Authority:
Client Engineer:
Contractor Consultant:
Date Date
01-11-2021
OSOOL POULTRY S.A.O.C./ TANWEER/ SEMAC & PARTNERS L.L.C.
Reviewed by Approved by Stamp/Seal
Name Name
Designation Designation
Signature Signature
Date Date
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE
INDEX
S No. DESCRIPTION PAGE No.
1.0 Purpose 03
2.0 Applicable Specifications & Standards 03
3.0 Tools & Tackles 03
4.0 HSE
4.1 Hazard Identification 03
4.2 Action by execution team 03
4.3 First Aid 04
5.0 Responsibilities
5.1 Construction Manager 04
5.2 Site Engineer 04
5.3 Electrical Supervisor 05
5.4 Safety Adviser 05
5.5 QC Inspector 05
6.0 Installation Procedure
6.1 Receipt, Handling and Storage 06
6.2 Erection/Installations 06
a Structures 06
b Base Assembly 06
c Insulators 07
d Contacts Assembly (Male and Female Assembly) 07
e Connecting Disconnector 07
f Tandem Pipe Assembly 08
g Earth Switch Assembly 08
6.3 Do’s, Don’ts and Special Precautions 09
7.0 Documents & Records 09
Page 2 of 9
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE
1.0 PURPOSE
The purpose of this method statement is to provide the guidelines for 132 kV ISOLATOR
INSTALLATION WORKS and associated activities to satisfy all the relevant specifications and
requirements.
Scope of work.
Manufacturers Instruction Manual
Issued Method Statement
Tender Specification & Standards
Approved MAS
Approved MRDR
4.0 HSE
Tripping Hazard
Trappinghazard
Unguarded opening
Working at height
Falling objects
Inertia of large object
Lifting equipment failure
Beware of objects falling from above the worksite. Take care not to drop objects when
working at height.
Ladders (when used) to be secured.
Lifting is to be stopped if the load cannot be seen clearly.
Competency certificate of the lifting tools shall be available at site during the erection
work.
Unautorized persons shall not be allowed to work near the lifting area.
Only essential work at height to be carried out in darkness. All hazards to be assessed
before starting work.
Tools and equipment to be secured to avoid their being dropped.
Sufficient number of first boxes & third party certified first aiders will be present at site, at
the time of work.
5.0 RESPONSIBILITY
Ensuring that the quality of materials and installation of work are in accordance with the
criteria identified for the project.
Receiving of all relevant information regarding design, drawings, and engineering.
Implement all aspects of the Project Quality Management System.
Implement all HSE aspects related to the Project.
Reviewing the manpower requirements for the project.
Attending meetings with the Engineer / Owner
Site engineer shall be overall responsible for the safe execution of complete Activity including but
not limited to.
Organizing tools and equipment required for the work.
Assigning work crew.
Confirming the materials-handling in safe manner.
Ensure all materials are inspected prior to utilizing at site.
Ensure the availability of required technical documents like approved method statement,
IFC Drawings at workplace.
Page 4 of 9
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE
Responsible for carrying out Stage inspections in accordance with ITP and as per the
project requirement.
Ensure the work is done by the qualified person.
Responsible for ensuring the all the Testing activities are as per project requirement.
The supervisor shall be responsible for the safe execution of the following: -
Toolbox talks given prior to commencing of the day's work.
Assigning a competent work crew (details of the activity and task information shall be
given to the work crew).
Organizing tools and equipment required for the work.
Confirm the work is being carried out as per the work procedure (Installation Instruction
manual).
The safety advisor shall be responsible for safe work execution at site.
5.5 QC INSPECTOR
Page 5 of 9
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE
Update & main the tracking sheet of all measuring & monitoring equipment along with
their calibration details.
Update & maintain inspection records.
Coordinate with the client and Site In-charge for inspection.
Ensure adherence to all procedures.
All packages are to be carefully opened and verified for damages and shortages, if any.
These shortcomings have to be properly intimated to the manufacturer as well as to the
Insurance authorities as the case may be.
Handling of large crates should be handled by crane carefully.
All items should be stored on ramps/platforms, free from water logging.
All items should be stored in upright position only.
Insulators are to be stored separately to avoid breakages.
6.2 Erection/Installations
a. Structures
Refer the site layout drawings and compare with equipment General Assembly Drawing.
Identify the structures according to the General Assembly Drawing
Structure assembly is lifted and fixed over the plinth (Without damaging the foundation
bolts)
Assemble washer, spring washer and nuts in all foundation bolts.
Check for level at the top of the structure in both directions by using spirit levels. If
required give shims below the base plate of structure and tighten the nuts.
All other structures should be assembled in similar way.
b. Base Assembly
Identify the Base Assembly from Equipment General Assembly drawing.
