DETAIL BREAKDOWN WORK VOLUME 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3

0 SCHEDULE
PIPING ERECTION - IFS PROJECT
A AWARD
B MOBILIZATION 100.0% 0.9%
Man Power
Heavy Equipment
C INDIRECT 90.0% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1%
D OTHERS 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.2%
E DEMOBILIZATION 0.2%
Demolish & Clearing Area 80.0%
F OFFICE AND INFRASTRUCTURE 2%
Temporary Office for Fabrication
Temporary Office for Field Installation
70.0%
Workshop For Fabrication
Storage for Permanent Material
Material Handling
60.0%
G PIPING WORK
Fabrication 1.7% 1.7% 2.6% 2.6% 3.5% 7.0% 7.0% 7.0% 7.0% 7.0% 5.2% 5.2% 5.2%
Welding Joint
Fabrication Pipe Support 50.0%

Threaded Joint
Instalation 0.3% 0.3% 0.3% 0.4% 0.4% 0.5% 0.8% 1.4% 1.4% 1.4% 1.4% 1.4% 1% 1% 1%
Install Pipe Support 40.0%
In-Line Instrument
Install Pipe Spool
Install Tagged Valve 30.0%
Install Valve
Install Lining Pipe
Special Cleaning 20.0%
Tie-In
H SCAFFOLDING 0.2% 0.2% 0.2% 0.3% 0.3% 0.6% 0.6% 0.6% 0.6% 0.6% 0.6% 0.3% 0.3%
I PRECOMMISIONING WORK 10.0%
1.6% 1.6% 1.6% 1.6% 1.6%
PREPARATION
PRESSURE TESTING / SERVICES TEST
PIPE INTERNAL CLEANING 4%
0.0%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1% 4% 2% 3% 3% 4% 8% 8% 8% 9% 9% 7% 7% 7% 3% 3% 3% 2% 6% 0%

1.1% 4.8% 7.0% 10.1% 13.2% 17.6% 25.4% 33.4% 41.7% 50.6% 59.8% 67.1% 74.5% 81.9% 85.1% 88.4% 91.4% 93.6% 99.5% 100.0%