You are on page 1of 11

From Date : Monday, September 30, 2019 SUMMARY WEEKLY PROGRESS

To Date : Sunday, October 06, 2019

PROJECT : 33000 TPA CAP. FERRONICKEL SMELTING PLANT AREA : PROCESS PLANT & INFRASTRUCTURE LOCATION : BUA KAB.LUWU - INDONESIA

SUBJECT : RAW MATERIAL WAREHOUSE TITTLE : SUMMARY REV : A PAGE : 1 OF 1

WORK DONE QUANTITY


NO ITEM WORK Unit Volume Bobot (%)
Current (%) Previous (%) Total (%) % Executed

1 2 3 4 5 6 7 8 9 10

A Earth Work Ls 1.00 1.049 - 1.027 1.027 1.03%

1 Excavation m3 446.94 0.817 - 0.804 0.804 98.43%

2 Back fill m3 285.29 0.232 - 0.223 0.223 96.24%

B Foundation Work Ls 1.00 98.951 24.062 25.669 49.731 49.73%

1 B0 K100 m3 585.45 20.820 9.602 3.127 12.729 61.14%

2 Beton K300 Footing m3 100.80 5.031 - 4.948 4.948 98.34%

3 Beton K300 Column m3 18.82 0.939 - 0.861 0.861 91.65%

4 Beton K300 Ground Beam m3 45.90 2.291 - 2.088 2.088 91.13%

5 Floor Work m3 1,080.00 53.909 14.376 - 14.376 26.67%

6 Rebar kg 16,696.64 8.679 - 8.001 8.001 92.18%

7 Formwork m2 893.76 6.461 - 6.357 6.357 98.39%

8 Install Anchor Bolt kg 1,025.28 0.312 - 0.287 0.287 91.90%

9 Grouting 50 mm m3 2.00 0.113 0.085 - 0.085 75.00%

10 Second Grouting 300 mm m3 7.00 0.395 - - - 0.00%

ACCUMULATIVE OF WEEKLY PROGRESS 50.76%

SPV : Name : Abdul Rahman DATE : DOC. PAGE NO. :

SE : Name : Sapri DATE :


PREP-B151-C-BU34-RX-013
SM : Name : Zulkarnain ST. DATE :
PREP-B151-C-BU34-RX-013
SM : Name : Zulkarnain ST. DATE :
Project : 33000 T/A FERRONICKEL SMELTING PLANT

Sub.Project : RAW MATERIAL WAREHOUSE

Area : : PROCESS PLANT & INFRASTRUCTURE

Date : 30 September - 6 Oktober 2019

Levelling ground eksisting menggunakan Unit Grader Pemadatan Subbase menggunakan Unit Vibro Roller

Fabrikasi bekisting floor work Instal besi wiremesh 2 layer

Pengecoran lantai warehouse mutu beton K-300 Pengecoran lantai warehouse mutu beton K-300
Project : 33000 T/A FERRONICKEL SMELTING PLANT
Sub.Project : RAW MATERIAL WAREHOUSE
Area : : PROCESS PLANT & INFRASTRUCTURE
Date : 30 September - 6 Oktober 2019

Bongkar dan perapihan bekisting

0 Bongkar dan perapihan bekisting

Area Raw Material Warehouse terkini


WEEKLY WEATHER RECORD

From date Monday, September 30, 2019


PERIODE
To date Sunday, October 06, 2019

DATE 30 1 2 3 4 5 6
Curah Hujan Durasi

NO WAKTU

1 06 - 07 Siang Hari Jam

2 07 - 08 Malam Hari Jam

3 08 - 09 Jumlah Curah Hujan Jam

4 09 - 10 Keterangan

5 10 - 11 Cerah

6 11 - 12 Lembur

7 12 - 13 Hujan

8 13 - 14 Mendung

Libur Nasional/No
9 14 - 15
actifity

10 15 - 16 Catatan

11 16 - 17

12 17 - 18

13 18 - 19

14 19 - 20

15 20 - 21

16 21 - 22

17 22 - 23

18 23 - 24

19 00 - 01

20 01 - 02

21 02 - 03

22 03 - 04

23 04 - 05

24 05 - 06

SPV Abdul Rahman Date : DOC. PAGE NO.

SE Sapri Date :
PREP-B151-C-BU34-RX-013
PREP-B151-C-BU34-RX-013
SM Zulkarnain ST. Date :
MANPOWER RECORD

Week 30 September - 6 Oktober 2


Description Satuan
Day 30 1 2
Site Project
Site Manager Oh 6.00 1.00 1.00 1.00
Site Enginering Oh 6.00 1.00 1.00 1.00
Supervisor Oh 6.00 1.00 1.00 1.00
QA / QC Oh - - - -
Logistik & Procurement Oh 7.00 1.00 1.00 1.00
Document Control (DC) Oh - - - -
Stock keeper (SK) Oh 12.00 2.00 2.00 2.00
Total 37.00 6.00 6.00 6.00
Daily Manpower
Head Foreman Oh 6.00 1.00 1.00 1.00
Foreman Oh 72.00 12.00 12.00 12.00
Helper (Civil Work) Oh 144.00 24.00 24.00 24.00
Helper SK Oh - - - -
Helper Mekanik Oh - - - -
Operator Heavy Equipment Oh 18.00 3.00 3.00 3.00
Operator Mobil Truck Oh 30.00 5.00 5.00 5.00
Total 270.00 45.00 45.00 45.00
EQUIPMENT/TOOLS RECORD
Week 30 September - 6 Oktober 2
Description Satuan
Day 30 1 2
Heavy Equipment
Crawler Crane Zoomlion 55 ton Unit - - - -
Excavator 320D2 (CAT) Unit 6.00 1.00 1.00 1.00
Excavator 320D2 (CAT) Unit - - - -
Vibrator Roller Yialing 212 Unit 6.00 1.00 1.00 1.00
Dump Truck (HOWO) Unit 12.00 2.00 2.00 2.00
Dump Truck (Dyna) Unit 6.00 1.00 1.00 1.00
Motor Grader Unit 6.00 1.00 1.00 1.00
Mobil Mixer Cap.8m3 Unit 6.00 1.00 1.00 1.00
Mobil Mixer Cap.5m3 Unit 6.00 1.00 1.00 1.00
Molen Tiger Unit - - - -
Total 42.00 8.00 8.00 8.00

- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - -
- - - -
MANPOWER RECORD

30 September - 6 Oktober 2019


3 4 5 6

1.00 1.00 1.00 -


1.00 1.00 1.00 -
1.00 1.00 1.00 -
- - - -
2.00 1.00 1.00 -
- - - -
2.00 2.00 2.00 -
7.00 6.00 6.00 -

1.00 1.00 1.00 -


12.00 12.00 12.00 -
24.00 24.00 24.00 -
- - - -
- - -
3.00 3.00 3.00 -
5.00 5.00 5.00 -
45.00 45.00 45.00 -
QUIPMENT/TOOLS RECORD
30 September - 6 Oktober 2019
3 4 5 6

- - - -
1.00 1.00 1.00 -
- - - -
1.00 1.00 1.00 -
2.00 2.00 2.00 -
1.00 1.00 1.00 -
1.00 1.00 1.00 -
1.00 1.00 1.00 -
1.00 1.00 1.00 -
- - - -
8.00 8.00 8.00 -

- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - -
- - - -

You might also like