Engineering, Procurement & Construction Work for Natural Gas bypass line on Lump sum Turn Key (LSTK)

P.O.#:.  6241907665
Proposed Remaining Activity Revised Baseline Schedule

# Activity ID Activity Name Activity Status Duration Start Finish Nov 01 Nov 08 Nov 15 Nov 22 Nov 29 Dec 06 Dec 13 Dec 20
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
1 48 20.Aug.20 A 24.Dec.20 EPC Work for Natural Gas Bypass Line
EPC Work for Natural Gas Bypass Line
2 General 14 20.Aug.20 A 3.Nov.20

3 Project Documents 0
4 Engineering 14 20.Aug.20 A 3.Nov.20
5 A1070 Issuance of IFC Civil & Piping Package In Progress 3 20.Aug.20 A 3.Nov.20
6 A1100 Issuance of IFC EI Package Not Started 3 31.Oct.20 2.Nov.20
7 Procurements 43 28.Sep.20 A 29.Nov.20Procurements

8 Material Submittal for MA Review and Approval 0


9 Piping materials 0
10 Long lead Items 0
11 Pipes, Valves & Bolts 0
12 Piping Support Materials 12 28.Sep.20 A 8.Nov.20
13 Structural 0
14 Civil 12 28.Sep.20 A 8.Nov.20
15 A2350 Concrete procurements & Concumables In Progress 12 28.Sep.20 A 8.Nov.20
16 Maaden Free Issued Materials 0 31.Oct.20 Maaden Free Issued Materials
31.Oct.20
17 A2320 Arrival of XV,PV&PCV Not Started 0 31.Oct.20
18 EI Materials 32 29.Oct.20 A 29.Nov.20 EI Materials

19 A2520 Purchasing Instrumentation Cables In Progress 7 29.Oct.20 A 29.Nov.20


20 A2530 Puchasing cable conduits or/and trays In Progress 7 29.Oct.20 A 24.Nov.20
21 A2480 Arrival of Pressure transmitter & Gauges Not Started 0 11.Nov.20
Arrival of Pressure transmitter & Gauges
22 20 Workshop
2.Sep.20 A Fabrications Works
23.Nov.20
Workshop Fabrications Works
23 Pipe Spool Fabrication 19 2.Sep.20 APipe23.Nov.20
Spool Fabrication

24 Pipe Handling & Fit-Up 8 2.Sep.20 A 5.Nov.20


25 A1590 Line 10" - NAG - 4205 - 004 -0006 - CAB1 - NI In Progress 3 2.Sep.20 A 4.Nov.20
26 A1600 Line 12" - NAG - 4205 - 000 -0030 - AAB1 - NI In Progress 5 3.Sep.20 A 5.Nov.20
27 Welding 16 5.Sep.20 A 10.Nov.20
28 A1650 Line 10" - NAG - 4205 - 004 -0006 - CAB1 - NI In Progress 5 5.Sep.20 A 5.Nov.20
29 A1660 Line 12" - NAG - 4205 - 000 -0030 - AAB1 - NI In Progress 5 10.Sep.20 A 7.Nov.20
30 Quality Inspection & Testing 11 10.Sep.20 A 10.Nov.20
31 A2540 Line 10" - NAG - 4205 - 004 -0006 - CAB1 - NI In Progress 3 10.Sep.20 A 7.Nov.20
32 A2550 Line 12" - NAG - 4205 - 000 -0030 - AAB1 - NI In Progress 5 13.Sep.20 A 8.Nov.20
33 A2560 Line 8" - NAG - 4205 - 001 -0010 - AAB1 - NI In Progress 1 18.Sep.20 A 9.Nov.20
34 A2570 Line 8" - NAG - 4205 - 001 -0009 - AAB1 - NI In Progress 1 18.Sep.20 A 9.Nov.20
35 A2580 Line 12 " - NAG - 4205 - 001 -0031 - AAB1 - NI In Progress 2 19.Sep.20 A 10.Nov.20
36 A2590 Line 12 " - NAG - 4205 - 001 -0032 - AAB1 - NI In Progress 2 19.Sep.20 A 10.Nov.20
37 Pipe Spool Painting 14 8.Nov.20 23.Nov.20 Pipe Spool Painting

