88,25%

DR-01

DR-02
DR-06

Target finish All : 15 Jan 2022


DR-03
CIVIL WORK _ NEW FILLING BUILDING AREA
06 Jan 2022 0

NO Item Description Target

01 Area 14 (remaing access in East Side) 08 Jan 22

02 Pedestrian Walkway (North & East) 15 Jan 22

03 Lighting FDN (East Fence) 07 Jan 22

04 Joint sealant & Road marking (North,East,South) 15 Jan 22

05 Road Signage (North,East,South) 15 Jan 22

06 Sliding Gate for Emergency Access (East) 15 Jan 22

07 Soil relocation to Laydown 10 Jan 22

08 PVC Connect to U Ditch 08 Jan 22

09 Concrete Apron 12 Jan 22

10 Hydrant Paving & Hydrant Box Installed 15 Jan 22

Legend
Boundary
Soil Relocation
Handover
Concrete Apron
Remaining Road access
Hydrant Paving
Pedestrian walkway

Remaining lighting pole fdn & equipment

WWF and Backfill done for Pedestrian


NO Risk Mitigation PIC Target Status

1 Pedestrian Walkway for - Additonal new Manpower HANDRIANSYAH 14 Jan 22 Open


New Filling & Concrete
Apron

2 Lighting Pole Foundation in - Precast installation, Pulling cable HANDRIANSYAH 05 Jan 22 Open
east side Fence

3 Soil relocation to laydown - Dumtruck,Readiness laydown HANDRIANSYAH 10 Jan 22 OPen

4 Road Marking Delivery Equipment earlier HANDRIANSYAH 07 Jan 22 Open


53-N-B-002 Architecture in New Filling Building 06 Jan 22

DESCRIPTI INSTALLE REMAIN TARGET SPV /SI


02 NO QTY
ON D ING FINISH
03 03
Metal Sheet
Corrugated Aziz
01 3402 m2 3350 m2 35 m2 DONE
Fascia & /Raya
Siding
03
Aluminium Aziz
02 47 Nos 45 Nos 2 Nos 06 Jan 22
Louvre /Raya

03 Roll Up Door,
Steel Door,
Aziz
03 single Swing 13 Nos 7 6 Nos 15 Jan 22
/Raya
Door: ETA 5
JAN 22

Remaining
Will explain Aziz
04 Epoxy Work 2429 m2 1669 m2 760 m2
6,2 03
friday /Raya

Line Marking
03 North Side 15 Jan 22
05 in Staging As per drawing
(migration area) Aziz/Raya
Area

As per drawing
06 Hard Barrier 0
15 Jan 22 Aziz/Raya
03
Convective
07 Mirror and 14 0 14
15 Jan 22 Dafid
Signage

03
HVAC Installation
06 Jan 2022

LEGEND

Tray & Pulling Cable Done


Remaining Pulling Cable
Scaffolding & Support installed

Roof Fan Installed

1 NO Risk Mitigation PIC Target Statu


s
2 1 HVAC Roof -- Closely Monitoring Andy K 15 Jan Open
Fan Panel Fabrication 22
impact to 2 -- Start Installation Roof fan
Small BLD 1st

-FAT 15 Jan 22
-Installation 2 week
-SAT Complete 31 Jan 22

9
53-N-M-201 DOCK LEVELER READINESS 06 Jan 22

REMAI TARGET Remark


NO DESCRIPTION QTY INSTALLED
NING FINISH

JGC & SHELL Close


SAT 12 Jan
1 inspection Check 6 Nos 4 Nos 0 Punch C
22
(Construction) before SAT

Cleaning all
Readiness Area for
H-3320 2 4 Nos material, install
SAT
Grating

H-3319
3 ITR Close 4 ITR 0 4 ITR 10 Jan 22

4 Desktop Readiness 11 Jan 22


6,2

5 SAT Dock Leveler 12 Jan 22

H-3318

H-3317 03
53-N-M-201 EDSS READINESS
06 Jan 22

REMAININ TARGET Remark


NO DESCRIPTION QTY INSTALLED
G FINISH

Installation 1st Conveyor


1 batch for 3352 18 Conv 1 17 15 Jan 22 ETA 06
Comm’s Jan 22

Installation Gantry COL : 18 COL : 14 COL : 4


Partial
2 (Column & BEAM :16 BEAM :0 BEAM :16 15 Jan 22
RAIL 16 Delivery
01
Beam(2nd Prioirty) RAIL : 0 RAIL : 16

