From Date : Monday, February 03, 2020 SUMMARY WEEKLY PROGRESS

To Date : Sunday, February 09, 2020

PROJECT : 33000 TPA CAP. FERRONICKEL SMELTING PLANT AREA : PROCESS PLANT & INFRASTRUCTURE LOCATION : BUA KAB.LUWU - INDONESIA

SUBJECT : PRIMARY BATCHING SYSTEM TITTLE : SUMMARY REV : B PAGE : 1 OF 6

WORK DONE QUANTITY


NO ITEM WORK Unit Volume Bobot (%)
Current (%) Previous (%) Total (%) % Subcont

A Earth Work Ls 1.00 3.920 - 3.920 3.920 3.92%

1 Excavation m3 2,319.00 3.920 - 3.920 3.920 100%

B Foundation Work Ls 1.00 96.080 6.227 43.875 50.102 50.10%

1 Lean Concrete K100 m3 41.00 1.334 - 1.334 1.334 100%

2 Concrete 30 Mpa for Foundation m3 531.00 29.893 1.182 8.782 9.964 33.33%

3 Rebar kgs 109,479.78 52.641 4.849 31.999 36.848 70%

4 Formwork m2 1,708.25 11.422 - 1.630 1.630 14.27%

5 Instal embedded plate kgs 1,584.58 0.747 0.196 0.130 0.326 43.58%

6 Instal anchor bolt kgs 90.42 0.043 - - - 0.00%

ACCUMULATIVE OF WEEKLY PROGRESS 54.02%

SPV : Name : Abdul Rahman DATE : DOC. NO. :

SE : Name : Sapri DATE :


PREP-B151-C-BG34-RX-A06
SM : Name : Zulkarnain ST. DATE :
From Date : Monday, February 03, 2020 SUMMARY W
To Date : Sunday, February 09, 2020
PROJECT : 33000 TPA CAP. FERRONICKEL SMELTING PLANT
SUBJECT : BATCHING SYSTEM

Volume
No Uraian Pekerjaan Unit
Total Terlaksana

A Earth Work
1 Excavation m3 2,319.00
B Foundation Work
1 Lean Concrete K100 m3 41.00
2 Concrete 30 Mpa for Foundation m3 531.00
3 Rebar kgs 109,479.78
4 Formwork m2 1,708.25
5 Instal embedded plate kgs 1,584.58
6 Instal anchor bolt kgs 90.42
ACCUMULATIVE OF WEEK
5 Perkerasan Lean Concrete (B0) Ls 1.00
a Lean Concrete mutu K125, tebal = 10 cm. m3 735.25
b Formwork m2 155.80
6 Drainase Ls 1.00

SPV : Name

SE : Name

SM : Name
SUMMARY WEEKLY PROGRESS

AREA : PROCESS PLANT & INFR LOCATION : BUA KAB.LUW


TITTLE : SUMMARY RE : B

2,662,071,000
Volume WORK DONE QUANT
Belum Harga Satuan Total Bobot (%)
Current (%) Previous (%)
terlaksana
104,365,765 3.920 - 3.920
45,000 104,365,765 3.920 - 3.920
2,557,705,843 96.080 6.227 43.875
875,670 35,502,050 1.334 - 1.334
1,500,000 795,772,697 29.893 1.182 8.782
12,800 1,401,341,168 52.641 4.849 31.999
178,000 304,068,712 11.422 - 1.630
12,550 19,886,424 0.747 0.196 0.130
12,550 1,134,792 0.043 - -
ACCUMULATIVE OF WEEKLY PROGRESS
1.00 680,043,840.00 100.00000000 - 18.4787734
735.25 881,200.00 647,902,300.00 95.273607654 - 17.534101625
155.80 206,300.00 32,141,540.00 4.726392346 - 0.944671744
1.00 411,726,500.00 100.00000000 - -

: Abdul Rahman DATE : D

: Sapri DATE :
PREP-B15
: Zulkarnain ST. DATE :
ATION : BUA KAB.LUWU - INDONESIA
PAGE : 1 OF 6

WORK DONE QUANTITY

Total (%) % Subcont

3.920 3.92%
3.920 100%
50.102 50.10%
1.334 100%
9.964 33.33%
36.848 70%
1.630 14.27%
0.326 43.58%
- 0.00%
54.02%
18.4787734 19.20% BMS
17.534101625 18.40%
0.944671744 19.99%
- 0% BMS

DOC. NO. :

