EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL

AND 132/11KV TRANSFORMER YARD AT OSOOL POULTRY WITH PRIMARY SUBSTATION IN


WILAYAT HIMA GOVERNORATE
TENDER NO: 13/2020
Client:

OSOOL POULTRY S.A.O.C.

Authority:

TANWEER (RURAL AREAS ELECTRICITY COMPANY)

Client Engineer:

SEMAC & PARTNERS L.L.C.

Contractor Consultant:

WORLEY OMAN ENGINEERING L.L.C


Contractor

TRADE LINKS & SERVICES CO. LLC

METHOD STATEMENT FOR INSTALLATION OF 132 KV ISOLATOR


TLS Doc. No.: 13OS-E-2252-A4-00
TRADE LINKS & SERVICES Co. LLC
Prepared by Reviewed & Approved by Stamp/Seal
Name Name
B ANANTH NAIDU
Designation Designation
QA/QC Engineer
Signature Signature

Date Date
01-11-2021
OSOOL POULTRY S.A.O.C./ TANWEER/ SEMAC & PARTNERS L.L.C.
Reviewed by Approved by Stamp/Seal
Name Name

Designation Designation

Signature Signature

Date Date
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE

INDEX
S No. DESCRIPTION PAGE No.
1.0 Purpose 03
2.0 Applicable Specifications & Standards 03
3.0 Tools & Tackles 03
4.0 HSE
4.1 Hazard Identification 03
4.2 Action by execution team 03
4.3 First Aid 04
5.0 Responsibilities
5.1 Construction Manager 04
5.2 Site Engineer 04
5.3 Electrical Supervisor 05
5.4 Safety Adviser 05
5.5 QC Inspector 05
6.0 Installation Procedure
6.1 Receipt, Handling and Storage 06
6.2 Erection/Installations 06
a Structures 06
b Base Assembly 06
c Insulators 07
d Contacts Assembly (Male and Female Assembly) 07
e Connecting Disconnector 07
f Tandem Pipe Assembly 08
g Earth Switch Assembly 08
6.3 Do’s, Don’ts and Special Precautions 09
7.0 Documents & Records 09

Page 2 of 9
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE

132 KV ISOLATOR INSTALLATION

1.0 PURPOSE

The purpose of this method statement is to provide the guidelines for 132 kV ISOLATOR
INSTALLATION WORKS and associated activities to satisfy all the relevant specifications and
requirements.

2.0 APPLICABLE SPECIFICATIONS REFRENCE DRAWINGS & STANDARDS

 Scope of work.
 Manufacturers Instruction Manual
 Issued Method Statement
 Tender Specification & Standards
 Approved MAS
 Approved MRDR

3.0 TOOLS & TACKLES


 Lifting belts
 Hydraulic trolley
 Chain block
 Wrenches of appropriate size.
 Torque wrench

4.0 HSE

4.1 HAZARD IDENTIFICATION

 Tripping Hazard
 Trappinghazard
 Unguarded opening
 Working at height
 Falling objects
 Inertia of large object
 Lifting equipment failure

4.2 ACTION BY EXECUTION TEAM

 Ensure Barriers & Sign Boards are to be erected.


 Ensure Safety harness attached to a safe anchor point to be worn.
Page 3 of 9
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE

 Beware of objects falling from above the worksite. Take care not to drop objects when
working at height.
 Ladders (when used) to be secured.
 Lifting is to be stopped if the load cannot be seen clearly.
 Competency certificate of the lifting tools shall be available at site during the erection
work.
 Unautorized persons shall not be allowed to work near the lifting area.
 Only essential work at height to be carried out in darkness. All hazards to be assessed
before starting work.
 Tools and equipment to be secured to avoid their being dropped.

4.3 FIRST AID

 Sufficient number of first boxes & third party certified first aiders will be present at site, at
the time of work.

5.0 RESPONSIBILITY

5.1 CONSTRUCTION MANAGER

 Ensuring that the quality of materials and installation of work are in accordance with the
criteria identified for the project.
 Receiving of all relevant information regarding design, drawings, and engineering.
 Implement all aspects of the Project Quality Management System.
 Implement all HSE aspects related to the Project.
 Reviewing the manpower requirements for the project.
 Attending meetings with the Engineer / Owner

5.2 SITE ENGINEER

Site engineer shall be overall responsible for the safe execution of complete Activity including but
not limited to.
 Organizing tools and equipment required for the work.
 Assigning work crew.
 Confirming the materials-handling in safe manner.
 Ensure all materials are inspected prior to utilizing at site.
 Ensure the availability of required technical documents like approved method statement,
IFC Drawings at workplace.

