PROJECT: Air Product Project -Neom

DURATION:
WORK PACKAGE SUMMARY
SL. NO. PRIORITY BLDG TAG PARCEL DESCRIPTION PARCEL # DISCIPLINE DISC CODE CODE WORK PACKAGE WORK PACKAGE DESCRIPTION REMARKS

01 1 01 I 01 01I01 Mobilization
Indirect Manpower, Design Services, Safety, Office Supply, Pantry Supply and
02 1 INDIRECT 01 INDIRECT I 02 01I02 Site Running Cost
Others
03 1 01 I 03 01I03 Demobilization
SUB-TOTAL
04 1 02 C 01 02C01 Substructure ( Earthworks ,Concrete & Waterproofing from SOG and below)
05 1 02 C 02 02C02 Super Structure (Concrete above SOG + Masonry+ PEB & S.Panel)
CIVIL
06 1 02 C 03 02C03 Finishing Works (Floor,Wall Ceiling Finishes)
07 1 02 C 04 02C04 Furnishing & Equipment ( Overhead Crane & Kitchen Appliances/Equipment)
09 1 02 M 01 02M01 Mechanical Works 1st & 2nd Fix ( Piping , Valves & others)
900-B917

CELL ASSEMBLY
10 1 02 MECHANICAL M 02 02M02 Mechanical Works Final Fix (Toilet Acc.,Equipment & Fixtures) 900-B917 CELL ASSEMBLY WORKSHOP BLDG
WORKSHOP BLDG.
11 1 02 M 03 02M03 Mechanical Works Testing & Commisioning
12 1 02 E 01 02E01 Electrical & Low Current Works 1st & 2nd Fix ( Piping , Wiring , Panel Board & Acc., Trays and others)
13 1 02 E 02 02E02 Electrical Works Final Fix ( Fixture, Switch, Equipment & Outlet)
ELECTRICAL
14 1 02 E 03 02E03 Low Current Works Final Fix ( Switch, Instrument & Equipment)
15 1 02 E 04 02E04 Electrical Works Testing & Commisioning
16 2 03 C 01 03C01 Substructure ( Earthworks ,Concrete & Waterproofing from SOG and below)
17 2 03 C 02 03C02 Super Structure (Concrete above SOG + Masonry+ PEB & S.Panel)
CIVIL
18 2 03 C 03 03C03 Finishing Works (Floor,Wall Ceiling Finishes)
19 2 03 C 04 03C04 Furnishing & Equipment ( Overhead Crane & Kitchen Appliances/Equipment)
20 2 03 M 01 03M01 Mechanical Works 1st & 2nd Fix ( Piping , Valves & others)
900-B901

21 2 Central Control Building 03 MECHANICAL M 02 03M02 Mechanical Works Final Fix (Toilet Acc.,Equipment & Fixtures) 900-B901 Central Control Building
22 2 03 M 03 03M03 Mechanical Works Testing & Commisioning
23 2 03 E 01 03E01 Electrical & Low Current Works 1st & 2nd Fix ( Piping , Wiring , Panel Board & Acc., Trays and others)
24 2 03 E 02 03E02 Electrical Works Final Fix ( Fixture, Switch, Equipment & Outlet)
ELECTRICAL
25 2 03 E 03 03E03 Low Current Works Final Fix ( Switch, Instrument & Equipment)
26 2 03 E 04 03E04 Electrical Works Testing & Commisioning
27 3 04 C 01 04C01 Substructure ( Earthworks ,Concrete & Waterproofing from SOG and below)
28 3 04 C 02 04C02 Super Structure (Concrete above SOG + Masonry+ PEB & S.Panel)
B903,B906,B101,B220,B203,B902

CIVIL BDLG. INCLUDED:


29 3 04 C 03 04C03 Finishing Works (Floor,Wall Ceiling Finishes)
1- (100-B101) Operator Building for ASU
30 3 04 C 04 04C04 Furnishing & Equipment ( Overhead Crane & Kitchen Appliances/Equipment)
2- (200-B220) Operator Building for Hydrogen
31 3 04 M 01 04M01 Mechanical Works 1st & 2nd Fix ( Piping , Valves & others)
3- (261-B203) Operator Building for Ammonia Generation Unit
32 3 Operation Buildings 04 MECHANICAL M 02 04M02 Mechanical Works Final Fix (Toilet Acc.,Equipment & Fixtures)
4-(900-903) Canteen
33 3 04 M 03 04M03 Mechanical Works Testing & Commisioning
5- (900-B902) Administration Building
34 3 04 E 01 04E01 Electrical & Low Current Works 1st & 2nd Fix ( Piping , Wiring , Panel Board & Acc., Trays and others)
6- (900-B906) Maintenance Workshop
35 3 04 E 02 04E02 Electrical Works Final Fix ( Fixture, Switch, Equipment & Outlet)
ELECTRICAL
36 3 04 E 03 04E03 Low Current Works Final Fix ( Switch, Instrument & Equipment)
37 3 04 E 04 04E04 Electrical Works Testing & Commisioning
38 4 05 C 01 05C01 Substructure ( Earthworks ,Concrete & Waterproofing from SOG and below)
B911,B910,B908,B912,B913,B920,B801B

39 4 05 C 02 05C02 Super Structure (Concrete above SOG + Masonry+ PEB & S.Panel) BDLG. INCLUDED:
CIVIL
40 4 05 C 03 05C03 Finishing Works (Floor,Wall Ceiling Finishes) 1- (900-B908) Security Control Building
41 4 05 C 04 05C04 Furnishing & Equipment ( Overhead Crane & Kitchen Appliances/Equipment) 2- (900-B910) Visitor Centre Main Gate Security building
42 4 05 M 01 05M01 Mechanical Works 1st & 2nd Fix ( Piping , Valves & others) 3- (900-B911) Main Gate Guard House
802

43 4 Security Buildings 05 MECHANICAL M 02 05M02 Mechanical Works Final Fix (Toilet Acc.,Equipment & Fixtures) 4- (900-B912) Internal Gate Security House
44 4 05 M 03 05M03 Mechanical Works Testing & Commisioning 5- (900-B913) Internal Gate Guard house
45 4 05 E 01 05E01 Electrical & Low Current Works 1st & 2nd Fix ( Piping , Wiring , Panel Board & Acc., Trays and others) 6- (900-B923) Preliminary Inspection and Check Point Building
46 4 05 E 02 05E02 Electrical Works Final Fix ( Fixture, Switch, Equipment & Outlet) 7- (800-802) Jetty Guard House
ELECTRICAL
47 4 05 E 03 05E03 Low Current Works Final Fix ( Switch, Instrument & Equipment) 8-(800-B801) Jetty Guard House
48 4 05 E 04 05E04 Electrical Works Testing & Commisioning