38 A1770 Line 10" - NAG - 4205 - 004 -0006 - CAB1 - NI Not Started 2 8.Nov.20 9.Nov.20
Line 10" - NAG - 4205 - 004 -0006 - CAB1 - NI
39 A1780 Line 12" - NAG - 4205 - 000 -0030 - AAB1 - NI Not Started 5 10.Nov.20 Line 15.Nov.20
12" - NAG - 4205 - 000 -0030 - AAB1 - NI
40 A1790 Line 8" - NAG - 4205 - 001 -0010 - AAB1 - NI Not Started 3 16.Nov.20 18.Nov.20 Line 8" - NAG - 4205 - 001 -0010 - AAB1 - NI

Remaining Level of Effort summary Prepared By: R. Buntog Page 1 of 3


Date Revision Checked Approved
Actual Level of Effort
31.Oct.20 REV.3
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Engineering, Procurement & Construction Work for Natural Gas bypass line on Lump sum Turn Key (LSTK)
P.O.#:.  6241907665
Proposed Remaining Activity Revised Baseline Schedule

# Activity ID Activity Name Activity Status Duration Start Finish Nov 01 Nov 08 Nov 15 Nov 22 Nov 29 Dec 06 Dec 13 Dec 20
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
41 A1800 Line 8" - NAG - 4205 - 001 -0009 - AAB1 - NI Not Started 3 16.Nov.20 18.Nov.20 Line 8" - NAG - 4205 - 001 -0009 - AAB1 - NI
42 A1810 Line 12 " - NAG - 4205 - 001 -0031 - AAB1 - NI Not Started 4 19.Nov.20 23.Nov.20 Line 12 " - NAG - 4205 - 001 -0031 - AAB1 - NI
43 A1820 Line 12 " - NAG - 4205 - 001 -0032 - AAB1 - NI Not Started 4 19.Nov.20 23.Nov.20 Line 12 " - NAG - 4205 - 001 -0032 - AAB1 - NI
44 Pipe Support Fabrication 20 21.Sep.20 A 16.Nov.20
45 Fit-up, Welding & Inspection 20 21.Sep.20 A 10.Nov.20
46 A1870 PS1 - PS4 In Progress 3 21.Sep.20 A 4.Nov.20
47 A1880 PS6 - P11 In Progress 4 21.Sep.20 A 5.Nov.20
48 A1890 PS12 - PS15 In Progress 10 21.Sep.20 A 9.Nov.20
49 A1900 PS5 In Progress 3 21.Sep.20 A 10.Nov.20
50 Pipe Support Painting 9 5.Nov.20 16.Nov.20 Pipe Support Painting

51 A1950 PS1 - PS4 Not Started 2 5.Nov.20 8.Nov.20 PS1 - PS4


52 A1960 PS6 - P11 Not Started 2 8.Nov.20 10.Nov.20 PS6 - P11
53 A1970 PS12 - PS15 Not Started 3 10.Nov.20 14.Nov.20 PS12 - PS15
54 A1980 PS5 Not Started 2 14.Nov.20 16.Nov.20 PS5
55 Pipe Support Foundation 0
56 Rebar Fabrications 0
57 38 15.Oct.20 A 15.Dec.20 Site Execution Works
Site Execution Works
58 Mobilization 0
59 Surveying 0
60 Equipment & Temp. Facilities 0
61 Piping Supports 25 15.Oct.20 A 30.Nov.20 Piping Supports

62 Civil Works 21 15.Oct.20 A 25.Nov.20 Civil Works

63 A1260 Polyethylne sheet & Installation of Rebars In Progress 4 15.Oct.20 A 4.Nov.20


64 A1270 Installation of Shuttering In Progress 4 15.Oct.20 A 8.Nov.20
65 A1280 Anchor Bolts Installation Not Started 2 2.Nov.20 4.Nov.20
Anchor Bolts Installation
66 A1290 Concreting + 7 days Curing Not Started 7 9.Nov.20 16.Nov.20 Concreting + 7 days Curing
67 A1300 Bitument coating for concrete exposed to earth Not Started 3 17.Nov.20 19.Nov.20 Bitument coating for concrete exposed to earth
68 A1310 Bacfilling and Compaction Not Started 5 21.Nov.20 25.Nov.20 Bacfilling and Compaction
69 Pipe Support Installations 12 17.Nov.20 30.Nov.20 Pipe Support Installations