Installation Panel ETA : 6


3 2 Nos 0 0 12 Jan 22
(Calling) JAN 22

Testing and Partial PIC


4 1 Package 16 Jan 22
6,2 SAT Nugroho

01

01

04
03

03
BUILDING WORK _ NEW FILLING BUILDING AREA 06 Jan 2022

Electrical in New Filling Building


TARGET SPV /SI
NO DESCRIPTION QTY INSTALLED REMAINING
FINISH

InstallationRG
Suyitno
01 S Conduit PR 165 m 165 0m 28 Dec 21
/Andy K
19

Tray Suyitno
02 475 m 475 m 0m 16 Dec 21
Installation /Andy K

Pulling cable(3 Suyitno


03 7200 m 7130 m 70 m 05 Jan 22
office, PR 19) /Andy K

Lighting fixture
256 Siswanto /
04 installation(pr1 251 Nos 05 Nos 05 Jan 22
Nos Andy K
9)

Panel
Siswanto /
05 installation & 4 Nos 4 Nos 0 Nos 20 Dec 21
Andy K
energize

Grounding & 05 Jan


110 110 Nos Siswanto /
06 Lightning 0 Nos 22( hsse
Nos Andy K
Protection (life line)

Switch Installed
LEGEND
lighting fixture installed included
lighting fixture installed
termination

Tray Installed Testing ON


Fire Alarm Installation
06 Jan 2022

TARGET SPV /SI


NO DESCRIPTION QTY INSTALLED REMAINING
FINISH

Fire Alarm Siswanto /


01 50 50 0 DONE
Tray in staging Andy K

Fire Alarm
Conduit Siswanto /
02 216 m 66 m 150 m 10 Jan 22
Installation Andy K
RGS)

Fire Alarm Siswanto /


03 3624 m 3500 m 124 m 12 Jan 22
Pulling cable Andy K

Fire Alarm Siswanto /


04 46 Nos 5 41 Nos 14 Jan 22
Devices Andy K

NO Risk Mitigation PIC Target Statu


s

1 Delay for -Additional manpower for Andy K 15 Jan Open


RGS RGS installation , From 22
Installation PRO only 6. NEED to
RGS improve : 10 Person
Conduit

LEGEND

Tray & Cable already installed

Remaining Tray

13
53-N-B-005-PIPING WORK _ NEW FILLING BUILDING AREA
Hose reel installation

Update as of 06 Jan 22

TARGET SPV /SI


NO DESCRIPTION QTY INSTALLED REMAINING
FINISH

Pipe
01 270 ID 270 ID 0 DONE Sunaryo
Installation

Open(Modifica
Hose rail tion during
02 4 Nos 4 Nos 0 Sunaryo
installation Traffic Meeting
with OPS)

Hydrotest- Sunaryo
03 270 ID 0 270ID 09 Jan 22
Closing Punch /Nurul

Desktop
04 46 Nos 5 41 Nos 12 Jan 22 Baktiar
Readinrss

05 SAT Hose reel 4 Nos 0 4 Nos 14 Jan 22 Rizal


Telecom Work in New Filling Building Status as of 06 January 2022
Update as of 06 Jan 22
NEW FILLING BUILDING AND NEW STAGING (INCLUDE LABEL PRINTING ROOM, COMPRESSOR AND NEW OFFICE)
To ta l PHOTO
NO Re m a ining Wo rk Ite m UNIT To ta l Qty Insta lle d Re m a ining Ta rg e t Finish Re m a rk
Ma np o we r 1. Install Telecom Cable Way 70 Meter

