MECHANICAL
3 Valve System Instalasi Industrial Waste Water (IWW) 26-Nov-22 3-Feb-23 Delay
HVAC/BAS
Done
1 AHU Indoor/Outdoor 5-Dec-22 17-Dec-22
Schedule Finish
No Description Status
Installation
Done
1 Lifting AHU 2 Unit (Wet Lab, Dry Lab) 20-Dec-22
2 Install/Jointing AHU Dry Lab, Wet Lab 28-Dec-22 Done
16 Install Exhaust Wall mounted area Raw Bean & Bean Winower 7-Jan-23 Menunggu Flashing
Progress 50%
19 Install Valve System Compress air 10-Jan-23
Delay
25 Install PRD area New Office 15-Jan-23
Delay
26 Install Wall Grill 10-Jan-23
Done
28 Install Ducting Exhaust area analytical Lab 26-Nov-22
Schedule Finish
No Description
Installation
4 Install BCP (Branch Control Valve) (Ground Floor & Above ceiling) 22-Nov-22
5 Install Four Way Bracing (Ground Floor & Above Ceiling) 24-Nov-22
7 Install 4 Way Riser Bracing (Ground Floor & Above Ceiling) 24-Nov-22
Done
Done
Done
Material Belum ada PO
1 Eye Wash
2 Service Colomn