CONSTRUCTION AND DEVELOPMENT OF 2-STOREY DILG LAGUNA PROVINCIAL OFFICE

COST PERCENTAGE Duration Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30
1 Preparatory Works 303,365.66 2.62% 1 2.62%
2 Structural Works 3,769,648.81 32.53% 11 2.96% 2.96% 2.96% 2.96% 2.96% 2.96% 2.96% 2.96% 2.96% 2.96% 2.96%
3 Masonry Works 1,444,222.08 12.46% 7 1.78% 1.78% 1.78% 1.78% 1.78% 1.78% 1.78%
4 Roofing Works 958,688.84 8.27% 1 8.27%
5 Wet Works 968,626.51 8.36% 2 4.18% 4.18%
6 Ceiling System 404,421.69 3.49% 1 3.49%
7 Doors & Windows 502,678.84 4.34% 1 4.34%
8 Plumbing Works 553,585.53 4.78% 3 1.59% 1.59% 1.59%
9 Electrical Works 1,150,379.19 9.93% 3 3.31% 3.31% 3.31%
10 Painting Works 732,538.24 6.32% 3 2.11% 2.11% 2.11%
11 Cabinetry Works 603,954.40 5.21% 1 5.21%
12 Other Finishing Works 196,000.00 1.69% 1 1.69%
11,588,109.79 1.00

% COMPLETED 2.62% 2.96% 2.96% 2.96% 2.96% 2.96% 2.96% 2.96% 2.96% 2.96% 2.96% 2.96% 1.78% 1.78% 1.78% 1.78% 1.78% 1.78% 1.78% 8.27% 7.67% 4.18% 4.34% 4.90% 4.90% 4.90% 2.11% 2.11% 2.11% 6.90%
CUMMULATIVE % 2.62% 5.58% 8.53% 11.49% 14.45% 17.40% 20.36% 23.32% 26.28% 29.23% 32.19% 35.15% 36.93% 38.71% 40.49% 42.27% 44.05% 45.83% 47.61% 55.88% 63.55% 67.73% 72.07% 76.97% 81.87% 86.78% 88.88% 90.99% 93.10% 100.00%

S CURVE
100.00%

95.00%

90.00%

85.00%

80.00%

75.00%

70.00%

65.00%

60.00%

55.00%

50.00%

45.00%

40.00%

35.00%

30.00%

25.00%

20.00%

15.00%

10.00%

5.00%

0.00%
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30