Professional Documents
Culture Documents
net/publication/324102507
CITATIONS READS
4 1,661
6 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Jinsu Gim on 04 April 2018.
A DAQ system was built to acquire and process signals As shown in Figure 2, each gate showed gate open lag
from the limit switch and valve gate controller. The DAQ time from 150 msec to 300 msec, which was approximately
system consisted of NI cDAQ-9178 Chassis, NI 9401 digital 10% of the total filling time. This result means that if a
signal input/output module, and NI USB 6008. The screw solenoid valve of a valve gate receives the open signal at 1.5
forward signal was fed to the system as the timing reference. sec, the valve gates open entirely at 1.65–1.8 sec. The
The program for control and measuring was developed in NI difference of the gate open lag times among the gates was
LabVIEW. The DAQ system had an additional function to about 6% of the filling time. The scale of the gate open lag
control the valve gates. time could influence the melt front pattern in the filling stage.
The molded part was a 40 inches TV back cover, and In the continuous process, deviation of the gate open lag
the mold had ten hot runner gates, as shown in Figure 1. The time was approximately 2.5% for a gate, which is 0.2% of
valve pin diameter of the main gate was 8 mm, and the the filling time. The variation of the gate open lag time
others were 6 mm. Table 1 and Table 2 show the reference among cycles could be negligible in comparison with the
injection molding condition and the reference hot runner filling time. Therefore, the gate open lag time was stable in
sequence condition each. the stabilized continuous process.
The injection molding machine used for the experiment The viscosity of the melt in the manifold would
was LS-Mtron hydraulic injection molding machine LG influence the gate open lag time. The melt viscosity would
1800S-i150 with 1,800 ton of clamping force and 125 mm affect the movement of the valve pin by exerting the shear
of the screw diameter. The resin was PC-ABS LUPOY GN force on the valve pin surface. At the beginning moment of
5000SLF by LG Chemical, and it was dried sufficiently valve pin movement, shear rate of melt on the valve pin
before the experiment. surface is zero. Therefore, the zero-shear viscosity would
influence valve pin movement. The temperature of the
manifold and barrel was in 4 conditions; the reference
Gate Open Lag Time temperature, and temperatures of 10ºC, 15ºC, and 30ºC
lower than the reference temperature. After 30–60 minutes
30 cycles of test injection molding process of 10–20 stabilization cycles, the gate open lag time at a melt
corresponding to the reference process condition were temperature was measured. As shown in Figure 3, the gate
performed to estimate the amount of the gate open lag time. open lag time increases as melt temperature decreases.
For the process stabilization, 20 cycles had been proceeded Especially at the condition 4, the gate open lag time
before the test. increased significantly. As shown in Figure 4, the zero-shear
viscosity of the resin in each condition rises as much as 42%, Influence of gate open lag time
73% and 240% from the reference condition (Condition 1,
melt temperature 260ºC). The difference of the zero-shear The gate open lag time was nearly constant when melt
viscosity in the condition 3 and 4 is much larger than the temperature stabilized. Therefore, advancing the signal
others. The zero-shear viscosity in the condition 3 and 4 timing as much as the gate open lag time of each gate could
could explain the significant increase of the gate open lag correct the gate open lag time. The difference between
time. Therefore, the zero-shear viscosity of melt influences corrected and desired valve gate open timing and was 0.7%.
the gate open lag time.
Part weights and surface defects were measured and
tested by changing the open signal timing to investigate the
effect of this variation of the gate open lag time on the part
quality. As well as the corrected condition by advancing the
timing of the reference, the other condition by retarding the
gate open timing as much as the lag time was applied. In the
first condition (advancing condition), the gate opened
entirely as much as the gate open lag time earlier than the
reference condition. This condition is the gate open lag time
corrected condition. In the second condition (retarding
condition), the gate opened entirely as much as the lag time
later than the reference condition. Throughout the molding
Figure 3. Gate open lag time change with melt temperature. experiments, the other process parameters were left
unaltered from the reference condition.
The part weight difference in the two conditions was
about 0.3%. Even if the valve gate opened in different
timing in the conditions, it occurred within the filling stage,
not in the holding stage influencing much of the part weight.
Melt temperature or holding pressure acting the cavity that
affects the density did not change. However, the surface
quality was sensitive to the gate open lag time as shown in
Figure 5, especially near the gates 6 and 9. Halo surface
defect occurred when the gate opened as much as the gate
open lag time earlier than the reference condition.
Mold filling simulation was performed by Autodesk
Figure 4. Zero-shear viscosity of LUPOY GN5000SFL [13]. Moldflow Insight 2018 to investigate the effect of the gate
open lag time on the filling pattern and flow front speed. The
complete open time in the experiment set to the valve gate
open timing in the simulation. The specimen and whole
runner was modeled with about 120,000 elements of dual
domain mesh, as shown in Figure 6. Simulation conditions
were referred to the reference condition except the valve
gate timing. The halo surface defects occur by a sudden
change of flow front speed according to previous research
[14, 15]. Therefore, from the simulation results, the flow
front speed distribution was presented in Figure 7. The
simulation result of the advancing condition was Figure 7
(a), and the retarding conditions was Figure 7 (b).
As shown in Figure 7 (a), sudden flow front speed
change appeared near the gate 6 and 9 in the case of the early
gate open. Notably, the location of the drastic flow front
speed change near the gate 6 was on the polished surface,
which emphasized the halo defect. On the contrary, the
location of flow front speed change moved to the etched
surface in the case of the late gate open as shown in Figure
Figure 5. Surface defects (a) near the gate 6 and (b) near the 7 (b), which did not cause any visible defect in the molding
gate 9. trial.
Figure 6. CAE simulation model of the specimen.