1 ITRa c k Se t 3 1 2 13-Ja n-21 Wa itin g Re a d ine ss o f


2 C a b le to th e ITRa c k
5,2 M e te r 12 4 8 14-Ja n-21 La b e l Printin g Ro o m
3 Te rmina tio n Ha rd Wire C a b le a t IT Po in t 24 8 16 15-Ja n-21 re a d y a n d Ne w
4 Te rmina tio n Fib e r O p tic a t ITRa c k C o re 160 96 64 15-Ja n-21 O ffic e
5 C C TV C a me ra Se t 8 6 2 13-Ja n-21 Wa itin g Re a d ine ss o f
6 C C TV C a me ra C a b le M e te r 625 500 125 14-Ja n-21 La b e l Printin g Ro o m
7 C C TV C a b le Te rmina tio n Po in t 16 11 5 15-Ja n-21 re a d y a n d Ne w
8 PAG A Sp e a ke r Se t 18 13 5 15-Ja n-21
9 PAG A Sp e a ke r JB Se t 9 7 2 12-Ja n-21
10 PAG A Sp e a ke r C a b le M e te r 650 450 200 13-Ja n-21
Wa iting La b e l
11 PAG A Sp e a ke r C a b le Te rmin a tio n Po in t 18 14 4 14-Ja n-21
Printin g Ro o m re a d y
a nd Ne w O ffic e
10 PAG A C a ll Sta tio n Se t 2 1 1 12-Ja n-21
Re a d y
10 PAG A C a ll Sta tio n Ac c o u stic Ho o d Se t 1 1 0 12-Ja n-21
6 Pe rso n
10 PAG A C a ll Sta tio n C a b le M e te r 300 120 180 13-Ja n-21
11
6,2
PAG A C a ll Sta tio n C a b le Te rmina tio n Po in t 4 1 3 14-Ja n-21
Wa iting La b e l
12 Wire le ss a c c e ss p o in t Se t 14 14 0 12-Ja n-21
Printin g Ro o m re a d y
13 Wire le ss a c c e ss p o int C a b le M e te r 1200 1200 0 13-Ja n-21 a nd Ne w O ffic e
14 Wire le ss a c c e ss p o int C a b le Te rmina tio n Po in t 28 16 12 14-Ja n-21 Re a d y
15 Te le p h o n e M DF Se t 1 1 0 12-Ja n-21
Wa iting La b e l
15 Te le p ho n e Ha n d se t Se t 4 1 3 12-Ja n-21 Printin g Ro o m re a d y

16 Te le p ho n e C a b le M e te r 600 500 100


8,1 – 8,6 13-Ja n-21
a nd Ne w O ffic e
Re a d y
17 Te le p h o ne C a b le Te rmina tio n Po in t 10 2 8 14-Ja n-21
18 Se c u rity Pa tro l Pa ne l Se t 1 0 1 12-Ja n-21 Wa iting La b e l
18 Se c u rity Pa tro l C a rd Re a d e r Se t 5 2 3 12-Ja n-21 Printin g Ro o m re a d y
19 Se c u rity Pa tro l C a b le M e te r 500 500 0 13-Ja n-21 a nd Ne w O ffic e
20 Se c urity Pa tro l C a b le Te rmin a tio n Po in t 12 2 10 14-Ja n-21 Re a d y
21 Te le c o m C a b le Wa y Tra y a n d C o nd u it M e te r 1500 900 600 14-Ja n-21
21 Q C Che c k 0 15-Ja n-21
22 SAT 0 16-Ja n-21
23 0
24 0
TO TAL 5725 4371 1354
PERCENTAGE 100% 76% 24%
Electrical Work in New Filling Building
Update as of 06 Jan 22
Status as of 06 January 2022
NEW FILLING BUILDING AND NEW STAGING (INCLUDE LABEL PRINTING ROOM, COMPRESSOR AND NEW OFFICE)
5,2 NO Re m a ining Wo rk Ite m UNIT To ta l Qty Insta lle d Re m a ining
To ta l
Ta rg e t Finish Re m a rk
Ma np o we r
1 DB Pa n e l Pn l 3 3 0 30-De s-21
2 LC P fo r Do c k Le v e le r Pn l 6 4 2 30-De s-21 w a iting e xistin g
3 We ld in g O u tle t & So c ke t O utle t Pn l 6 6 0 30-De s-21 w a itin g c iv il
12 Pe rso n
4 C a b le Wa y Me te r 645 645 0 24-De s-21
5 C a b le Pu llin g Me te r 4139 4000 139 08-Ja n -22
6 Te rmin a tio n Po in t 63 58 5
0
0
TO TAL 4862 4716 146
PERCENTAGE 100% 97% 3%

6,1

6,2

Legend :
: Cable Tray & cable Installed
: LCP Panel Installed
: Socket Battery charging include pulling cable
termination Done
Instrument Work in New Filling Building
Update as of 05 Jan 22

NO Description Total Qty Installed Remaining Remarks


5,2 1 Main Cable Ladder (M) 90 90 0

Remaining for
Relocated Drum
2 Perforated Tray (M) 754 704 50
Line (U3350 &
U3351)

3 Remote IO (unit) 3 3 0
4 Install JB (unit) 4 4 0
5 JB-PLS & JB-DVP (unit) 12 12 0
6 Control Box (unit) 4 2 2 (*)

7 Pulling Main Cable (M) 6815 6815 0


8 Pulling Secondary Cable (point) 58 58 0
9 Glanding Cable & Termination (point) 116 100 16 (**)
6,2 10 IA Line (point) 51 51 0

344 (incl. SOFT


11 Loop Test (loop) 400 (incl. SOFT IO) 58 Loops (#)
IO)

Will be installed
12 Install DPI (***) 12 0 12 after filter
handover
8,1 – 8,6
13 Install Lubcel PC (****) 2 0 2

