QUANTIT MAN-HOURS TOTAL MAN-DAYS (C) NUMBER OF

ITEM NO. DESCRIPTION Y (A) UNIT PER UNIT (B) = (AxB)/8 WORKERS (D)

2 FOUNDATION
2.2 Earthworks
Excavation of Column Footings 31.5 cu.m. 4.00 15.75 5.00
Excavation of Wall Footings 12.68 cu.m. 4.00 6.34 3.00
Gravel Bedding 1 cu.m. 1.20 0.15 1.00
Soil Poisoning 170.5 sq.m. 0.50 10.66 3.00
found Concrete Works
Pouring of Column Footing 6.93 cu.m. 5.00 4.33 3.00
Curing of Column Footing cu.m.
Pouring of Wall Footing 5.93 cu.m. 5.00 3.71 3.00
Curing of Wall Footing cu.m.
Pouring of Slab on Fill 11.06 cu.m. 5.00 6.91 5.00
Curing of Slab on Fill
ground Concrete Works
Pouring of Column 7.845 cu.m. 4.83 4.74 5.00
Pouring of Beam 7.455 cu.m. 4.83 4.50 5.00
Pouring of Floor Slab 4.965 cu.m. 4.83 3.00 5.00
Pouring of Stairs 2.375 cu.m. 4.83 1.43 3.00
4.5 Concrete Works
Pouring of Column 7.845 cu.m 4.83 4.74 4.00
Pouring of Beam 7.455 cu.m 4.83 4.50 4.00
4.6 Pouring of Floor Slab 4.965 cu.m 4.83 3.00 4.00
Concrete Works
Roof Beam 58.8 sq.m. 4.83 35.50 10.00
Gutter Length 117 sq.m. 0.87 12.72 5.00
ground Masonry Works
Laying of Exterior CHB 120.115 sq.m. 1.60 24.02 4.00
Laying of Interior CHB 87.435 sq.m. 1.33 14.54 4.00
3.4 Plastering of Exterior Wall 240.23 sq.m. 3.00 90.09 10.00
Plastering of Interior Wall 174.87 sq.m. 3.00 65.58 8.00
Masonry Works
Laying of Exterior CHB 120.115 sq.m. 1.60 24.02 5.00
Laying of Interior CHB 87.435 sq.m. 1.33 14.54 4.00
4.3 Plastering of Exterior Wall 240.23 sq.m. 3.00 90.09 10.00
Plastering of Interior Wall 174.87 sq.m. 3.00 65.58 8.00

Steel Works
Fabrication of Reinforcing Bars 398 kg 0.10 4.98 2.00
Installation of Reinforcing Bars 398 kg 0.07 3.48 2.00
Steel Works
Fabrication of Reinforcing Bars 2996.8 kg 0.10 37.46 8.00
3 Installation of Reinforcing Bars 2996.8 kg 0.07 26.22 10.00
ROOFING
4.9 Steel Works
Fabrication of Reinforcing Bars 599.36 kg 0.10 7.49 3.00
5 Installation of Reinforcing Bars 599.36 kg 0.07 5.24 3.00
3.1 Steel Works
Fabrication of Reinforcing Bars 2996.8 kg 0.10 37.46 8.00
4 Installation of Reinforcing Bars 2996.8 kg 0.08 29.97 10.00
5.3 Gutter 22 pcs 0.87 2.39 2.00
Ridge Roll 5 pcs 0.20 0.13 2.00
Hip Roll 21 pcs 0.20 0.53 2.00
Flashing 3 pcs 0.20 0.08 2.00
2.3
Formworks
Fabrication of Forms 52.12 sq. m. 2.35 15.31 5.00
Installation of Forms 52.12 sq. m. 2.35 15.31 4.00
2.4 Stripping of Forms 52.12 sq. m. 3.50 22.80 5.00
Installation of Scaffoldings 2 set 11.00 2.75 4.00
Dismantling of Scaffoldings 2 set 11.00 2.75 3.00
3.1 Formworks
Fabrication of Forms 519.46 sq.m. 2.35 152.59 15.00
Installation of Forms 519.46 sq.m. 2.35 152.59 15.00
3.2 Stripping of Forms 520.46 sq.m. 3.50 227.70 16.00
4.1
Formworks
Fabrication of Forms 519.46 sq.m 2.35 152.59 22.00
Installation of Forms 519.46 sq.m 2.35 152.59 22.00
4.2 Stripping of Forms 520.46 sq.m 3.50 227.70 23.00
5.1 Formworks
Fabrication of Forms 58.8 sq.m. 2.35 17.27 5.00
Installation of Forms 58.8 sq.m. 2.35 17.27 5.00
5.2 Stripping of Forms 59.8 sq.m. 3.50 26.16 6.00
Fixing Hardware
Installation of Doors 7 pcs 24.00 21.00 8.00
Installation of Windows 16 pcs 4.00 8.00 4.00
Fixing Hardware
Installation of Doors 7 pcs 24.00 21.00 8.00
Installation of Windows 12 pcs 4.00 6.00 4.00
3.8 Tile Works
Installation of Tiles 6067 pcs 3.00 2275.13 40.00
Grouting
4.7 Tile Works
Installation of Tiles 6067 pcs 3.00 2275.13 40.00
3.9 Paint Works
Application of Paint 569.8 sq.m 0.64 45.58 15.00
Paint Works
4.8 Application of Paint 441.69 sq.m 0.64 35.34 15.00
DURATION (days)
= C/D