PREP-B151-C-BG34-RX-A06
Project : 33000 T/A FERRONICKEL SMELTING PLANT

Sub.Project : PRIMARY BATCHING SYSTEM

Area : PROCESS PLANT & INFRASTRUCTURE

Date : 3 - 9 FEBRUARI 2020

Penegecoran Elevasi -4.270 & -4.145 Penegecoran Elevasi -4.270 & -4.145

Vibrating concrete Vibrating concrete

Joint Inscpection Kontrol elevasi


Project : 33000 T/A FERRONICKEL SMELTING PLANT
Sub.Project : PRIMARY BATCHING SYSTEM
Area : PROCESS PLANT & INFRASTRUCTURE
Date : 3 - 9 FEBRUARI 2020

Install bekisting Install bekisting

Pembesian slab section 4-4, 5-5, 6-6 Pembesian slab section 4-4, 5-5, 6-6

Fabrikasi rebar Pembesian slab section 4-4, 5-5, 6-6


WEEKLY WEATHER RECORD

From date Monday, February 03, 2020


PERIODE
To date Sunday, February 09, 2020

DATE 3 4 5 6 7 8 9
Curah Hujan Durasi

NO WAKTU

1 06 - 07 Siang Hari Jam

2 07 - 08 Malam Hari Jam

3 08 - 09 Jumlah Curah Hujan Jam

4 09 - 10 Keterangan

5 10 - 11 Cerah

6 11 - 12 Lembur

7 12 - 13 Hujan

8 13 - 14 Mendung

Libur Nasional/No
9 14 - 15
actifity

10 15 - 16 Catatan

11 16 - 17

12 17 - 18

13 18 - 19

14 19 - 20

15 20 - 21

16 21 - 22

17 22 - 23

18 23 - 24

19 00 - 01

20 01 - 02

21 02 - 03

22 03 - 04

23 04 - 05

24 05 - 06

SPV Abdul Rahman Date : DOC. NO.

SE Sapri Date :
PREP-B151-C-BG34-RX-A06
PREP-B151-C-BG34-RX-A06
SM Zulkarnain ST. Date :
MANPOWER RECORD

Week 3 - 9 Februari 2020


Description Satuan
Day 3 4 5
Site Project
Site Manager Oh 6.00 1.00 1.00 1.00
Site Enginering Oh 6.00 1.00 1.00 1.00
Supervisor Oh 6.00 1.00 1.00 1.00
QA / QC Oh - - - -
Logistik & Procurement Oh 18.00 3.00 3.00 3.00
Document Control (DC) Oh 6.00 1.00 1.00 1.00
Stock keeper (SK) Oh 36.00 6.00 6.00 6.00
Total 78.00 13.00 13.00 13.00
Daily Manpower
Head Foreman Oh 6.00 1.00 1.00 1.00
Foreman Oh 54.00 9.00 9.00 9.00
Helper (Civil Work) Oh 96.00 16.00 16.00 16.00
Helper SK Oh - - - -
Helper Mekanik Oh - - - -
Operator Heavy Equipment Oh 8.00 1.00 1.00 2.00
Operator Mobil Truck Oh 22.00 3.00 3.00 5.00
Total 186.00 30.00 30.00 33.00
EQUIPMENT/TOOLS RECORD
Week 3 - 9 Februari 2020
Description Satuan
Day 3 4 5
Heavy Equipment
Crawler Crane Zoomlion 55 ton Unit 2.00 - - 1.00
Excavator 320D2 (CAT) Unit 6.00 1.00 1.00 1.00
Excavator 320D2 (CAT) Unit - - - -
Vibrator Roller Yialing 212 Unit - - - -
Dump Truck (HOWO) Unit 12.00 2.00 2.00 2.00
Dump Truck (Dyna) Unit 6.00 1.00 1.00 1.00
Motor Grader Unit - - - -
Concrete Pump Unit - - - -
Mobil Mixer Cap.7m3 Unit 2.00 - - 1.00
Mobil Mixer Cap.6m3 Unit 2.00 - - 1.00
Molen Tiger Unit - - - -
Total 28.00 4.00 4.00 7.00

- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - -
- - - -
MANPOWER RECORD

3 - 9 Februari 2020
6 7 8 9

1.00 1.00 1.00 -


1.00 1.00 1.00 -
1.00 1.00 1.00 -
- - - -
3.00 3.00 3.00 -
1.00 1.00 1.00 -
6.00 6.00 6.00 -
13.00 13.00 13.00 -

1.00 1.00 1.00 -


9.00 9.00 9.00 -
16.00 16.00 16.00 -
- - - -
- - -
1.00 1.00 2.00 -
3.00 3.00 5.00 -
30.00 30.00 33.00 -
QUIPMENT/TOOLS RECORD
3 - 9 Februari 2020
6 7 8 9

- - 1.00 -
1.00 1.00 1.00 -
- - - -
- - - -
2.00 2.00 2.00 -
1.00 1.00 1.00 -
- - - -
- - - -
- - 1.00 -
- - 1.00 -
- - - -
4.00 4.00 7.00 -

- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - -
- - - -