You are on page 1of 8

From Date : Monday, January 06, 2020 SUMMARY WEEKLY PROGRESS

To Date : Sunday, January 12, 2020

PROJECT : 33000 TPA CAP. FERRONICKEL SMELTING PLANT AREA : PROCESS PLANT & INFRASTRUCTURE LOCATION : BUA KAB.LUWU - INDONESIA

SUBJECT : SMELTING WORKSHOP TITTLE : SUMMARY REV : B PAGE : 1 OF 6

WORK DONE QUANTITY


NO ITEM WORK Unit Volume Bobot (%)
Current (%) Previous (%) Total (%) % Subcont

A Bored Piles Work Ls 1.00 44.592 11.395 29.495 40.890 91.70%

1 Pekerjaan Boring titik 103 5.489 0.533 4.530 5.063 92.24%

2 Rebar kg 158,775 15.159 4.227 9.683 13.910 91.76%

3 Concrete f'c 30 Mpa m3 2,140 23.944 6.635 15.282 21.917 91.54%

B Foundation Work Ls 1.00 46.575 0.302 - 0.302 0.65%

1 Excavation for Foundation m3 3,651 0.621 0.129 - 0.129 20.70%

2 Backfill m3 821 0.075 - - - 0.00%

3 Lean Concrete K-100 t=10cm m3 120 0.833 0.174 - 0.174 20.83%

4 Rebar kg 193,297 18.455 - - - 0.00%

5 Formwork m2 4,320 5.736 - - - 0.00%

6 Concrete K-350 m3 2,026 20.855 - - - 0.00%

C Floor Work Ls 1.00 8.833 - - - 0.00%

1 Lean Concrete K-100 t=10cm m3 308 2.138 - - - 0.00%

2 Concrete K-300 m3 513 5.740 - - - 0.00%

3 Formwork m2 71 0.094 - - - 0.00%

4 Finishing by trowel m2 2,565 0.861 - - - 0.00%

ACCUMULATIVE OF WEEKLY PROGRESS (%) 41.19

SPV : Name : M. Agung Amiluhur DATE : DOC. NO. :

SE : Name : Sapri DATE :


PREP-B151-C-BL34-RX-A09
SM : Name : Zulkarnain ST. DATE :
PREP-B151-C-BL34-RX-A09
SM : Name : Zulkarnain ST. DATE :
Project : 33000 T/A FERRONICKEL SMELTING PLANT

Sub.Project : SMELTING WORKSHOP (BORED PILES)

Area : PROCESS PLANT & INFRASTRUCTURE

Date : 6-12 JANUARI 2020

Pekerjaan LC Concrete Furnace Base Pekerjaan LC Concrete Furnace Base

Excavasi Furnace Base

Stake out Furnace Base Excavasi Furnace Base


Project : 33000 T/A FERRONICKEL SMELTING PLANT
Sub.Project : SMELTING WORKSHOP (BORED PILES)
Area : PROCESS PLANT & INFRASTRUCTURE
Date : 6-12 JANUARI 2020

Pekerjaan Boring grid J8A CT-2A Install rebar grid J7A CT-2A

Install pipa tremi Concreting grid J7A CT-2A


WEEKLY WEATHER RECORD

From date Monday, January 06, 2020


PERIODE
To date Sunday, January 12, 2020

DATE 6 7 8 9 10 11 12
Curah Hujan Durasi

NO WAKTU

1 06 - 07 Siang Hari Jam

2 07 - 08 Malam Hari Jam

3 08 - 09 Jumlah Curah Hujan Jam

4 09 - 10 Keterangan

5 10 - 11 Cerah

6 11 - 12 Lembur

7 12 - 13 Hujan

8 13 - 14 Mendung

Libur Nasional/No
9 14 - 15
actifity

10 15 - 16 Catatan

11 16 - 17

12 17 - 18

13 18 - 19

14 19 - 20

15 20 - 21

16 21 - 22

17 22 - 23

18 23 - 24

19 00 - 01

20 01 - 02

21 02 - 03

22 03 - 04

23 04 - 05

24 05 - 06

SPV M. Agung Amiluhur Date : DOC. PAGE NO.

SE Sapri Date :
PREP-B151-C-BL34-RX-A09
SM Zulkarnain ST. Date :
MANPOWER RECORD

Week 6-12 Januari 2020


Description Satuan
Day 6 7 8 9 10 11 12
Site Project
Site Manager Oh 6.00 1.00 1.00 1.00 1.00 1.00 1.00 -
Site Enginering Oh 6.00 1.00 1.00 1.00 1.00 1.00 1.00 -
Supervisor Oh 6.00 1.00 1.00 1.00 1.00 1.00 1.00 -
QA / QC Oh - - - - - - - -
Logistik & Procurement Oh 12.00 2.00 2.00 2.00 2.00 2.00 2.00 -
Document Control (DC) Oh 6.00 1.00 1.00 1.00 1.00 1.00 1.00 -
Stock keeper (SK) Oh 24.00 4.00 4.00 4.00 4.00 4.00 4.00 -
Total 60.00 10.00 10.00 10.00 10.00 10.00 10.00 -
Daily Manpower -
Head Foreman Oh - - - - - - - -
Foreman Oh 12.00 2.00 2.00 2.00 2.00 2.00 2.00 -
Helper Oh 12.00 2.00 2.00 2.00 2.00 2.00 2.00 -
Helper SK Oh - - - - - - - -
Helper Mekanik Oh - - - - - - -
Operator Heavy Equipment Oh 12.00 2.00 2.00 2.00 2.00 2.00 2.00 -
Operator Mobil Truck Oh 18.00 3.00 3.00 3.00 3.00 3.00 3.00 -
Total 54.00 9.00 9.00 9.00 9.00 9.00 9.00 -
EQUIPMENT/TOOLS RECORD
Week 6-12 Januari 2020
Description Satuan
Day 6 7 8 9 10 11 12
Heavy Equipment
SANY SR220 Unit 6.00 1.00 1.00 1.00 1.00 1.00 1.00 -
Crawler Crane Zoomlion 55 ton Unit - - - - - - - -
Mobil Yap Crane 10 ton (BOB LIFT) Unit - - - - - - - -
Excavator 320D2 (CAT) Unit 6.00 1.00 1.00 1.00 1.00 1.00 1.00 -
Excavator 320D2 (CAT) Unit - - - - - - - -
Vibrator Roller Yialing 212 Unit - - - - - - - -
Dump Truck (HOWO) Unit 6.00 1.00 1.00 1.00 1.00 1.00 1.00 -
Dump Truck (Dyna) Unit - - - - - - - -
Motor Grader Unit - - - - - - - -
Mobil Mixer Cap.7m3 Shacman Unit 6.00 1.00 1.00 1.00 1.00 1.00 1.00 -
Mobil Mixer Cap.6m3 Shacman Unit 6.00 1.00 1.00 1.00 1.00 1.00 1.00 -
Molen Tiger Unit - - - - - - - -
Total 18.00 5.00 5.00 5.00 5.00 5.00 5.00 -

- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - -
- - - - - - - -