70 A2240 PS1 - PS4 Not Started 3 17.Nov.20 19.Nov.20 PS1 - PS4


71 A2250 PS6 - P11 Not Started 3 21.Nov.20 23.Nov.20 PS6 - P11
72 A2260 PS12 - PS15 Not Started 6 24.Nov.20 30.Nov.20 PS12 - PS15
73 A2270 PS5 Not Started 4 26.Nov.20 30.Nov.20 PS5
74 Existing Pipe Support Modification 6 17.Nov.20 23.Nov.20 Existing Pipe Support Modification

75 A2450 Demoltion of Existing Pipe Supports Platforms Not Started 6 17.Nov.20 23.Nov.20 Demoltion of Existing Pipe Supports Platforms
76 A2460 Extension of Existing Pipe Support Platform Not Started 6 17.Nov.20 23.Nov.20 Extension of Existing Pipe Support Platform
77 NGL bypass Line Installation 28 10.Nov.20 12.Dec.20 NGL bypass Line Installation

78 Pipe Spool Delivery 13 10.Nov.20 24.Nov.20 Pipe Spool Delivery

79 A2620 Line 10" - NAG - 4205 - 004 -0006 - CAB1 - NI Not Started 1 10.Nov.20 Line 10.Nov.20
10" - NAG - 4205 - 004 -0006 - CAB1 - NI
80 A2630 Line 12" - NAG - 4205 - 000 -0030 - AAB1 - NI Not Started 2 16.Nov.20 17.Nov.20
Line 12" - NAG - 4205 - 000 -0030 - AAB1 - NI
81 A2640 Line 8" - NAG - 4205 - 001 -009&10 - AAB1 - NI & Line
Not Started
12" - NAG - 4205
1 - 000
24.Nov.20
-0031 & 32 - AAB1
24.Nov.20
- NI
Line 8" - NAG - 4205 - 001 -009&10 - AAB1 - NI & Line 12" - NAG - 4205 - 000 -0031 & 32 - AAB1 - NI
Remaining Level of Effort summary Prepared By: R. Buntog Page 2 of 3
Date Revision Checked Approved
Actual Level of Effort
31.Oct.20 REV.3
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Engineering, Procurement & Construction Work for Natural Gas bypass line on Lump sum Turn Key (LSTK)
P.O.#:.  6241907665
Proposed Remaining Activity Revised Baseline Schedule

# Activity ID Activity Name Activity Status Duration Start Finish Nov 01 Nov 08 Nov 15 Nov 22 Nov 29 Dec 06 Dec 13 Dec 20
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
82 Pipe spool Handling and Installation 15 21.Nov.20 7.Dec.20 Pipe spool Handling and Installation

83 A2080 Line 10" - NAG - 4205 - 004 -0006 - CAB1 - NI Not Started 3 21.Nov.20 23.Nov.20 Line 10" - NAG - 4205 - 004 -0006 - CAB1 - NI
84 A2090 Line 12" - NAG - 4205 - 000 -0030 - AAB1 - NI Not Started 4 24.Nov.20 28.Nov.20 Line 12" - NAG - 4205 - 000 -0030 - AAB1 - NI
85 A2100 Line 8" - NAG - 4205 - 001 -0010 - AAB1 - NI Not Started 3 29.Nov.20 1.Dec.20 Line 8" - NAG - 4205 - 001 -0010 - AAB1 - NI
86 A2110 Line 8" - NAG - 4205 - 001 -0009 - AAB1 - NI Not Started 4 29.Nov.20 2.Dec.20 Line 8" - NAG - 4205 - 001 -0009 - AAB1 - NI
87 A2120 Line 12 " - NAG - 4205 - 001 -0031 - AAB1 - NI Not Started 3 2.Dec.20 5.Dec.20 Line 12 " - NAG - 4205 - 001 -0031 - AAB1 - NI
88 A2130 Line 12 " - NAG - 4205 - 001 -0032 - AAB1 - NI Not Started 4 3.Dec.20 7.Dec.20 Line 12 " - NAG - 4205 - 001 -0032 - AAB1 - NI
89 Flange Bolt-ups 3 29.Nov.20 1.Dec.20 Flange Bolt-ups