4.00
3.00
1.00
4.00

2.00
7.00
2.00
7.00
2.00
7.00

1.00
1.00
1.00
1.00

2.00
2.00
1.00

4.00
3.00

7.00
4.00
10.00
9.00

5.00
4.00
10.00
9.00

3.00
3.00

5.00
3.00
3.00
2.00

5.00
3.00
2.00
1.00
1.00
1.00

4.00
4.00
5.00
1.00
1.00

11.00
11.00
15.00

7.00
7.00
10.00

4.00
4.00
5.00

3.00
2.00

3.00
2.00

57.00

57.00

4.00

3.00
TOTAL MAN-DAYS (C) =
ITEM NO. DESCRIPTION QUANTITY (A) UNIT MAN-HOURS PER UNIT (B) (AxB)/8 NUMBER OF WORKERS (D) DURATION (days) = C/D

1 MOBILIZATION
Installation of Perimeter Fence 400 sq.m. 0.20 10.00 7.00 2.00
Construction of Temfacil 15 sq.m. 0.50 0.94 2.00 1.00
2 FOUNDATION
2.1 Layout
Clearing and Grubbing 360 sq.m. 0.05 2.25 2.00 2.00
2.2 Earthworks
Excavation of Column Footings 152.145 cu.m. 4.00 76.07 5.00 16.00
Excavation of Wall Footings 44.34 cu.m. 4.00 22.17 3.00 8.00
Gravel Bedding 9.609 cu.m. 1.20 1.44 1.00 2.00
Soil Poisoning 200 sq.m. 0.50 12.50 3.00 5.00

2.4 Formworks
Fabrication of Forms 52.12 sq. m. 2.35 15.31 5.00 4.00
Installation of Forms 52.12 sq. m. 2.35 15.31 4.00 4.00
Stripping of Forms 52.12 sq. m. 3.50 22.80 5.00 5.00
Installation of Scaffoldings 2 set 11.00 2.75 4.00 1.00
Dismantling of Scaffoldings 2 set 11.00 2.75 3.00 1.00