Lift the base assembly by using proper ropes and place it over the relevant structure
After keeping it over the base without removing the rope align it to the mounting hole of
base and top plate of structure and fix the bolts and nuts and remove the rope.
Check for level of flanges in both direction by using spirit level.
If necessary, add shims below the leg of the base and align it.
Tighten all the Bolts.
Repeat the installation process for other two poles also.
Ensure the Centre line of same pole and centre line of other phases are aligned.
After completing the installation keep all the base assemblies in open position.
Page 6 of 9
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE
c. Insulators
The top middle and bottom units of Insulators should be identified by using Insulator
Drawing.
The bottom and middle units are assembled together by using proper bolts and nuts.
Lift the Insulator stack by using proper hook and placed over the base assembly by
ensuring the top 4 holes position.
Without removing the hook align the holes and fix all bolts.
The level of top surface of insulator should be checked by spirit level/plumb and if
necessary, the shims should be inserted below the bottom flange of the insulator or/and
between two insulator unit flanges.
Now rotate the shaft assembly & check for the rotation of insulator & its eccentricity.
The same procedure is to be repeated for the other side of same pole also
In the same way the top unit of insulator and middle unit are installed on both sides.
e. Connecting Disconnector
Manually set mechanism and disconnector to be connected into fully OPEN position
(Arrow mark on top of mechanism cabinet indicates the 'open' and 'close' positions).
Page 7 of 9
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE
If mechanical interlock keys are fitted, it will be necessary to obtain the relevant keys to
make mechanism operational.
Align the fixing hole and bolt them together to achieve desired tightness.
Ensure that the mounting channel on the drive and the structure are matching.
Level the box by placing the spirit level on output shaft flange in two directions.
Provide shim wherever required.
Check for centre line and verticality between torque bearing flange and drive flange with a
plumb.
Introduce Universal Coupling as called for in the General Arrangement Drawing.
Measure exact height between torque bearing flange and top of universal flange.
Cut the operating pipe with the specified clearance to facilitate smooth entry.
Weld the Vernier flange properly keeping the flange perpendicular to the centreline of the
pipe. Level and bolt the same. The drive is now ready for operation. Mounting angles of
mechanism to structure are slotted to provide horizontal adjustment. Adjust the
mechanism so that the vertical drive tube rotates TRUE.
Cabling (internal/external) be completed as per schematic drawing. Ensure that all
electrical interlocks are wired properly.
Before energising the circuitry, interlock wiring and control wiring should be checked by
multi meter (as per schematic drawings).
Attach counterbalance weights in pendulum arm at suitable hole and check the position of
Earth Switch which should be parallel to ground.
Manually move earthing blade towards closing position .To adjust add shims at the back of
the mounting plate to tilt the earthing blade in required direction.
Continue to move earthing blade towards closing and observe that the contact fingers
come into the fixed contact. A small adjustment to twist the contact fingers is possible by
shimming
mounting plate.
Continue to close earthing switch until contacts are fully engaged i.e. when the insulated
stop of the earthing blade comes to rest without straining against fixed contact.
Tighten all fixing bolts and keep the earth switch in closed position.
Page 9 of 9
Ref. No.: TLS-EL-CL-61-00
PROJECT
PROJECT COMPANY
CONTRACTOR
INSPECTION
Sl. Result
Description of the Checks
No A NA N/A
Proper unloading arrangement has been made at site
1
(Preferably with crane) to unload the packages.
2 All items have been checked with the packing list/DO.
After unloading the visual inspection of the packings has
3
been carried out
Any type of damage to the equipment/components during
4 transportation or any missing items has been brought to the
notice of the panel supplier.
Assembly drawings along with the installation and O&M
5
manual received.
6 Test certificate received for the switch.
Remarks / Observation
PROJECT
PROJECT COMPANY
CONTRACTOR
INSPECTION
Sl. Result
Description of the Checks
No A NA N/A
Site where isolator is to be erected is ready before the
1
starting of erection work.
Level of the structure assembly has been checked during
2
erection using spirit level
Site where isolator is to be erected is ready before the
3
starting of erection work.
Level of the top surface of isolators has been checked
4
during erection, alignment & level of equipment
5 Centre line of all the poles in different phases are aligned.
Centre line alignment of male & female assembly has been
6
checked
Before fitting, the crane rings have been identified for male
7
and female assembly
Moving parts have been operated 2-3 times for checking
8
the free movement
9 The rotation of motor is in right direction
In case it is in opposite direction the same has been
10 corrected by altering of the phase sequence of the motor
terminal.
11 Lifting of tandem pipe assembly is with proper size rope
During erection movement of earthing blade has been
12
checked
Page 1 of 2
Ref. No.: TLS-EL-CL-60-00
PROJECT
PROJECT COMPANY
CONTRACTOR
Page 2 of 2