ACE BUILDERS & SUPPLY

Item No. Item of work Cost %wt


1 Layout/Excavation 3,294.00 1.83%
2 Gravel Bedding/Rebar Footing 3,582.00 1.99%
3 Concreting of Footing 4,068.00 2.26%
4 Concreting of Column/Rebars 3,708.00 2.06%
5 Septic Tank/Catch Basin 4,158.00 2.31%
6 Installation of Smart Block - Floor line 1,980.00 1.10%
7 Scrapping /Compaction - Gravel Bedding 2,754.00 1.53%
8 Rebars/Concreting Flooring - Grnd Flr SOG 1,980.00 1.10%
9 Installation of Smart Block - Grnd Floor 7,380.00 4.10%
10 Scaffold/Form - Second Floor slab 3,204.00 1.78%
11 Rebars to Second Floor/Concreting(Suspend 4,140.00 2.30%
12 Concrete Canopies 4,122.00 2.29%
13 Installation of Smart Block - Second Floor 7,380.00 4.10%
14 Installation of Stairs 6,858.00 3.81%
15 Fabrication/installation of Roof Truss 6,894.00 3.83%
16 Tinsmithry/Ceiling 9,378.00 5.21%
17 Partition/Fretworks 4,014.00 2.23%
18 Installation of Door Jamb/Door 4,284.00 2.38%
19 Installation of Window Grills/ Window 5,922.00 3.29%
20 Plumbing works/Fixtures 7,830.00 4.35%
21 Cabinet/Kitchen counter 2,700.00 1.50%
22 Diamond Render (8mm) 9,018.00 5.01%
23 Diamond Finish Coat 8,910.00 4.95%
24 Paint Finish (All ) 40,104.00 22.28%
25 Installation of Tiles (Grnd floor all) 6,462.00 3.59%
26 Installation of Vinyl tiles (Second Floor) 6,462.00 3.59%
27 Service Entrance Post/Rebar/Concreting 5,256.00 2.92%
28 Scaffolding Clearing 4,158.00 2.31%
TOTAL 180,000.00 100.00%