90 A2140 Line 10" - NAG - 4205 - 004 -0006 - CAB1 - NI Not Started 3 29.Nov.20 1.Dec.20 Line 10" - NAG - 4205 - 004 -0006 - CAB1 - NI
91 A2150 Line 12" - NAG - 4205 - 000 -0030 - AAB1 - NI Not Started 3 29.Nov.20 1.Dec.20 Line 12" - NAG - 4205 - 000 -0030 - AAB1 - NI
92 Valve handling and Bolts-ups 12 24.Nov.20 7.Dec.20 Valve handling and Bolts-ups

93 A2200 Line 10" - NAG - 4205 - 004 -0006 - CAB1 - NI Not Started 3 24.Nov.20 26.Nov.20 Line 10" - NAG - 4205 - 004 -0006 - CAB1 - NI
94 A2210 Line 12" - NAG - 4205 - 000 -0030 - AAB1 - NI Not Started 2 29.Nov.20 30.Nov.20 Line 12" - NAG - 4205 - 000 -0030 - AAB1 - NI
95 A2220 Line 8" - NAG - 4205 - 001 -0010 - AAB1 - NI Not Started 5 2.Dec.20 7.Dec.20 Line 8" - NAG - 4205 - 001 -0010 - AAB1 - NI
96 A2230 Line 8" - NAG - 4205 - 001 -0009 - AAB1 - NI Not Started 3 3.Dec.20 6.Dec.20 Line 8" - NAG - 4205 - 001 -0009 - AAB1 - NI
97 Pipe Spool Site Quality Testing 4 8.Dec.20 12.Dec.20 Pipe Spool Site Quality Testing

98 A2650 Pneumatic testing Not Started 2 8.Dec.20 9.Dec.20 Pneumatic testing


99 A2660 Nitrogen Purging Not Started 2 10.Dec.20 12.Dec.20 Nitrogen Purging
100 Instrumentation 19 24.Nov.20 15.Dec.20 Instrumentation

101 Signals & Power Supply 11 24.Nov.20 6.Dec.20 Signals & Power Supply

102 A2030 Installation of Conduits Not Started 4 24.Nov.20 28.Nov.20 Installation of Conduits
103 A2040 Cable Pullings Not Started 4 29.Nov.20 2.Dec.20 Cable Pullings
104 A2050 Support for PLC and DCS configuration Not Started 3 3.Dec.20 6.Dec.20 Support for PLC and DCS configuration
105 Installations of Instruments 19 24.Nov.20 15.Dec.20 Installations of Instruments

106 A2060 Installation of XV valve, PV & PSV Not Started 3 24.Nov.20 26.Nov.20 Installation of XV valve, PV & PSV
107 A2070 Installation of PIT (Transmitter) & Gauges Not Started 5 28.Nov.20 2.Dec.20 Installation of PIT (Transmitter) & Gauges
108 A2160 Testing and Commissioning Not Started 3 13.Dec.20 15.Dec.20 Testing and Commissioning
109 8 16.Dec.20 24.Dec.20 Close Out
Close Out
110 Post Construction Activities 6 16.Dec.20 22.Dec.20 Post Construction Activities

111 A1460 Punch Point listing Not Started 2 16.Dec.20 17.Dec.20 Punch Point listing
112 A1470 Final acceptance Not Started 2 19.Dec.20 20.Dec.20 Final acceptance
113 A2300 Demobilization Not Started 2 21.Dec.20 22.Dec.20 Demobilization
114 Post Construction Documents 4 21.Dec.20 24.Dec.20 Post Construction Documents

115 A2280 Submission and approval of project dossier Not Started 2 21.Dec.20 22.Dec.20 Submission and approval of project dossier
116 A2290 Submission and approval of Red Mark-up/As-built drawings
Not Started 2 21.Dec.20 22.Dec.20 Submission and approval of Red Mark-up/As-built drawings
117 A2310 Signing Work Completion Certificate Not Started 2 23.Dec.20 24.Dec.20 Signing Work Completion Certificate

Remaining Level of Effort summary Prepared By: R. Buntog Page 3 of 3


Date Revision Checked Approved
Actual Level of Effort
31.Oct.20 REV.3
Actual Work
Remaining Work
Critical Remaining Work
Milestone