Page 4 of 9
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE

 Responsible for carrying out Stage inspections in accordance with ITP and as per the
project requirement.
 Ensure the work is done by the qualified person.
 Responsible for ensuring the all the Testing activities are as per project requirement.

5.3 ELECTRICAL SUPERVISOR

The supervisor shall be responsible for the safe execution of the following: -
 Toolbox talks given prior to commencing of the day's work.
 Assigning a competent work crew (details of the activity and task information shall be
given to the work crew).
 Organizing tools and equipment required for the work.
 Confirm the work is being carried out as per the work procedure (Installation Instruction
manual).

5.4 SAFETY ADVISOR

The safety advisor shall be responsible for safe work execution at site.

 Ensure for effective toolbox talk.


 Ensure all the PPEs are available at site and all employees are using correct PPE.
 Conduct the emergency mock drills.
 Ensure the first aid box available at site
 Ensure that adequate fire extinguishers are available at site.
 Ensure the required warning signs and boards are available at necessary place'
 Ensure only required people are available at site

5.5 QC INSPECTOR

 Ensure that the method statement concerned to the work is approved.


 Ensure that the materials to be used in the work are inspected prior to the start of work.
 Ensure that all the required test certificates are available prior for start of the work.
 Remove all products and materials that fail to meet specifications to avoid their
unintended use.
 Report inspection and test data such as weights, temperatures, grades, moisture content,
and quantities inspected.
 Ensure stage inspections are done in line with the ITP.
 Ensure that all the measuring & monitoring equipment are calibrated.

Page 5 of 9
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE

 Update & main the tracking sheet of all measuring & monitoring equipment along with
their calibration details.
 Update & maintain inspection records.
 Coordinate with the client and Site In-charge for inspection.
 Ensure adherence to all procedures.

6.0 INSTALLATION PROCEDURE

6.1 Receipt , Handling and Storage

 All packages are to be carefully opened and verified for damages and shortages, if any.
These shortcomings have to be properly intimated to the manufacturer as well as to the
Insurance authorities as the case may be.
 Handling of large crates should be handled by crane carefully.
 All items should be stored on ramps/platforms, free from water logging.
 All items should be stored in upright position only.
 Insulators are to be stored separately to avoid breakages.
6.2 Erection/Installations
a. Structures
 Refer the site layout drawings and compare with equipment General Assembly Drawing.
 Identify the structures according to the General Assembly Drawing
 Structure assembly is lifted and fixed over the plinth (Without damaging the foundation
bolts)
 Assemble washer, spring washer and nuts in all foundation bolts.
 Check for level at the top of the structure in both directions by using spirit levels. If
required give shims below the base plate of structure and tighten the nuts.
 All other structures should be assembled in similar way.
b. Base Assembly
 Identify the Base Assembly from Equipment General Assembly drawing.
 Lift the base assembly by using proper ropes and place it over the relevant structure
 After keeping it over the base without removing the rope align it to the mounting hole of
base and top plate of structure and fix the bolts and nuts and remove the rope.
 Check for level of flanges in both direction by using spirit level.
 If necessary, add shims below the leg of the base and align it.
 Tighten all the Bolts.
 Repeat the installation process for other two poles also.
 Ensure the Centre line of same pole and centre line of other phases are aligned.
 After completing the installation keep all the base assemblies in open position.

Page 6 of 9
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE

c. Insulators
 The top middle and bottom units of Insulators should be identified by using Insulator
Drawing.
 The bottom and middle units are assembled together by using proper bolts and nuts.
 Lift the Insulator stack by using proper hook and placed over the base assembly by
ensuring the top 4 holes position.
 Without removing the hook align the holes and fix all bolts.
 The level of top surface of insulator should be checked by spirit level/plumb and if
necessary, the shims should be inserted below the bottom flange of the insulator or/and
between two insulator unit flanges.
 Now rotate the shaft assembly & check for the rotation of insulator & its eccentricity.
 The same procedure is to be repeated for the other side of same pole also
 In the same way the top unit of insulator and middle unit are installed on both sides.

