Wave-2 Medinah YANBU-196 Villas 287 01-Jan-20 30-Nov-20 0 30-Nov-20, Wave-2 Medinah YANBU-196 Villas
A1020 Ph 1 -Design Mockup & Sample Approvals (90 calendar days) 79 01-Jan-20 01-Apr-20 1 Ph 1 -Design Mockup & Sample Approvals (90 calendar days)
A1030 Approval on Ph-1 (Issue of NTP2) 0 02-Apr-20 1 Approval on Ph-1 (Issue of NTP2)
A1040 Ph 2 -Procurement, Mobilisation, Establishing Factory / V.O works (2 months) 52 02-Apr-20 01-Jun-20 1 Ph 2 -Procurement, Mobilisation, Establishing Factory / V.O works (2 months)
A1050 Access of Contractor to site (Issue of NTP3)-Construction Start 0 02-Jun-20 1 Access of Contractor to site (Issue of NTP3)-Construction Start
W1090 Completion of 20% Units --39 in 30 days 0 01-Sep-20* 0 Completion of 20% Units --39 in 30 days
W1100 Completion of 30% Units --59 in 30 days 0 01-Oct-20* 0 Completion of 30% Units --59 in 30 days
W1110 Completion of 40% Units --78 in 60 days 0 30-Nov-20* 0 Completion of 40% Units --78 in 60 days
A1130 20 villas @24 days per 2 villas 34 14-Jun-20 22-Jul-20 1 20 villas @24 days per 2 villas
A1210 20 villas @24 days per 2 villas 34 25-Jun-20 03-Aug-20 1 20 villas @24 days per 2 villas
A1220 20 villas @24 days per 2 villas 34 07-Jul-20 15-Aug-20 1 20 villas @24 days per 2 villas
A1150 20 villas @ 26 days per 2 villas 36 30-Jul-20 09-Sep-20 1 20 villas @ 26 days per 2 villas
A1160 16 villas @ 26 days per 2 villas 34 11-Aug-20 19-Sep-20 1 16 villas @ 26 days per 2 villas
A1180 20 villas @ 28 days per 1 villas 48 13-Sep-20 07-Nov-20 1 20 villas @ 28 days per 1 villas
A1190 20 villas @ 28 days per 1 villas 47 06-Oct-20 29-Nov-20 1 20 villas @ 28 days per 1 villas