Project : AS-BUILT 2-STOREY RESIDENTIAL BUILDING W/ ROOF DECK

Location : LOT 8 BLK 4 MANGO BEND ST. GREENLAND SUBD PHASE 8, BRGY. STA. ANA TAYTAY RIZAL
Subject : Architectural Works
Date : March 11,2023

AS-BUILT 2-STOREY RESIDENTIAL BUILDING W/ ROOF DECK

TIMESCALE (WEEK)
MANPOWER
AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY
SL NO. DESCRIPTION OF WORK DURATION START FINISH AMOUNT WEIGHT PERCENT % PER DAY
PER DAY
1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 TOTAL %

A. General Requirements 24 25-Aug-21 3-Feb-22


a. Mobilization 1 7 6-Sep-21 13-Sep-21 37024.92 0.91% 0.91% 0.009087157 0.91% 0.00%
b. Permit, Licenses and Clearance, Bonds and Insruance 3 4 25-Aug-21 8-Sep-21 50000 1.23% 0.41% 0.41% 0.41% 0.41% 1.23% 0.00%
c. Temporary Facility and Utilities for Staff and Workers 5 7 13-Sep-21 8-Oct-21 37024.92 0.91% 0.18% 0.18% 0.18% 0.18% 0.18% 0.73% 0.18%
d. Installation of Temporary Safety Railings & Signages 20 2 13-Sep-21 1-Feb-22 37024.92 0.91% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.82% 0.09%
e. Site Documentation / Shop Drawing 20 3 6-Sep-21 1-Feb-22 4000 0.10% 0.00% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.08% 0.01%
f. As Built Drawing 11 1 8-Sep-21 17-Nov-21 49500 1.21% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.99% 0.22%
g. House Keeping and Proper Disposal of Rubbish and Other Deleterious 20 7 6-Sep-21 1-Feb-22 27768.69 0.68% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.61% 0.07%
h. Site Supervision/ Management 20 5 6-Sep-21 1-Feb-22 55537.37 1.36% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 1.23% 0.14%
i. Procurement of CSA Materials 22 4 6-Sep-21 3-Feb-22 37024.92 0.91% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.83% 0.08%
j. Procurement of MEPF Materials 22 4 6-Sep-21 3-Feb-22 37024.92 0.91% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.83% 0.08%
B. CIVIL WORKS 4 13-Sep-21 27-Oct-21 0.00%
a. Staking & Layout 1 2 13-Sep-21 20-Sep-21 18,410 0.45% 0.45% 0.45% 0.45% 0.00%
b. Chipping of Concrete 2 4 15-Sep-21 24-Sep-21 33,620.40 0.83% 0.41% 0.41% 0.41% 0.83% 0.00%
c. Excavation 2 5 16-Sep-21 30-Sep-21 142,157 3.49% 1.74% 1.75% 1.75% 3.49% 0.00%
d. Backfilling & Compaction 2 5 22-Oct-21 27-Oct-21 575,674 14.13% 7.06% 7.06% 7.06% 7.06%
e. Gravel Bedding 1 5 17-Sep-21 30-Sep-21 6,157.62 0.15% 0.15% 0.15% 0.15% 0.30% -0.15%
f. Vapor Barrier 2 3 20-Sep-21 30-Sep-21 24,002.65 0.59% 0.29% 0.30% 0.30% 0.59% 0.00%
C. STRUCTURAL WORKS 11 30-Sep-21 17-Dec-21 0.00%
a. Foundation 2 5 30-Sep-21 14-Oct-21 668,920.80 16.42% 8.21% 8.21% 8.21% 8.21% 24.63% -8.21%
b. Concrete Column Pedestal & Column 2 10 8-Oct-21 22-Oct-21 33,000.00 0.81% 0.41% 0.41% 0.41% 0.81% 0.00%
c. Concrete Footing Tie Beam 2 10 8-Oct-21 22-Oct-21 62,210 1.53% 0.76% 0.76% 0.76% 1.53% 0.00%
d. Slab on Grade 1 10 15-Oct-21 24-Oct-21 313,939.50 7.71% 7.71% 7.71% 7.71% 0.00%
f. Suspended Slab 2 10 26-Nov-21 10-Dec-21 627,880 15.41% 7.71% 7.71% 7.71% 15.41% 0.00%
g. Waterproofing 1 3 10-Dec-21 17-Dec-21 177,464.56 4.36% 4.36% 4.36% 4.36% 0.00%
D. MASONRY WORKS 14 10-Sep-21 14-Dec-21 0.00%
a. Laying of CHB 11 6 10-Sep-21 23-Nov-21 118,029.75 2.90% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 2.90% 0.00%
b. Plastering 13 6 17-Sep-21 14-Dec-21 78371.4 1.92% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 1.92% 0.00%
G. ARCHITECTURAL WORKS 18 17-Sep-21 19-Jan-22 0.00%
a. Wall Partition and Finishes 11 4 17-Sep-21 6-Dec-21 191,821.97 4.71% 0.43% 0.43% 0.43% 0.43% 0.43% 0.43% 0.43% 0.43% 0.43% 0.43% 0.43% 0.43% 4.71% 0.00%
b. Ceiling Finish Works 16 4 24-Sep-21 18-Jan-22 269,110.00 6.60% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 6.19% 0.41%
F. DOORS AND WINDOWS 6 14-Dec-21 21-Jan-22 0.00%
a. Installation of Doors 2 4 14-Dec-21 28-Dec-21 179,657.60 4.41% 2.20% 2.21% 2.21% 4.41% 0.00%
b. Installation of Windows 1 4 21-Dec-21 28-Dec-21 141,344.00 3.47% 3.47% 3.47% 3.47% 0.00%
a. Installation Door Contact to Auxiliary 1 4 28-Dec-21 4-Jan-22 15,810 0.39% 0.39% 0.39% 0.39% 0.00%
b. Painting Finishes 3 4 4-Jan-22 21-Jan-22 24,910.60 0.61% 0.20% 0.20% 0.20% 0.20% 0.61% 0.00%
% Completed 0.00% 0.00% 0.00% 0.41% 0.41% 1.85% 1.80% 3.97% 12.18% 9.99% 10.97% 17.54% 1.25% 0.84% 1.60% 1.60% 1.22% 8.93% 8.50% 7.14% 6.32% 1.03% 0.85% 0.85% 0.44% 0.24% 0.08% 0.00% 0.00% 0.00%
Cummulative % 0.00% 0.00% 0.00% 0.41% 0.82% 2.67% 4.47% 8.44% 20.62% 30.60% 41.58% 59.12% 60.37% 61.21% 62.80% 64.40% 65.63% 74.56% 83.06% 90.20% 96.52% 97.55% 98.40% 99.25% 99.69% 99.92% 100.00% 100.00% 100.00% 100.00%

Subtotal : 3,702,491.55
Total : 4,074,422.19 100.00%