2.5 Plumbing Works


Installation of Plumbing Pipes 100 m 0.60 7.50 5.00 2.00

2.6 Concrete Works


Pouring of Column Footing 18.11 cu.m. 5.00 11.32 3.00 4.00
Curing of Column Footing cu.m. 7.00
Pouring of Wall Footing 6.98 cu.m. 5.00 4.36 3.00 2.00
Curing of Wall Footing cu.m. 7.00
Pouring of Slab on Fill 21 cu.m. 5.00 13.13 5.00 3.00
Curing of Slab on Fill 7.00
3 GROUND FLOOR
3.1 Steel Works
Fabrication of Reinforcing Bars 2996.8 kg 0.10 37.46 8.00 5.00
Installation of Reinforcing Bars 2996.8 kg 0.07 26.22 10.00 3.00
3.2 Formworks
Fabrication of Forms 519.46 sq.m. 2.35 152.59 15.00 11.00
Installation of Forms 519.46 sq.m. 2.35 152.59 15.00 11.00
Stripping of Forms 520.46 sq.m. 3.50 227.70 16.00 15.00
3.4 Masonry Works
Laying of Exterior CHB 120.115 sq.m. 1.60 24.02 4.00 7.00
Laying of Interior CHB 87.435 sq.m. 1.33 14.54 4.00 4.00
Plastering of Exterior Wall 240.23 sq.m. 3.00 90.09 10.00 10.00
Plastering of Interior Wall 174.87 sq.m. 3.00 65.58 8.00 9.00
3.5 Electrical Works
Installation of Electrical Pipes 425.06 L.M 0.19 10.10 5.00 3.00
Installation of Electrical Fixtures 55 PC/m 0.39 2.68 5.00 1.00
Installation of Electrical Wires 252.45 PC/m 0.25 7.89 5.00 2.00
3.6 Plumbing Works
Installation of Plumbing Pipes 46.2 pcs 0.19 1.10 1.00 2.00
Installation of Plumbing Fixtures 21 pcs 4.00 10.50 6.00 2.00
3.7 Concrete Works
Pouring of Column 7.845 cu.m. 4.83 4.74 5.00 1.00
Pouring of Beam 7.455 cu.m. 4.83 4.50 5.00 1.00
Pouring of Floor Slab 4.965 cu.m. 4.83 3.00 5.00 1.00
Pouring of Stairs 2.375 cu.m. 4.83 1.43 3.00 1.00
3.8 Fixing Hardware
Installation of Doors 7 pcs 24.00 21.00 8.00 3.00
Installation of Windows 16 pcs 4.00 8.00 4.00 2.00
3.9 Tile Works
Installation of Tiles 6067 pcs 3.00 2275.13 40.00 57.00
Grouting
3.1 Paint Works
Application of Paint 569.8 sq.m 0.64 45.58 15.00 4.00
4 SECOND FLOOR
4.1 Steel Works
Fabrication of Reinforcing Bars 2996.8 kg 0.10 37.46 8.00 5.00
Installation of Reinforcing Bars 2996.8 kg 0.08 29.97 10.00 3.00

4.2 Formworks
Fabrication of Forms 519.46 sq.m 2.35 152.59 22.00 7.00
Installation of Forms 519.46 sq.m 2.35 152.59 22.00 7.00
Stripping of Forms 520.46 sq.m 3.50 227.70 23.00 10.00
4.3 Masonry Works
Laying of Exterior CHB 120.115 sq.m. 1.60 24.02 5.00 5.00
Laying of Interior CHB 87.435 sq.m. 1.33 14.54 4.00 4.00
Plastering of Exterior Wall 240.23 sq.m. 3.00 90.09 10.00 10.00
Plastering of Interior Wall 174.87 sq.m. 3.00 65.58 8.00 9.00
4.4 Electrical Works
Installation of Electrical pipes 425.07 L.M 0.19 10.10 6.00 2.00
Installation of Electrical fixtures 61 PC/m 0.39 2.97 5.00 1.00
Installation of Electrical Wires 252.45 PC/m 0.25 7.89 5.00 2.00
4.5 Plumbing Works
Installation of Plumbing Pipes 30.8 pcs 0.19 0.73 1.00 1.00
Installation of Plumbing Fixtures 24 pcs 4.00 12.00 6.00 2.00
4.6 Concrete Works
Pouring of Column 7.845 cu.m 4.83 4.74 4.00 2.00
Pouring of Beam 7.455 cu.m 4.83 4.50 4.00 2.00
Pouring of Floor Slab 4.965 cu.m 4.83 3.00 4.00 1.00
4.7 Fixing Hardware
Installation of Doors 7 pcs 24.00 21.00 8.00 3.00
Installation of Windows 12 pcs 4.00 6.00 4.00 2.00
4.8 Tile Works
Installation of Tiles 6067 pcs 3.00 2275.13 40.00 57.00
4.9 Paint Works
Application of Paint 441.69 sq.m 0.64 35.34 15.00 3.00
5 ROOFING
5.1 Steel Works
Fabrication of Reinforcing Bars 599.36 kg 0.10 7.49 3.00 3.00
Installation of Reinforcing Bars 599.36 kg 0.07 5.24 3.00 2.00
5.2 Formworks
Fabrication of Forms 58.8 sq.m. 2.35 17.27 5.00 4.00
Installation of Forms 58.8 sq.m. 2.35 17.27 5.00 4.00
Stripping of Forms 59.8 sq.m. 3.50 26.16 6.00 5.00
5.3 Concrete Works
Roof Beam 58.8 sq.m. 4.83 35.50 10.00 4.00