TIME SCHEDULE
I PREPARING WORKING
1 Project fence 0.00 - 100%
II STRUCTURE WORK
A Foundation Work
11 Slab 1st Floor /metal work 39.90 5.70 5.70 5.70 5.70 5.70 5.70 5.70
12 Roof work 29.63 3.70 3.70 3.70 3.70 3.70 3.70 3.70 1.85 1.85 0%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
TOTAL 100.00 2.57 4.76 11.59 11.67 12.27 9.32 6.80 9.40 9.40 3.70 3.70 3.70 3.70 3.70 1.85 1.85
BOBOT RENCANA KOMULATIF (%) 0.00 2.568664 7.324921 18.91081 30.5821 42.84847 52.17341 58.97362 68.37726 77.7809 81.48408 85.18727 88.89045 92.59363 96.29682 98.14841 100
SELISIH (%)