1 PEKERJAAN ELEKTRIKAL
Tarikan Kabel Power + Merger & Terminasi CLOSED
Panel LVMDP ke PP- Hydrant Closed
PP-Hydrant ke PC-Pompa Diesel Closed
PP-Hydrant ke PC-Pompa Electrik Closed
PP-Hydrant ke PC-Pompa Jockey Closed
Panel LVMDP ke PP- Pompa Air Bersih Closed
PP-Pompa Air Bersih ke PC-Pompa Transfer Closed
PP-Pompa Air Bersih ke PC-Pompa Booster Closed
PP-Pompa Air Bersih ke PC-Pompa Deep Well Closed
PP-Pompa STP ke PC-Pompa Sewage Closed
PP-Lift Museum ke PC-Lift Closed
Panel LVMDP ke PP-Pos Scurity Closed
2 PEKERJAAN ELEKTRONIK
Pekerjaan Fire Alarm
Tarikan Kabel Terminal Box FA Closed
Pengecekan Instalasi Alarm Fixtures 14-Jul-22 20-Jul-22
Pemasangan Alarm Fixtures 21-Jul-22 27-Jul-22 Area yang sudah terpasang plafond
Setting Peralatan Utama FA 28-Jul-22 29-Jul-22
Parsial Test Fire Alarm 29-Jul-22 31-Jul-22
Pekerjaan Sound System
Tarikan Kabel Terminal Box Sound System Closed
Pengecekan Instalasi Sound System 14-Jul-22 20-Jul-22
Pemasangan Sound System 21-Jul-22 27-Jul-22 Area yang sudah terpasang plafond
Setting Peralatan Utama Sound System 28-Jul-22 29-Jul-22
Parsial Test Sound System 29-Jul-22 31-Jul-22
Pekerjaan Telepon
Pengecekan Instalasi Telepon 18-Jul-22 27-Jul-22
Setting Peralatan Utama Telepon 28-Jul-22 29-Jul-22
Parsial Test Telepon 29-Jul-22 31-Jul-22
Pekerjaan Data
Pengecekan Instalasi Data 18-Jul-22 27-Jul-22
Setting Peralatan Utama Data 28-Jul-22 29-Jul-22
Parsial Test Data 29-Jul-22 31-Jul-22
4 PEKERJAAN PLUMBING
Penutupan Kembali Bobokan Instalasi 17-Jul-22
Test Instalasi Toilet Diorama 15-Jul-22 17-Jul-22
Pengecekan Urinoir yang Mampet 18-Jul-22 23-Jul-22
Menaikan Pompa Deep Well ke Elevasi 15 m 23-Jul-22 25-Jul-22
No. Uraian Pekerjaan Start Finish Status Keterangan
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Mengurug Kedalaman Deep Well menjadi 40 m dgn Pasir 26-Jul-22 28-Jul-22
Test Pompa Transfer Closed
Test Pompa Booster Closed
Test Pompa Kran Taman Closed
Test Pompa Sumpit & Sewage Closed