You are on page 1of 6

Material Not Onsite PT SPGN

MECHANICAL

No Description Schedule Onsite Status

1 Pompa Condensate Vertical Inline 22-Nov-22 30-Nov-22 Done

2 Booster pump Town Water 22-Nov-22 10-Dec-22 Done

3 Valve System Instalasi Industrial Waste Water (IWW) 26-Nov-22 3-Feb-23 Delay

4 Valve System Instalasi Town Water 26-Nov-22 3-Feb-23 Delay

5 Valve System Instalasi Compress air 26-Nov-22 3-Feb-23 Delay

6 DTS System Instalasi Compress air 26-Nov-22 Done

7 Valve System Instalasi Steam Condensate 26-Nov-22 Done

8 Steam Filter 1-Dec-22 10-Dec-22 Done

9 Mixing Valve 1-Dec-22 10-Jan-23 Done

10 Flow Meter Steam 1-Dec-22 10-Jan-23 Delay

11 Globe Valve Stainless Steel (Steam) 26-Nov-22 Done

12 Gate Valve Carbon Steel (Condensate Steam) 26-Nov-22 3-Feb-23 Delay

13 Panel Pompa CP01, CP02, Booster Pump 26-Nov-22 15-Dec-22 Done

14 Temporary Valve 10-Dec-22 Done

HVAC/BAS

Done
1 AHU Indoor/Outdoor 5-Dec-22 17-Dec-22

2 AC DX System Indoor/Outdoor 30-Nov-22 30-Jan-23 Delay

3 Duct Pressure Transmitter 22-Nov-22 Done

4 Duct Temperature Hmidity Transmitter 22-Nov-22 Done

5 Duct Dew Point Transmitter 22-Nov-22 Done

6 Room Pressure Transmitter 22-Nov-22 Done

7 Room Temperature Transmitter 22-Nov-22 Done

8 Cable Control 110 CE 19-Nov-22 Done

9 Temporay AC Ruang Panel 5-Dec-22 Done


Remaining Works PT SPGN

Schedule Finish
No Description Status
Installation

Done
1 Lifting AHU 2 Unit (Wet Lab, Dry Lab) 20-Dec-22
2 Install/Jointing AHU Dry Lab, Wet Lab 28-Dec-22 Done

3 Install Outdoor AHU Dry Lab, Wet Lab 22-Dec-22 Done

4 Install Pipa Refrigerant AHU 11-Jan-23 Progress 50%

5 Pressure Test Instalasi pipa Refrigerant AHU 13-Jan-23 Delay

6 Install Pipa Condensate AHU 11-Jan-23 Done

7 Install AC DX System (Ruang Panel) 3-Feb-23 Delay

8 Install Pipa Refrigerant AC DX System 3-Feb-23 Delay

9 Install Pipa Condensate AC DX System 3-Feb-23 Delay

10 Pressure Test Instalasi pipa Refrigerant AC DX System 3-Feb-23 Delay

11 Install DTS System Instalasi Compress air 9-Dec-22 Done

12 Install Pompa CP01 10-Dec-22 Done

13 Install Pompa CP02 11-Jan-23 Delay

14 Install Pompa Booster Pump 7-Jan-23 Done

15 Install Panel Pompa CP01, CP02, Booster Pump 11-Jan-23 Done

16 Install Exhaust Wall mounted area Raw Bean & Bean Winower 7-Jan-23 Menunggu Flashing

17 Install Valve System Steam 7-Jan-23 Progress 50%

18 Install Valve System Town Water 17-Dec-22 Done

Progress 50%
19 Install Valve System Compress air 10-Jan-23

20 Install Mixing Valve 12-Jan-23


Done
21 Steam Filter 20-Dec-22
Delay
22 Flow Meter Steam 12-Jan-23
Done
23 Setting Expantion Joint/Stopper 14-Dec-22
Follow Ceiling Kurang 5 Titik
24 Install Diffuser & Grill Installation

Delay
25 Install PRD area New Office 15-Jan-23
Delay
26 Install Wall Grill 10-Jan-23

27 Install Ducting supply area analytical Lab 28-Nov-22 Done

Done
28 Install Ducting Exhaust area analytical Lab 26-Nov-22

29 Install BAS system 14-Jan-23 Delay


30 Validasi IQ,OQ, BAS System 17-Jan-22 Delay

31 Internal Testing Commissioning & Balancing 31-Jan-22 Delay


Remaining Works PT PTP

Schedule Finish
No Description
Installation

1 Hydro test Pipa sprinkler Ground Floor 17-Nov-22

2 Hydro test Pipa sprinkler Above Ceiling 18-Nov-22

3 Hydro test Pipa Hydrant 19-Nov-22

4 Install BCP (Branch Control Valve) (Ground Floor & Above ceiling) 22-Nov-22

5 Install Four Way Bracing (Ground Floor & Above Ceiling) 24-Nov-22

6 Install Lateral Bracing (Ground Floor & Above Ceiling) 25-Nov-22

7 Install 4 Way Riser Bracing (Ground Floor & Above Ceiling) 24-Nov-22

8 Install Longitudinal Bracing (Ground Floor & Above Ceiling) 24-Nov-22

9 Install Head Sprinkler ( Above Ceiling) 22-Nov-22


Follow Ceiling
10 Install Head Sprinkler ( Ground Floor) Installation

11 Install IHB 24-Nov-22

12 Install Drain Instalasi Groun Floor & Above Ceiling 23-Nov-22

13 Install AAV (Automatic Air Venting) 22-Nov-22

14 Pondasi Support Header 19-Nov-22

15 Install APAR 27-Dec-22

16 Testing Commissioning Deluge Valve 28-Dec-22


Status

Done

Done

Delay. Move to 24 nov

Done
Material Belum ada PO

1 Eye Wash
2 Service Colomn

You might also like