d. Contacts Assembly (Male and Female Assembly)


 Identify the Assembly as per General Assembly Drawing
 Keep the Insulator corona ring on top of the Insulator
 Lift the Male Assembly by using proper sized rope and place it over the insulator above
corona ring.
 Without removing the rope align the holes and fix the screws.
 Repeat the similar process for female assembly.
 Rotate the bearing shaft assembly and check for alignment of
 Contacts assembly for horizontal alignment. Shims should be inserted between the
mounting flange of Assembly and top of the insulator at relevant side. Similarly, for vertical
alignment
 necessary shims should be inserted between insulator flange and top of shaft assembly
flange.
 If the entry is not smooth, loosen the contacts Mounting screws and push the contacts
forward or backward to get free entry.
 After achieving the entry check for centre line of Male and Female in both directions.
 Now moving part should be rotated 2 to 3 times to ensure the proper alignment
 The Corona ring assembly should be identified for male and female unit and connected
properly to it.
 Moving part should be operated two to three times for checking the free movement and
also check that the contact corona ring are not fouling each other.

e. Connecting Disconnector
 Manually set mechanism and disconnector to be connected into fully OPEN position
(Arrow mark on top of mechanism cabinet indicates the 'open' and 'close' positions).

Page 7 of 9
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE

 If mechanical interlock keys are fitted, it will be necessary to obtain the relevant keys to
make mechanism operational.
 Align the fixing hole and bolt them together to achieve desired tightness.
 Ensure that the mounting channel on the drive and the structure are matching.
 Level the box by placing the spirit level on output shaft flange in two directions.
 Provide shim wherever required.
 Check for centre line and verticality between torque bearing flange and drive flange with a
plumb.
 Introduce Universal Coupling as called for in the General Arrangement Drawing.
 Measure exact height between torque bearing flange and top of universal flange.
 Cut the operating pipe with the specified clearance to facilitate smooth entry.
 Weld the Vernier flange properly keeping the flange perpendicular to the centreline of the
pipe. Level and bolt the same. The drive is now ready for operation. Mounting angles of
mechanism to structure are slotted to provide horizontal adjustment. Adjust the
mechanism so that the vertical drive tube rotates TRUE.
 Cabling (internal/external) be completed as per schematic drawing. Ensure that all
electrical interlocks are wired properly.
 Before energising the circuitry, interlock wiring and control wiring should be checked by
multi meter (as per schematic drawings).

f. Tandem Pipe Assembly


 Measure the distance between the lever of two adjacent poles ('R' & 'Y')
 Check and set the Tandem, pipe length on the floor itself
 Lift the Tandem pipe by using proper rope and fix one side first by using suitable anti
friction washers, brass washers and split pins.
 Fix other side in the same manner.
 Operate the operating mechanism and check for proper closing and opening of both poles.
If required do minor adjustments in Tandem Pipe by length by using adjusting screw. Then
finally lock the adjusting screws by check nut.
 Repeat this process for the other poles ('Y' & 'B').
g. Earth Switch Assembly
 Identify the Assembly to fix the fixed contact assembly through General Arrangement
Drawing
 Take the Earth fixed contact assembly and fix it with the Hamper Assembly by using proper
sized Bolts as per General Assembly Drawings. The above assembly can be carried out
before
 installing the Hamper Assembly over the insulator.
 Lift the Earth Blade Assembly by using rope and fix it with base assembly using the middle
set of mounting holes to hold the assembly in place.
Page 8 of 9
Client: Authority: Client Engineer: Contractor Consultant Contractor:
OSOOL POULTRY S.A.O.C. TANWEER SEMAC & PARTNERS WORLEY OMAN TRADE LINKS & SERVICES
L.L.C. ENGINEERING L.L.C Co. LLC
EPC FOR CONSTRUCTION OF 132KV SAYYALA SUBSTATION MODIFICATION, 132KV OHL AND 132/11KV TRANSFORMER YARD AT OSOOL
PROJECT POULTRY WITH PRIMARY SUBSTATION IN WILAYAT HIMA GOVERNORATE

 Attach counterbalance weights in pendulum arm at suitable hole and check the position of
Earth Switch which should be parallel to ground.
 Manually move earthing blade towards closing position .To adjust add shims at the back of
the mounting plate to tilt the earthing blade in required direction.
 Continue to move earthing blade towards closing and observe that the contact fingers
come into the fixed contact. A small adjustment to twist the contact fingers is possible by
shimming
 mounting plate.
 Continue to close earthing switch until contacts are fully engaged i.e. when the insulated
stop of the earthing blade comes to rest without straining against fixed contact.
 Tighten all fixing bolts and keep the earth switch in closed position.

