09/11/2021

MASTER SCHEDULE
JETTY 2 TRESTLE RESTIFICATION

NOVEMBER 2021 DESEMBER 2021 JANUARI 2022 FEBRUARI 2022 MARET 2022
DURA- PERSENTASE
NO. URAIAN PEKERJAAN BOBOT I II III IV I II III IV I II III IV I II III IV I II
TION SCHEDULE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
INDIRECT COST / PREPARATORY WORKS
A Indirect Cost / Preparatory Works 84 days 100.00% 100%
1 Mob-Demob 5.72% 84 days 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36%
2 Preparation Works 12.01% 84 days 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75%
3 Project Management (4 months) 9.89% 84 days 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62%

90%
B Direct Cost STEEL STRUCTURE RECTIFICATIONS
B.1 Steel Structure Rectifications
1 Scaffolding installation (rent) 17.18% 64 days 1.23% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23%
2 Removal and renew baseplate supports main girders 65 days
2.1 Removal defect supports (Base plate) main girders 16 days
2.1.1 0 Base plate for WF-450.200.12.19 0.45% 11 days 0.23% 0.23%
2.1.2 0 Base plate for WF-700.200.12.22 0.09% 6 days 0.09% 80%
2.2 Jacking Main Girder 0.93% 5 days 0.93%
2.3 Chipping Concrete Base & Repair with Grouting 0.65% 5 days 0.65%
2.4 Fabrication, Re-Installation New Base Plate 17 days
2.4.1 0 Base plate for WF-450.200.12.19 0.65% 11 days 0.33% 0.33%
2.4.2 0 Base plate for WF-700.200.12.22 0.13% 6 days 0.07% 0.07%
2.5 Chemical Anchors for new base plate support 12 days
2.5.1 0 for Base plate for WF-450.200.12.19 1.03% 6 days 1.03%
2.5.2 0 for Base plate for WF-700.200.12.22 0.18% 6 days 0.18% 70%
3 Welding Inspection by NDT Penetrant (10%) 6.18% 6 days 6.18%
4 Welding Inspection by NDT X-Ray for girder heavy repair 0.99% 6 days 0.99%
5 Installation new members 17 days
5.1 Replacement Wind Bracing L-75x75x6 0.68% 6 days 0.68%
5.2
5.3
Replacement Crossing Beam C150x75x6,5x10
Replacement Grating Main support C150x75x6,5x10
1.26%
0.90%
6 days
6 days
1.26%
0.90%
61.19%
5.4 Replacement Grating Support L65x65x6 0.77% 6 days 0.77% 60%
5.5 Replacement/ Renew pipe support (Cantilever) 0.77% 6 days 0.77%
6 Cutting, patching, doubling parts 12 days
6.1 Cutting, patching, doubling WF-450.200.12.19 5.05% 6 days 5.05%
6.2 Cutting, patching, doubling (full web, one side) WF-450.200.12.19 1.13% 6 days 1.13%
6.3 Cutting, patching, doubling WF-700.200.12.22 0.13% 6 days 0.13%
7 Gusset plate replacement 6 days
7.1 Gusset plate replacement (th.10mm) Cross Girder C150x75x6,5x10 0.36% 6 days 0.36% 50%
7.2 Gusset plate replacement (th.10mm) Wind bracing L-75x75x6 0.30% 6 days 0.30%
8 Bolt replacement (M12-Galvanise) 6 days
8.1 Bolt replacement (M12) Cross Girder C150x75x6,5x10 0.11% 6 days 0.11%
8.2 Bolt replacement (M12) Wind bracing L-75x75x6 0.12% 6 days 0.12%
9 Removal HDPE wrap protection 5 days
9.1 Removal HDPE wrapping WF-700.200.12.22 0.06% 5 days 0.06%
9.2 Removal HDPE Wrapping Cross Girder C150x75x6,5x10 0.01% 5 days 0.01% 40%
10 Epoxy coating 6 days
10.1 Epoxy coating WF-450.200.12.19 0.02% 6 days 0.02%
10.2
10.3
Epoxy coating WF-700.200.12.22
Epoxy Coating Cross Girder C150x75x6,5x10
0.10%
0.01%
6 days
6 days
34.76% 0.10%
0.01%
10.4 Epoxy Coating Crossing Beam C150x75x6,5x10 0.03% 6 days 0.03%
11 Surface preparation and painting works 4 days
11.1 Repainting Bottom Structure (Girders, bracings) 4 days 30%
11.1.1 WF-450.200.12.19 1.00% 4 days 1.00%
11.1.2 WF-700.200.12.22 0.24% 4 days 0.24%
11.1.3 Cross Girder C150x75x6,5x10 0.53% 4 days 0.53%
11.1.4 Wind bracing L-75x75x6 0.42% 4 days 0.42%
11.2 Repainting Top Structure (Pipe & Walkway Supports) 11 days
11.2.1 Crossing Beam C150x75x6,5x10 0.52% 6 days 0.52%
11.2.2 Pipe Support C150x75x6,5x10 (Column & top sleeper) 0.63% 6 days 0.63% 20%
11.2.3 Grating Supports 0.87% 6 days 0.87%
11.2.4 0 Support L65x65x6 0.48% 6 days 0.48%
11.2.5 Pipe support (Cantilever) 0.09% 6 days 0.09%

9.90% 10%
CONCRETE STRUCTURE RECTIFICATIONS
B.2 Concrete Structure Rectifications
12 Repair Concrete pilecap (7 nos , 4mL x 0.9mW x 0.9mD)
12.1 Chipping concrete (est. 10cm th) until rebar exposed 2.34% 30 days 0.39% 0.39% 0.39% 0.39% 0.39% 0.39%
12.2 Installed shear connector chemical anchor dia. 12mm L 350mm 2.94% 6 days 2.94%
12.3 Installed new steel rebar 2.10% 15 days 0.70% 0.70% 0.70%
12.4 Installed Formwork 0.70% 6 days 0.70%
12.5 Chemical Grouting Admixture and Hydrophobic Concrete Coating for the entire pilecap concrete 19.27% 6 days 19.27% 0%

100.00%

TOTAL 1.73% 1.73% 3.18% 3.27% 4.53% 3.28% 7.72% 9.33% 4.82% 10.35% 7.05% 4.20% 6.22% 5.19% 24.05% 3.34%
PROGRES RENCANA (%) KUMULATIF 1.73% 3.45% 6.63% 9.90% 14.43% 17.71% 25.43% 34.76% 39.59% 49.94% 56.99% 61.19% 67.41% 72.61% 96.66% 100.0%
TOTAL
PROGRES AKTUAL (%) KUMULATIF