No Description Start Date Finish Date Amont Duration

Back filing Work


GFL Soil or Qurry dust Filling(70%) 2021.09.01 2021.09.31 1,254,086.40
Masonary Work
1st Floor (10%) 2021.09.01 2021.09.03 114,567.00
2nd Floor (10%) 2021.09.01 2021.09.03 171,567.00
3rd Floor (50%) 2021.09.01 2021.09.15 992,400.00
Roof Top (100%) 2021.09.17 2021.09.25 1,134,650.00
Internal Plaster Work
Brick Wall 1FL (15%) 2021.09.04 2021.09.06 152,235.00
Brick Wall 2FL (15%) 2021.09.04 2021.09.06 177,870.00
Brick Wall 3FL (50%) 2021.09.08 2021.09.20 607,365.00
Roof Top (100%) 2021.09.17 2021.09.27 198,800.00
External Plaster
Roof Top to 1st floor level (80%) 2021.09.01 2021.09.30 1,640,600.00
Water Proofing Work
Roof Top 2021.09.07 2021.09.12 1,950,480.00
Stair case cover slab 2021.09.05 2021.09.07 370,260.00
Chip Concrete Work 2021.09.14 2021.09.15
Bath Room
1st Floor 2021.09.13 2021.09.15 85,350.00
2nd Floor 2021.09.17 2021.09.19 128,025.00
3rd Floor 2021.09.21 2021.09.24 102,420.00
Painting Work Internal
1st Floor (85%) 2021.09.08 2021.09.15 276,930.00
2nd Floor (85%) 2021.09.08 2021.09.16 309,238.00
3rd Floor (85%) 2021.09.18 2021.09.30 312,315.00
Bath Room Tiling Work
1st Floor (100%) 2021.09.18 2021.09.25 310,400.00
2nd Floor (100%) 2021.09.22 2021.09.29 467,450.00
3rd Floor (35%) 2021.09.27 2021.09.30 375,540.00
Genaral Arae Tiling & Skirting Work
1st Floor (90%) 2021.09.18 2021.09.25 1,336,077.00
2nd Floor (90%) 2021.09.20 2021.09.30 1,586,484.00
Alluminium Work
1st Floor (80%) 2021.09.15 2021.09.30 880,595.00
2nd Floor (80%) 2021.09.15 2021.09.30 1,128,216.00
3rd Floor (20%) 2021.09.25 2021.09.30 312,086.00
ELECTRICAL WORKS
First Floor
Indoor lamp outlet 9/9/2021 12/9/2021 143,152.65
13A Switch Socket Outlet 9/9/2021 16/09/2021
Roof Terrace
Indoor lamp outlet 25/09/2021 30/09/2021 188,358.75
13A Switch Socket Outlet 25/09/2021 30/09/2021 430,267.50
Third Floor
Indoor lamp outlet 09/08/2021 14/08/2021 180,824.40
13A Switch Socket Outlet 09/08/2021 14/08/2021 549,717.30
Roof Terrace
Indoor lamp outlet 16/08/2021 20/08/2021 62,786.25
Plumbing Work
First Floor
Water supply line 5/9/2021 7/9/2021 19,999.80
Sewer & waste line 4/9/2021 6/9/2021 66,666.40
Testing 8/9/2021 10/9/2021 6,666.60
Second Floor
Water supply line 9/9/2021 11/9/2021 19,999.80
Sewer & waste line 6/9/2021 9/9/2021 66,666.40
Testing 12/9/2021 14/09/2021 6,666.60
Third Floor
Water supply line 13/09/2021 15/09/2021 19,999.80
Sewer & waste line 9/9/2021 13/09/2021 66,666.40
Testing 16/09/2021 18/09/2021 6,666.60
Roof Terrace
Water supply line 28/09/2021 30/09/2021 48,006.00
Testing 30/09/2021 1/10/2021 16,002.00
AC Work
All Floor
Piping Work 6/9/2021 25/09/2021 118,026.00
Fire Work
All Floor
fire detection point wiring 5/9/2021 15/09/2021 704,716.40
Pipe line fixed 16/09/2021 25/09/2021 85,932.00

Total Amount 19,183,794.05


Remarks

After Finalized brick matter

wall conduite and sunk box fixed 45% BOQ


AC Point wall conduite and sunk box fixed

wall conduite and sunk box fixed


wall conduite and sunk box fixed

wall conduite and sunk box fixed


wall conduite and sunk box fixed

wall conduite and sunk box fixed

Soffit line and wall piping

pressure testing

Soffit line and wall piping

pressure testing

Soffit line and wall piping

pressure testing

Soffit line and wall piping


pressure testing

40%

wiring and wall conduiting All 40%


GI Pipe work