You are on page 1of 2

July 08, 2023

CONSTRUCTION PROGRESS

PROGRESS BILLING LOG July 08, 2023


%
Scope of Work Contract Cost Billing Cost Remarks
Completion
TEMPORARY FACILITIES
Temporary Fence/Quarters
Safety Equipments ₱49,200.00 20.00% ₱9,840.00 Equipment Cost
Mobilization / Demobilization
Temporary Water and Power
SITE CLEARING AND
EARTHWORKS
98% Demolished and
Demolition & Hauling ₱63,360.00 98.00% ₱62,092.80
Hauled
Site Clearing, Layouting, Staking,
₱13,824.00 100.00% ₱13,824.00 Complete
Soil Poisoning
Excavation ₱25,920.00 100.00% ₱25,920.00 Complete
Earth filling and Compaction ₱25,920.00 100.00% ₱25,920.00 Complete
Gravel Bed / Lean Concrete ₱40,320.00 100.00% ₱40,320.00 Complete
CONCRETING WORKS
Footings ₱64,951.82 100.00% ₱64,951.82 Complete
Footing Tie Beam ₱79,518.43 100.00% ₱79,518.43 Complete
Columns ₱165,019.68 50.00% ₱82,509.84 Complete Ground Floor
Ground Floor Slab ₱68,274.18 83.70% ₱57,145.49 Ground Floor Slab
2F Beam Reinforcement :
Second Floor Beams ₱110,343.07 50.00% ₱55,171.54
100%
2F Slab Reinforcement
Second Floor Slab ₱157,011.88 22.00% ₱34,542.61
Procured
Roof Beams ₱88,737.50 0.00% ₱0.00
Concrete Stair ₱55,823.04 0.00% ₱0.00
Formworks and Scaffolding ₱168,000.00 68.00% ₱114,240.00 Purchased and Rented
MASONRY WORKS
Exterior Wall and Fire Wall
₱398,630.16 12.93% ₱51,542.88 Front & Side Wall Masonry
Masonry
Interior Wall Masonry ₱61,938.24 0.00% ₱0.00
Kitchen + Nook Counter
₱14,394.24 0.00% ₱0.00
Masonry
MOISTURE PROTECTION ₱28,526.40 0.00% ₱0.00
ELECTRICAL WORKS ₱119,451.36 4.83% ₱5,769.50 Ground Floor Rough Ins
PLUMBING & SANITARY ₱126,077.28 24.21% ₱30,523.31 Rough Ins
ROOFING WORKS 0.00% ₱0.00
Roof Framing ₱153,511.68 0.00% ₱0.00
Roofing Materials ₱206,619.84 0.00% ₱0.00
Thermal Proofing ₱28,627.20 0.00% ₱0.00
Total Construction Cost ₱2,314,000.01 32.58% ₱753,832.22

Ar. Jhean Edxer E. Magpantay, UAP


CONTRACTOR

You might also like