Wave-2 Medinah YANBU-196 Villas

Activity ID Activity Name Original Start Finish Total 2020 2021


Duration Float Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

Wave-2 Medinah YANBU-196 Villas 287 01-Jan-20 30-Nov-20 0 30-Nov-20, Wave-2 Medinah YANBU-196 Villas

General 287 01-Jan-20 30-Nov-20 0 30-Nov-20, General


A1010 Award of Contract (Issue of NTP1) 0 01-Jan-20* 154 Award of Contract (Issue of NTP1)

A1020 Ph 1 -Design Mockup & Sample Approvals (90 calendar days) 79 01-Jan-20 01-Apr-20 1 Ph 1 -Design Mockup & Sample Approvals (90 calendar days)

A1030 Approval on Ph-1 (Issue of NTP2) 0 02-Apr-20 1 Approval on Ph-1 (Issue of NTP2)

A1040 Ph 2 -Procurement, Mobilisation, Establishing Factory / V.O works (2 months) 52 02-Apr-20 01-Jun-20 1 Ph 2 -Procurement, Mobilisation, Establishing Factory / V.O works (2 months)

A1050 Access of Contractor to site (Issue of NTP3)-Construction Start 0 02-Jun-20 1 Access of Contractor to site (Issue of NTP3)-Construction Start

Contract Milestones 104 01-Aug-20 30-Nov-20 0 30-Nov-20, Contract Milestones


W1080 Completion of 10% Units --20 in 60 days 0 01-Aug-20* 0 Completion of 10% Units --20 in 60 days

W1090 Completion of 20% Units --39 in 30 days 0 01-Sep-20* 0 Completion of 20% Units --39 in 30 days

W1100 Completion of 30% Units --59 in 30 days 0 01-Oct-20* 0 Completion of 30% Units --59 in 30 days

W1110 Completion of 40% Units --78 in 60 days 0 30-Nov-20* 0 Completion of 40% Units --78 in 60 days

Engineering 45 01-Jan-20 22-Feb-20 154 22-Feb-20, Engineering


A1060 Dwgs Submission & Approvals 45 01-Jan-20 22-Feb-20 154 Dwgs Submission & Approvals

Procurement 88 23-Feb-20 03-Jun-20 154 03-Jun-20, Procurement


A1070 Procurement of Civil & MEP items 88 23-Feb-20 03-Jun-20 154 Procurement of Civil & MEP items

Construction 155 02-Jun-20 29-Nov-20 1 29-Nov-20, Construction


1BHK 0 0
2BHK-80 64 02-Jun-20 15-Aug-20 1 15-Aug-20, 2BHK-80
A1120 20 villas @24 days per 2 villas 34 02-Jun-20 11-Jul-20 1 20 villas @24 days per 2 villas

A1130 20 villas @24 days per 2 villas 34 14-Jun-20 22-Jul-20 1 20 villas @24 days per 2 villas

A1210 20 villas @24 days per 2 villas 34 25-Jun-20 03-Aug-20 1 20 villas @24 days per 2 villas

A1220 20 villas @24 days per 2 villas 34 07-Jul-20 15-Aug-20 1 20 villas @24 days per 2 villas

3BHK-56 54 19-Jul-20 19-Sep-20 1 19-Sep-20, 3BHK-56


A1140 20 villas @ 26 days per 2 villas 36 19-Jul-20 29-Aug-20 1 20 villas @ 26 days per 2 villas

A1150 20 villas @ 26 days per 2 villas 36 30-Jul-20 09-Sep-20 1 20 villas @ 26 days per 2 villas
A1160 16 villas @ 26 days per 2 villas 34 11-Aug-20 19-Sep-20 1 16 villas @ 26 days per 2 villas

4BHK-60 87 20-Aug-20 29-Nov-20 1 29-Nov-20, 4BHK-60


A1170 20 villas @ 28 days per 1 villas 48 20-Aug-20 14-Oct-20 1 20 villas @ 28 days per 1 villas

A1180 20 villas @ 28 days per 1 villas 48 13-Sep-20 07-Nov-20 1 20 villas @ 28 days per 1 villas

A1190 20 villas @ 28 days per 1 villas 47 06-Oct-20 29-Nov-20 1 20 villas @ 28 days per 1 villas

Project Close-out 0 29-Nov-20 29-Nov-20 1 29-Nov-20, Project Close-out


A1200 Closing of Project 0 29-Nov-20 1 Closing of Project

Remaining Level of Effort Remaining Work Date Revision Checked Approved


Page 1 of 1
Actual Work Critical Remaini...