No Item Pekerjaan Harga Pekerjaan Minggu Ke-1 Minggu Ke-2 %
Pekerjaan %
1 2 3 4 5 6 7 8 9 10 11 12 13 14
100%
1 PEKERJAAN PERSIAPAN Rp 2,628,000.00 10.92% 5.46% 5.46%
2 PEKERJAAN STRUKTUR Rp 6,338,859.00 26.34% 5.27% 5.27% 5.27% 5.27% 5.27%
3 PEKERJAAN PASANGAN Rp 2,667,825.00 11.08% 3.69% 3.69% 3.69% 50%
4 PEKERJAAN INSTALASI Rp 5,223,935.00 21.70% 4.34% 4.34% 4.34% 4.34% 4.34%
5 PEKERJAAN FINISHING Rp 7,209,674.00 29.96% 5.99% 5.99% 5.99% 5.99% 5.99%
0%
TOTAL Rp 24,068,293.00 100% 5.46% 5.46% 5.27% 5.27% 5.27% 5.27% 8.96% 8.04% 8.04% 10.33% 10.33% 10.33% 5.99% 5.99%
Akumulasi Harian 5.46% 10.92% 16.19% 21.45% 26.72% 31.99% 40.95% 48.99% 57.02% 67.35% 77.69% 88.02% 94.01% 100.00%