Prepared by :
SITE PT CERIA NUGRAHA INDOTAMA MINE TECHNICAL CONTROL
MTD ORE PRODUCTION DEC 2020
ORE GETTING ACCMULATIF PRODUCTION
ACTUAL
DATE ACTUAL ACH PROBLEM PRODUKSI
TARGET SHIFT I SHIFT II PRODUKSI ACHIEV TARGET DEVIASI
PRODUKSI (MT) % PRODUKSI
RIT MT RIT MT RIT MT %
28-Dec-20 1,982 41 574 0 0 574 29% 54,163 41 31612 -22551 58.4% Shift I slippery 8.30 - 10.22 , Jam 14.00 wait SM , Shift II Stock ore low grade hujan jan 12.00 ,
Shift I slippery dan ore getting karena hasil SM stock ore bagian selatan low grade , ore getting bagian utara, Shift II hujan jam
29-Dec-20 1,982 0 0 27 378 378 19% 56,146 27 31990 -24156 57.0%
12.00
30-Dec-20 1,982 76 1064 0 0 1,064 54% 58,128 76 33054 -25074 56.9% Shift I Pembenahan loading point, Shuft II hujan jam 10.00 dan gempa bumi
31-Dec-20 991 0 0 0 0 0 0% - 0.0% Shift I slippery,hujan gerimis jam 12.00-16.00 , shift II Libur
2
REVIEW PRODUCTION ORE WEEK 1
PERIODE 28 DEC 20 – 3 JAN 21
3
Simulasi Unit GSI
EXISTING UNIT
UNIT ACTUAL RFU BD REMARKS
PC 300 4 3 1 308
PC 200 12 11 1 Exca 213 accident
DT 20T 14 13 1
BULLDOZER 2 2 0
MOTORGRADER 1 1 0
COMPACTOR 1 0 1 Transmisi bermasalah
LIGHTING TOWER 5 5 0
5