Professional Documents
Culture Documents
WEEKLY REPORT
A. PROJECT PROGRES
Period (Week) : February - Week 3
Cumulative Progress Planning (%) : 33.21%
Cumulative Progress Realitation (%) : 34.41%
Deviation Progress (%) : 1.20%
Note: : More workers will come to catch up the progres
B. FINACIAL SITUATION
Total Contract : Rp 2,815,000,000.00
Paid Invoice : Rp 1,103,700,961.00
Balance : Rp 1,711,299,039.00
C. PROJECT ISSUE
Prepared by,
Agus Adnyana
Page 1
TIME SCHEDULE
PROJECT : VILLA NUSA
LOKASI : NUSA PENIDA
OWNER : MR. MAREK
Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24 Oct-24
NO WORK DESCRIPTION TOTAL BOBOT WEEK WEEK WEEK WEEK WEEK WEEK WEEK WEEK WEEK WEEK WEEK WEEK
( RP ) (%) 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2
3 BUILDING FINISHING
FIRST FLOOR
WALL WORK 164,108,725.91 5.48 1.37 1.37 1.37 1.37
WOOD DOOR WORK (estimation) 21,228,750.00 0.71 0.18 0.18 0.18 0.18
IRON DOOR AND WINDOW (estimation) 58,400,000.00 1.95 0.49 0.49 0.49 0.49
FLOOR WORK 97,681,100.00 3.26 0.82 0.82 0.82 0.82 50%
CEILING WORK 28,660,500.00 0.96 0.32 0.32 0.32
OTHERS WORK 113,650,000.00 3.79 0.76 0.76 0.76 0.76 0.76
4 SECOND WORK
WALL WORK 160,364,652.51 5.35 1.34 1.34 1.34 1.34
WOOD DOOR WORK (estimation) 12,743,750.00 0.43 0.14 0.14 0.14
FLOOR WORK 76,554,500.00 2.56 0.85 0.85 0.85
OTHERS WORK 34,500,000.00 1.15 0.38 0.38 0.38
TOTAL 2,996,253,518.33 100.00 1.38 1.38 1.38 2.99 1.62 1.62 1.62 2.69 2.69 1.62 2.63 2.63 2.63 2.63 3.71 2.84 2.84 2.84 1.82 1.82 1.82 1.82 1.82 1.88 1.88 1.88 3.24 3.11 2.44 3.20 2.33 2.33 2.82 2.06 2.38 2.15 2.15 2.55 2.80 1.60 1.60 1.36 1.36 1.36 1.05 0.54 0.54 0.54
BOBOT RENCANA KOMULATIF (%) - 1.38 2.75 4.13 7.12 8.74 10.35 11.97 14.66 17.35 18.96 21.60 24.23 26.87 29.50 33.21 36.05 38.90 41.74 43.56 45.39 47.21 49.04 50.86 52.73 54.61 56.48 59.73 62.84 65.28 68.48 70.81 73.14 75.96 78.02 80.40 82.55 84.70 87.26 90.05 91.65 93.25 94.61 95.98 97.34 98.39 98.93 99.46 100.00
REALISASI (%) 1.38 1.38 1.38 2.99 7.14 10.38 12.01 15.36 19.80 20.32 23.02 25.72 29.50 32.98 34.41
DEVIATION (%) - - 1.38 - 2.75 - 4.13 - 1.60 0.02 0.04 0.70 2.45 1.36 1.42 1.49 2.63 3.48 1.20
Agus Adnyana
Page 1
ATTACHMENT OF
PROJECT DOCUMENTATION
VILLA NUSA