Project Name: Construction of DOH Drug Abuse Treatment and Rehabilitation Center (DATRC)

Project Location: Osorio Rd., Brgy. Osorio, Trece Martires City, Cavite
Subject: Actual BOQ for Patient Dormitory
BUILDING 10 MALE STAFF DORM (ACTUAL COMPUTATION)

ITEM NO. PARTICULARS QTY UNIT UNIT COST AMOUNT

A. SITE PREPARATIONS ₱ 1,288,467.13


CLEARING AND GRUBBING 371.58 sq.m. 30.41 ₱ 11,298.99
DEMOLITION WORKS 1.00 lot 20,084.73 ₱ 20,084.73
DISPOSAL OF DEBRIS FROM 38.00 cu.m. 1,214.04 ₱ 46,133.47
DEMOLITION
DAYWORKS 1.00 lot 318,123.58 ₱ 318,123.58
Sub-total ₱ 395,640.78
EARTHWORKS
Structural Excavation for 293.20 cu.m. 728.42 Php 213,574.67
Building Foundations
Hauling and Disposal of 124.56 cu.m. 1,214.03 Php 151,219.71
excavated unsuitable
Backfilling material
and Compaction cu.m. 1,214.04 Php -
Disposal of Water (Dewatering) 1.00 lot 214,582.29 Php 214,582.29
Trimming Works 293.20 sq.m. 607.02 Php 177,978.23
Soil Poisoning 77.96 sq.m. 121.40 Php 9,464.65
Gravel Bedding (100mm thk.) 51.90 cu.m. 2,428.06 Php 126,006.80
Sub-total Php 892,826.36
B. CONCRETE WORKS ₱ 2,100,405.30
3.0 Reinforcing Steel Bars; Grade
60
Foundations 473.57 kgs Php 74.06 Php 35,072.91
Columns 3,020.55 kgs Php 74.06 Php 223,702.30
Concrete Walls kgs Php 74.06 Php -
Beams and Girders 17,892.70 kgs Php 74.06 Php 1,325,133.61
Reinforcing Steel Bars; Grade Php -
40
Suspended Slabs; Slabs on- kgs Php 72.62 Php -
grade
Stairs kgs Php 72.62 Php -
Sewage and Sump pits kgs Php - Php -
Sub-total Php 1,583,908.81
Formworks; including shoring
and bracing work
Foundations 29.13 sq.m. 2,655.73 Php 77,356.21
Columns 48.80 sq.m. 2,655.73 Php 129,589.18
Concrete Walls sq.m. 2,655.73 Php -
Beams and Girders 59.29 sq.m. 2,655.73 Php 157,458.44
Suspended Slabs; Slabs on- sq.m. 2,655.73 Php -
grade
Stairs sq.m. 2,655.73 Php -
Sub-total Php 364,403.83
Cast-in-place Concrete
Foundations 11.65 cu.m. 6,552.89 Php 76,334.66
Columns 6.82 cu.m. 6,552.89 Php 44,690.73
Concrete Walls cu.m. 6,552.89 Php -
Beams and Girders 4.74 cu.m. 6,552.89 Php 31,067.27
Suspended Slabs; Slabs on- cu.m. 6,552.89 Php -
grade
Stairs cu.m. 6,552.89 Php -
Sewage and Sump pits cu.m. Php -
Sub-total Php 152,092.66
TOTAL PROJECT COST: Php 3,388,872.43