TIME SCHEDULE

PROJECT : VILLA BEDUGUL


LOKASI : BEDUGUL
OWNER :

Sep-22 Oct-22 Nov-22 Dec-22


URAIAN PEKERJAAN BOBOT WEEK WEEK WEEK WEEK
(%) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

I PREPARING WORKING
1 Project fence 0.00 - 100%

2 Cut and fill 1.73 1.73

3 Bowplank 0.13 0.13

4 Storage, office, worker house, toilet 0.71 0.71


(water and electricity by owner)

II STRUCTURE WORK
A Foundation Work

1 Micropile (by PT. EDO) 0.00 -

2 Pile Cap (by PT. EDO) 0.00 -

3 Pedestal Column P1 0.62 0.62


50%
4 Stone foundations 5.71 2.86 2.86

5 Tie Beam S1 25 x 50 3.83 1.28 1.28 1.28

6 Tie Beam S2 20 x 40 2.11 1.05 1.05

7 Tie Beam S3 20 x 30 1.40 0.70 0.70

8 Slab Floor 10 Thk 5.88 2.94 2.94

9 Slab 1st Floor 7.25 3.62 3.62

10 Stair work 1.10 1.10

11 Slab 1st Floor /metal work 39.90 5.70 5.70 5.70 5.70 5.70 5.70 5.70

12 Roof work 29.63 3.70 3.70 3.70 3.70 3.70 3.70 3.70 1.85 1.85 0%

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
TOTAL 100.00 2.57 4.76 11.59 11.67 12.27 9.32 6.80 9.40 9.40 3.70 3.70 3.70 3.70 3.70 1.85 1.85

BOBOT RENCANA KOMULATIF (%) 0.00 2.568664 7.324921 18.91081 30.5821 42.84847 52.17341 58.97362 68.37726 77.7809 81.48408 85.18727 88.89045 92.59363 96.29682 98.14841 100

BOBOT REALISASI KOMULATIF (%)

SELISIH (%)

Ubud, 24 Agustus 2022


Agus Adnyana