SCHEDULE PENYELESAIAN PEKERJAAN MEP

PROYEK MUSEUM SBY - ANI PACITAN

No. Uraian Pekerjaan Start Finish Status Keterangan


10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

ENERGIZE PLN CLOSED

1 PEKERJAAN ELEKTRIKAL
Tarikan Kabel Power + Merger & Terminasi CLOSED
Panel LVMDP ke PP- Hydrant Closed
PP-Hydrant ke PC-Pompa Diesel Closed
PP-Hydrant ke PC-Pompa Electrik Closed
PP-Hydrant ke PC-Pompa Jockey Closed
Panel LVMDP ke PP- Pompa Air Bersih Closed
PP-Pompa Air Bersih ke PC-Pompa Transfer Closed
PP-Pompa Air Bersih ke PC-Pompa Booster Closed
PP-Pompa Air Bersih ke PC-Pompa Deep Well Closed
PP-Pompa STP ke PC-Pompa Sewage Closed
PP-Lift Museum ke PC-Lift Closed
Panel LVMDP ke PP-Pos Scurity Closed

2 PEKERJAAN ELEKTRONIK
Pekerjaan Fire Alarm
Tarikan Kabel Terminal Box FA Closed
Pengecekan Instalasi Alarm Fixtures 14-Jul-22 20-Jul-22
Pemasangan Alarm Fixtures 21-Jul-22 27-Jul-22 Area yang sudah terpasang plafond
Setting Peralatan Utama FA 28-Jul-22 29-Jul-22
Parsial Test Fire Alarm 29-Jul-22 31-Jul-22
Pekerjaan Sound System
Tarikan Kabel Terminal Box Sound System Closed
Pengecekan Instalasi Sound System 14-Jul-22 20-Jul-22
Pemasangan Sound System 21-Jul-22 27-Jul-22 Area yang sudah terpasang plafond
Setting Peralatan Utama Sound System 28-Jul-22 29-Jul-22
Parsial Test Sound System 29-Jul-22 31-Jul-22

Pekerjaan Telepon
Pengecekan Instalasi Telepon 18-Jul-22 27-Jul-22
Setting Peralatan Utama Telepon 28-Jul-22 29-Jul-22
Parsial Test Telepon 29-Jul-22 31-Jul-22

Pekerjaan Data
Pengecekan Instalasi Data 18-Jul-22 27-Jul-22
Setting Peralatan Utama Data 28-Jul-22 29-Jul-22
Parsial Test Data 29-Jul-22 31-Jul-22

3 PEKERJAAN AIR CONDITIONING


Penutupan Kembali Bobokan Instalasi 17-Jul-22
Tarikan Kabel Power AC (Merger + Terminasi) 28-Jul-22
Pemasangan Thermostat 28-Jul-22
Instalasi Pipa Refrigerant 20-Jul-22
Pengetesan Instalasi Refrigerant 26-Jul-22
Test Parsial System Air Conditioning 29-Jul-22 31-Jul-22 Area Sudah Bersih dan Tidak Berdebu

4 PEKERJAAN PLUMBING
Penutupan Kembali Bobokan Instalasi 17-Jul-22
Test Instalasi Toilet Diorama 15-Jul-22 17-Jul-22
Pengecekan Urinoir yang Mampet 18-Jul-22 23-Jul-22
Menaikan Pompa Deep Well ke Elevasi 15 m 23-Jul-22 25-Jul-22
No. Uraian Pekerjaan Start Finish Status Keterangan
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Mengurug Kedalaman Deep Well menjadi 40 m dgn Pasir 26-Jul-22 28-Jul-22
Test Pompa Transfer Closed
Test Pompa Booster Closed
Test Pompa Kran Taman Closed
Test Pompa Sumpit & Sewage Closed

Tarikan Kabel Power + Merger & Terminasi CLOSED


PC-Pompa Transfer ke Unit Pompa Transfer Closed
PC-Pompa Booster ke Unit Pompa Booster Closed
PC-Pompa Kran Taman ke Unit Pompa Taman Closed
PC-Pompa Sumpit ke Unit Pompa Sumpit Closed

5 PEKERJAAN FIRE FIGHTING


PC-Pompa Diesel ke Unit Pompa Diesel Closed
PC-Pompa Elektrik ke Unit Pompa Elektrik Closed
PC-Pompa Jockey ke Unit Pompa Jockey Closed
Instalasi Fire Fighting ( Luar dan Dalam Gedung ) Closed
Test Parsial Pompa Fire Fighting 28-Jul-22 30-Jul-22

6 PEKERJAAN KOLAM IKAN KOI


Instalasi Plumbing Kolam Closed
Instalasi Power Pompa dan Setting Pompa Kolam Closed
Test Pompa Kolam Ikan Koi Closed
Penutupan Kembali Bobokan Instalasi 17-Jul-22
Pengadaan Media Filter Kolam Ikan Koi 28-Jul-22 30-Jul-22
Pengetesan Kolam Ikan Koi By Other Air Kolam masih berkurang setiap di isi

7 PEKERJAAN LIFT CLOSED

8 PEKERJAAN GENSET CLOSED

9 PEKERJAAN SEWAGE TREATMENT PLANT (STP) CLOSED