TEMPORARY CONSTRUCTION FACILITY


TCF-1
Date: 10/03/2021
Sr. TOPICS PHOTO/ DETAILS Direct Manpower: 90
No Indirect Manpower: 25
1 TOOL BOX TALK

(a) Distracted Driving,


Traffic rules and
regulations, PPEs
and Housekeeping.

2 WORK PERMIT
Total No of Permit. 17 Sr. Work Equipment’s/Tools Hot Work Permit Manpower Company
(a) Cold Work Permit No Permit
= 04 No.
(b) Hot Work Permit
=11 1 0009 Drill machine, JCB, Compactor. Drilling work for sum pit and Drain 03 Advanced elements
chamber, Shuttering work for switch gear
(c) Lifting Permit Ramp.
=01 2 0010 Bobcat, compactor, JCB Backfilling compaction work for gathering 03 Advance Elements
(d) Confined space tent grade slab.
=01 3 0012 Grinder and Hand tools. Walkway curve stone &Interlock repair 05 Hexagon
work.
4 0014 Gas Tester, SCABA and Hand tools. Scaffolding erection work inside the Fuel 04 Advanced Elements
tanks.
5 0015 JCB and Hand tools. Excavation, Pipe laying and Backfilling for 10 Hexagon
Irrigation system.
6 0016 Mobile crane hand tools, Water Well Pump installation work. 07 Al-Aswad
[Type here]

7 0017 Mixer machine and Hand tools. Block work for car wash Building in fuel 03 Sawad-Al-Bander
station.
8 0018 Hand tools. Termination work for Light poles in camp 03 Hexagon
area.
COLD WORK

9 0692 Walkway curve stone &Interlock Hand tools 03 Project Lines


repair work.
10 0693 Rebar work for Diesel tank grade slab Hand Tools 02 Advance Elements
and Ramp.
11 0698 Walk way Inter-lock installation Hand Tools 02 Hexagon
work.
CONFINED SPACE

12 0369 Gas Tester, SCABA and Hand tools. Scaffolding erection work inside the Fuel 04 Advanced Elements
tanks.
LIFTING PERMIT

13 0320 Water well pump installation work. Mobile Crane, Mechanical Jacks. 07 Al-Aswad
[Type here]

3 Daily Activities
Backfilling compaction work for gathering tent grade slab. Termination line leak rectification.

Walkway curve stone &Interlock repair work. Grinding works for A/C foundation chamfer.
Backfilling, leveling compaction for light pole foundation. Walkway curve stone &Interlock repair work.
Well Existing Pump installation work. Rebar work for Diesel tank grade slab and Ramp.
4 HEIGH RISK
ACTIVITIES
5 ACHIVEMENT ZERO INCIDENT/ ACCIDENT

6 LOOK AHEAD Water well existing pump removal in Playground area .Hand Rail Installation for the Kitchen &Clinic, Excavation for the 15 m Gate foundation
ACTIVITEIS near to the helipad, Swimming Pool Plastering, Interlock and curbstone work, Gathering Tend foundation backfilling, Housekeeping laydown area,
Backfilling and leveling for Around STP Area, Backfilling and leveling roads and sport area, Backfilling for inside the roundabout, RO
{LIGHTING , POWER SOCKETS & FIRE ALARM}, Grounding connection for the AC, INSTALLATION OF STREET LIGHTING POLES
{OFFICE}, INSTALLATION OF STREET LIGHT POLES IN PLAYGROUND 25 MTR, CLOSING OF EIL COMMENTS AND OPEN RFI'S,
Irrigation water tank commissioning, Spindle Surface cover installation transmission & force main line, Kitchen commissioning(Air balancing for
Duct& Exhaust fans), A/C Rectification and inspection, Diesel Tank flushing with Diesel, Potable water supply installation for STP, Fire
networking commissioning with overall network, Inspection Chamber Installation for STP.
7 MAJOR INCIDENT/
NEAR MISS
[Type here]

8
CONCERN & ISSUES CONSTRUCTION

9 Safety
1. Sabre Alam 3. Asif Ali (Approved)

2. Hafiz Sher dil 4 Imran Gul(Approved)

10 TCF- 1 Project/ Sign:


Construction Manager