Last Issue: - Internal

Rev: -
Document Number: FL3B-100-G-SCH-0001-02
S/N Description Duration Start Finish Remarks
L. WATER INTAKE AND TREATMENT 381 24-Jun-21 09-Jul-22
1 Steel structure fabrication & installation (Incl. install grating) 229 15-Jul-21 28-Feb-22
2 Equipment Installation (Including Ducting, etc) 137 25-Oct-21 10-Mar-22
3 Piping fabrication & erection (Incl. Primary and Secondary Support) 280 24-Jun-21 30-Mar-22
4 Insulation works 90 14-Jan-22 13-Apr-22
5 Electrical works 147 25-Nov-21 20-Apr-22
6 Instrumentation works 122 25-Dec-21 25-Apr-22
7 Automation works 105 11-Jan-22 25-Apr-22
8 Check-out & commissioning 98 03-Apr-22 09-Jul-22
9 1st walkdown 03-Apr-22
Utilities readiness, pump & motor rotation test
10 Final walkdown (Final MEI Completion) 02-Jun-22
11 Pipe Flushing, Rotation Test & Hydro Test completed 16-Jun-22 Up to insulation completion
12 Cold Water Run & Vacuum Test Completed 23-Jun-22
13 Hot Water Run Completed 30-Jun-22
14 Start-up Water intake and treatment 10-Jul-22 To start filling up the reservoir by 30-Jun-21
N. DEMIN PLANT 375 01-Jul-21 10-Jul-22
1 Steel structure fabrication & installation (Incl. install grating) 239 15-Jul-21 10-Mar-22
2 Equipment Installation (Including Ducting, etc) 131 28-Sep-21 05-Feb-22
3 Piping fabrication & erection (Incl. Primary and Secondary Support) 274 01-Jul-21 31-Mar-22
4 Insulation works 150 02-Dec-21 30-Apr-22
5 Electrical works 180 01-Nov-21 29-Apr-22
6 Instrumentation works 181 11-Nov-21 10-May-22
7 Automation works 110 21-Jan-22 10-May-22
8 Check-out & commissioning 103 29-Mar-22 09-Jul-22
9 1st walkdown 29-Mar-22
Utilities readiness, pump & motor rotation test
10 Final walkdown (Final MEI Completion) 28-May-22
11 Pipe Flushing, Rotation Test & Hydro Test completed 11-Jun-22 Up to insulation completion
12 Cold Water Run & Vacuum Test Completed 18-Jun-22
13 Hot Water Run Completed 25-Jun-22
To start filling up the resins for 2/5 lines by 25-Jun-
14 Start-up 10-Jul-22 10-Jul-22
22
N. CPU UPGRADE 375 01-Jul-21 10-Jul-22
1 Mechanical works 23 26-Feb-22 20-Mar-22
2 Piping fabrication & erection (Incl. Primary and Secondary Support) 273 01-Jul-21 30-Mar-22
3 Insulation works 150 02-Dec-21 30-Apr-22
4 Electrical works 180 01-Nov-21 29-Apr-22
5 Instrumentation works 181 11-Nov-21 10-May-22
6 Automation works 110 21-Jan-22 10-May-22
7 Check-out & commissioning 103 29-Mar-22 09-Jul-22
8 1st walkdown 29-Mar-22
Utilities readiness, pump & motor rotation test
9 Final walkdown (Final MEI Completion) 28-May-22
10 Pipe Flushing, Rotation Test & Hydro Test completed 11-Jun-22 Up to insulation completion
11 Cold Water Run & Vacuum Test Completed 18-Jun-22
12 Hot Water Run Completed 25-Jun-22
13 Start-up 10-Jul-22 10-Jul-22

Prepared by: YA Checked by: Approved by:


Updated by: LMS SP/JMD ALB
Page 1 of 1