6.3 Do’s, Don’ts and Special Precautions


 Before the isolator is put into operation, the motor is to be meggered and the contacts are
cleaned.
 The mechanism box always is to be kept free from moisture. Hence, space heaters are
provided in the mechanism box.
 Also, rubber beading should be kept in good condition.
 Cable glands should be properly fitted at the entry of the cables and extra holes are
plugged properly to avoid hazards.
 For transportation, individual base and bearing pole assemblies & the male and female
contact arms should be packed separately.
 The Insulators and drive boxes should also be packed separately.
 The bolts and nuts required for mounting the base to the structure and the Insulators to
the base are packed separately as loose items, while all the other hardware (bolts & nuts)
are fitted in their respective places. Care should be taken that these are removed only at
the time of mounting to respective assemblies.
 All the assembles should be stored well preferably in a covered area to avoid any
damage/pilferage during storage.

7.0 DOCUMENTS & RECORDS.

Records shall include the following,


 Check List
 Mark up drawings
 RFI
 MAS & MRDR
 FAT & Routine Test Reports.

Page 9 of 9
Ref. No.: TLS-EL-CL-61-00

VISUAL INSPECTION OF ISOLATOR

PROJECT

PROJECT COMPANY
CONTRACTOR

MRCDR NO: DATE:


Make: Switch Serial No’s.:
TLS PO No.:
Vendor DO: MTC Ref:
Switch Type: Switch Quantity:

INSPECTION

Sl. Result
Description of the Checks
No A NA N/A
Proper unloading arrangement has been made at site
1
(Preferably with crane) to unload the packages.
2 All items have been checked with the packing list/DO.
After unloading the visual inspection of the packings has
3
been carried out
Any type of damage to the equipment/components during
4 transportation or any missing items has been brought to the
notice of the panel supplier.
Assembly drawings along with the installation and O&M
5
manual received.
6 Test certificate received for the switch.
Remarks / Observation

Contractor Representative Client Representative


NAME
DESIGNATION
SIGNATURE
DATE
A-Acceptable, NA-Not Acceptable, N/A – Not Available
Page 1 of 1
Ref. No.: TLS-EL-CL-60-00

CHECKLIST FOR INSPECTION OF ISOLATOR ERECTION

PROJECT

PROJECT COMPANY
CONTRACTOR

MRCDR NO: DATE:


Make: Switch Serial No’s.:
TLS PO No.:
Vendor DO: MTC Ref:
Switch Type: Switch Quantity:

INSPECTION

Sl. Result
Description of the Checks
No A NA N/A
Site where isolator is to be erected is ready before the
1
starting of erection work.
Level of the structure assembly has been checked during
2
erection using spirit level
Site where isolator is to be erected is ready before the
3
starting of erection work.
Level of the top surface of isolators has been checked
4
during erection, alignment & level of equipment
5 Centre line of all the poles in different phases are aligned.
Centre line alignment of male & female assembly has been
6
checked
Before fitting, the crane rings have been identified for male
7
and female assembly
Moving parts have been operated 2-3 times for checking
8
the free movement
9 The rotation of motor is in right direction
In case it is in opposite direction the same has been
10 corrected by altering of the phase sequence of the motor
terminal.
11 Lifting of tandem pipe assembly is with proper size rope
During erection movement of earthing blade has been
12
checked

Contractor Representative Client Representative


NAME
DESIGNATION
SIGNATURE
DATE
A-Acceptable, NA-Not Acceptable, N/A – Not Available

Page 1 of 2
Ref. No.: TLS-EL-CL-60-00

CHECKLIST FOR INSPECTION OF ISOLATOR ERECTION

PROJECT

PROJECT COMPANY
CONTRACTOR

Contact fingers of earthing blade are moving towards the


13
fixed contact
All fixing bolts have been tightened to keep the earth switch
14
in proper close/open position
Remarks / Observation

Contractor Representative Client Representative


NAME
DESIGNATION
SIGNATURE
DATE
A-Acceptable, NA-Not Acceptable, N/A – Not Available