TEMPORARY CONSTRUCTION
FACILITY
TCF-1
Date: 6/05/2021
Sr. TOPICS PHOTO/ DETAILS Direct Manpower: 35
No Indirect Manpower: 29
1 TOOL BOX TALK

(a) Heat stress


Management,
hazards, effect on
human body heat
related illness.
(b) Hand & Power tools
safety

2 WORK PERMIT
Total No of Permit. 10 Sr. Work Equipment’s/Tools Hot Work Permit Manpo Company
No Permit wer
(a) Hot Work Permit No.
= 06
(b) Cold Work Permit 1 1338 Generator ,Jack hammer ,hand tools Concrete chipping works for swimming pool 4 Advance Elements
= 03 filtration pump room .
(b) Lifting Permit
=00
[Type here]

2 1340 Generator, grinder, welding machine, Purling cutting fixing and welding works in 7 Al Kadi
Gas cutter gathering tent area

3 1342 JCB, Hand tools Excavation pipe lying and backfilling works for 13 Hexagon
irrigation system.

4 1337 Compactor ,water tanker hand tools Leveling and compaction works around sitting 08 Advance Elements
room and gym

5 1341 Generator grinder JCB hand tools Walkway interlock cutting and installation works 4 Hexagon

6 1343 Screw gun and hand tools Termination works for LCS in swimming pool 5 Hexagon
area and support installation work for switch No 2
and 6
Cold Work Permit

7 0702 Hand tools Walkway curbstone cleaning works 5 Shade

8 0704 Hand tools Paint touch up & bolt tightening 7 X-Smart

Lifting work
[Type here]

3 Daily Activities
Purling cutting fixing and welding works Leveling and compaction works in swimming pool and sitting room

Housekeeping works in camp area Walkway inter lock installation works


Termination of LCS in switch gear 2&6 Gathering tent purlin welding cutting works
Excavation pipe lying works for irrigation works. Walkway cleaning works
Paint touch up and bolt tightening works Concrete chipping works for swimming pool filtration pump room
4 HEIGH RISK
ACTIVITIES
5 ACHIVEMENT ZERO INCIDENT/ ACCIDENT

6 LOOK AHEAD Hand Rail Installation for the Kitchen &Clinic, Excavation for the 15 m Gate foundation near to the helipad, Swimming Pool Tiles Installation,
ACTIVITEIS Interlock and curbstone work, Gathering Tend foundation backfilling, Backfilling and leveling for Around stp Area, Backfilling and leveling roads
and sport area, Backfilling for inside the roundabout, Sludge tank leak rectification, Excavation & layer by layer backfilling and compaction for
the street poles, Foundation preparation for the control panel water well pump, RO {LIGHTING , POWER SOCKETS & FIRE ALARM}, Grounding connection
for the AC, INSTALLATION OF STREET LIGHTING POLES {OFFICE}, INSTALLATION OF STREET LIGHT POLES IN PLAYGROUND 25 MTR, CLOSING OF EIL
COMMENTS AND OPEN RFI'S, Irrigation water tank commissioning, Spindle Surface cover installation transmission & force main line, Kitchen commissioning(Air balancing for
Duct& Exhaust fans), A/C Rectification and inspection, Diesel Tank flushing with Diesel, Potable water supply installation for STP, Fire networking commissioning with overall
network, Air valve installation for fire network, Inspection Chamber Extension for STP, Water well existing pump remove and install the new pump.

7 MAJOR INCIDENT/
NEAR MISS
[Type here]

8
CONCERN & ISSUES CONSTRUCTION

9 Safety
1 Hafiz Sher Dil 2 Ahmad

10 TCF- 1 Project/ Sign:


Construction Manager