Note :
1. (*) Remaining Control Box for Relocated Drum Line (U-3350 & U-3351)
2. (**) Cable for Relocated Drum Line (U-3350 & U-3351) already pulled and coiled on pipe rack, will be termination after drum lines
relocated
3. (***) Priority for U3352 & U3360 (5 ea) and remaining (U3350 & U3351 will be installed after the filling line relocated
4. (****) Will be installed after filling line completed (Lubcel PC supplied by Shell)
5. Loop check for Drum Line on progress (by ABB)
(#) Priority for Drum Line (U-3352)
Cleaning Area & Dismantling Scaffolding New Filling Building
Legend

Scaffolding area
5,2 Touch-up paint FW line Touch-up paint FW line
Cover tray (Electrical & FA BLD Cover tray (Electrical & FA BLD)
Install Beam Detector & Termination MCP Scaffolding dismantle

Cleaning Area

MCP termination cable

Line Check Piping


Cover tray HVAC Panel )

6,2

Termination Cable for inbound

Replacement PPR pipe

Touch-up paint FW line


Cover tray (Electrical & FA BLD
Install Beam Detector & Termination MCP
Remaining
Material No Description ETA CRD REMARK
Concern
Handrail for Hard barrier,Nort Paving,Office BLD,
1
Label Printing 05 Jan 21 02 Jan 22 Partial delivery

2 Rool Up door RD 7Unit 05-Jan-22 22-Dec-21 2 nos for Workshop & south side, 5 Nos ETA :

3 Fire Extinguisher, 15 Jan 22 20-Dec-21 Class ABC 15 Jan 2022,

4 Conveyor, Bulk material,Panel 06 Jan 22 31 Dec 21 05 Jan 22 Beam Delivery : 14 Nos Beam

5 Convective Mirror & Vsignange Door 14 Jan 22 15 Jan 22 Under Purchasing

6 PVC for connecting Downspout to Ditch 07 Jan 22 08 Jan 22 Under Purchasing

Item Concern
COMPRESSOR_ NEW FILLING BUILDING AREA
Update as of 06 Jan 22

SPV /SI
NO DESCRIPTION QTY INSTALLED REMAINING TARGET FINISH

01 Paving 1 SECTION 0 0
11 Jan 22

PAGA System:
1. Horn 1 ea 0 ea 1 ea
Speaker 1 ea 0 ea 1 ea
02 2. JB Speaker 1 ea 0 ea 1 ea
3. Telephone 1 ea 0 ea 1 ea
Analog
4. SAT

Fire Alarm:
6 ea 6 ea 0 ea
1. HD
Installation
1 ea 1 ea 0 ea
03 2. MCP
1 ea 1 ea 0 ea
3. AAF/VAF
1 ea 0 ea 1 ea
4. JB (460-JE-
306)
New Filling Strategy Handover

Handover 17 Jan 22

21
Thank You
53-N-B-005-PIPING WORK _ NEW FILLING BUILDING AREA
Update as of 22 Dec 21

Hose reel installation

Remaining 1 Fire hose reel for installation


Meeting Outline
FAT Conveyor EDSS &
Proposal Conveyor Delivery • FAT plan
• Conveyor system installation and SAT
• Operation of U3352
• Installation of gantry system
• SAT of complete system (conveyor and 
gantry)
• interfere with the relocation schedule of
U3350/51
EDSS Schedule for interconnecting with 3352,3350,3351
Time Line EDSS
Status and Plan

Dec-21 Jan-22 Feb-22


No Activity Start Finish
20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Operation 3352
1 Remaining Conveyor Delivery D-11,D-12,D-13,D-22,D-26 TBC TBC
2 Motor Sliding Gate: Delivery TBC TBC
3 Panel EDSS Delivery TBC TBC
4 Conveyor Unit installatin (excluded D-11,D-12,D-13,D-22,D-26) 29-Dec-21 04-Jan-22
5 Main Control Pnael Instalaltion 05-Jan-22 07-Jan-22
6 E/I Installation & Termination 08-Jan-22 12-Jan-22
7 Leveling & Tightening 12-Jan-22 14-Jan-22
8 Inspection & Commisoning 15-Jan-22 16-Jan-22

Operation 3350.3351 & SAT EDSS


1 Delivery Non FAT Coloumn ITEM 30-Dec-21 30-Dec-21
2 Delivery Non FAT Rail and Beam Item 05-Jan-22 05-Jan-22
3 Servo Motor Delivery 15-Jan-22 15-Jan-22
4 FAT 20-Jan-22 21-Jan-22
5 Punch & Delivery to Murinda 22-Jan-22 31-Jan-22
6 Painting @Murinda 01-Feb-22 06-Feb-22
7 Delivery FAT Item 07-Feb-22 07-Feb-22
8 Erection Column Non FAT Item 31-Dec-21 06-Jan-22
9 Erection Rail and Beam Non FAT Item 07-Jan-22 08-Jan-22
10 Erection Column FAT Item 08-Feb-22 09-Feb-22
11 Erection Rail and Beam FAT Item 09-Feb-22 09-Feb-22
12 Main Control Panel Instalaltion 10-Feb-22 12-Feb-22
13 E/I Installation & Termination 13-Feb-22 17-Feb-22
14 Leveling & Tightening 18-Feb-22 20-Feb-22
15 Inspection 21-Feb-22 21-Feb-22
16 SAT EDSS 22-Feb-22 28-Feb-22
FAT PLAN: EDSS SYSTEM
SIMULATION SCENARIO
b. Storing Process
Scenario
b1. 5 drums in row
B2. Stacking 3-2-1

GANTRY WITH CONVEYOR


PROPOSE PLANT FAT
ORIGINAL PLANT FAT

D17
2
6
FAT PLAN: EDSS SYSTEM
SIMULATION SCENARIO
b. Scenario Storing
Process b1. 5 drums in a row b2. Stacking 3-2-1

Conv. D17 Conv. D17


FAT PLAN: EDSS SYSTEM
SIMULATION SCENARIO
c. Supply Process
Scenario c1. From 5 drums in row
c2. From stacking 3-2-1

GANTRY WITH CONVEYOR


PROPOSE PLANT FAT
ORIGINAL PLANT FAT

D17
2
8
FAT PLAN: SCHEDULE
 21-22 Dec 21 : FAT Conveyor System
 28 Dec 21 : PO new servo motor
 27-31 Dec 21 : Continue trial program with old servo motor
 03-07 Jan 22 : Repair girder box
 17 Jan 22 : new servo motor arrived at IMK workshop
 17-20 Jan 22 : Install new servo & preparation FAT
 21 Jan 22 : FAT Gantry System
 22-28 Jan 22 : Closing Punch list
 29 Jan 22 : Delivery remaining EDSS
Conveyor system installation and SAT No

1
Description

Servo Motor Delivery


Start

28 Dec 21
Finish

15 Jan 2022

2 FAT 20 Jan 22 21 Jan 22

3 Punch & Delivery to 22 Jan 22 31 Jan 22


Murinda

4 Painting @Murinda 01 Feb 22 06 Feb 22

5 Delivery to site 07 Feb 22 07 Feb 22

6 Site Installation &SAT 08 Feb 22 26 Feb 22


• Operation of U3352 (readiness Conveyor) No Description Start Finish

1 Remaining Conveyor
Delivery

2 Panel delivery

3 Installation Conveyor &


panel

4 Installation EI

5 Testing

Legend
Remaining Conveyor
Installation of gantry system

1. 1.The Access coming from East side door new filling Building
2. Material and erection by TMC 6 tons
1. Before installation QC Check padding installation
2. 2.Erection for column start from East Side
No Description Start Finish

1 Material Delivery EDSS 30 Dec 21 30 Dec 21


Column

2 Erection Column 31 Dec 21 04 Jan 22

3 Erection for Beam and 05 Jan 22 08 Jan 22


Rail
Electrical Work in New Filling Building
Update as of 27 Dec 21
NEW FILLING BUILDING AND NEW STAGING (INCLUDE LABEL PRINTING ROOM, COMPRESSOR AND NEW OFFICE)
5,2 Tota l
NO Re m a ining Wo rk Ite m UNIT To ta l Qty Insta lle d Re m a ining Ta rg e t Finish Re m a rk
Ma np o we r
1 DB Pa ne l Pnl 3 2 1 30-De s-21
2 LC P fo r Do c k Le v e le r Pnl 6 6 0 30-De s-21 w a iting e xisting
3 We ld ing O utle t & So c ke t O utle t Pnl 6 5 1 30-De s-21 w a iting c iv il
12 Pe rso n
4 C a b le Wa y Me te r 645 559 86 24-De s-21
5 C a b le Pulling Me te r 4139 3251 888 30-De s-21
6 Te rmina tio n Po int 63 40 23 30-De s-21
0
0
TO TAL 4862 3863 999
6,1 PERCENTAGE 100% 79% 21%

6,2

Legend :
: Cable Tray & cable Installed
: LCP Panel Installed
: Socket Battery charging include pulling cable
termination Done