Professional Documents
Culture Documents
Actual Level of Effort Remaining Work Page 1 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
16-Aug-20, Starting up
Mobilization
Shop drawings
chiller's Submittal
Pump's Submittal
AHU's Submittal
BMS's Submittal
MCC's Submittal
sprinkler's Submittal
Actual Level of Effort Remaining Work Page 2 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
p room Approval
Supply lighting fixture by owner
21-Nov
09-Nov-20, HVAC
chiller's Supplying
Pump's Supplying
AHU's Supplying
BMS's Supplying
MCC's Supplying
27-Oct-20, F.F
sprinkler's Supplying
Actual Level of Effort Remaining Work Page 3 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
Activity ID Activity Name OriginalRemaining Schedule Start Finish Total 2020
Duration % Jun 06
Float Jun 13 Jun 20 Jun 27 Jul 04
Duration Complete T W T F S S M T W T F S S M T W T F S S M T W T F S SM
A3820
Zone Controller's Supplying 50d 50d 0% 05-Aug-20 03-Oct-20 61d
A3830
Fire Cabinet's Submittal 10d 10d 0% 17-Aug-20 29-Aug-20 46d
A3840
Fire Cabinet's Supplying 50d 50d 0% 30-Aug-20 27-Oct-20 46d
Plumbing 100d 100d 0% 19-Jul-20 21-Nov-20 45d
A3850
Water Pump's Submittal 10d 10d 0% 19-Jul-20 04-Aug-20 65d
A3860
Water Pump's Supplying 70d 70d 0% 05-Aug-20 27-Oct-20 65d
A3870
submersible pump's Submittal 10d 10d 0% 17-Aug-20 29-Aug-20 45d
A3880
submersible pump's Supplying 70d 70d 0% 30-Aug-20 21-Nov-20 45d
Third floor 115d 115d 0% 14-Jul-20 03-Dec-20 34d
Actual Level of Effort Remaining Work Page 4 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
12-Aug-20, By owner
Floor insulation 3rd floor
Actual Level of Effort Remaining Work Page 5 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
Zone Controller's Supplying
Actual Level of Effort Remaining Work Page 6 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
Activity ID Activity Name OriginalRemaining Schedule Start Finish Total 2020
Duration % Jun 06
Float Jun 13 Jun 20 Jun 27 Jul 04
Duration Complete T W T F S S M T W T F S S M T W T F S S M T W T F S SM
A1440
install refrigerant pipe 3rd floor 12d 12d 0% 25-Jul-20 11-Aug-20 129d
A1450
duct work 3rd floor 12d 12d 0% 25-Jul-20 11-Aug-20 129d
A1460
install Grill 3rd floor 7d 7d 0% 17-Oct-20 24-Oct-20 34d
Plumbing 36d 36d 0% 14-Jul-20 31-Aug-20 113d
A1470
supply water pipe 3rd floor 15d 15d 0% 14-Jul-20 05-Aug-20 73d
A2510
Test water pipe 3rd floor 3d 3d 0% 06-Aug-20 09-Aug-20 113d
A1490
drainage pipe 3rd floor 12d 12d 0% 13-Aug-20 27-Aug-20 113d
A1500
Test drainage pipe 3rd floor 3d 3d 0% 29-Aug-20 31-Aug-20 113d
Second floor 113d 113d 0% 22-Jul-20 09-Dec-20 29d
Actual Level of Effort Remaining Work Page 7 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
install refrigerant pipe 3rd floor
duct work 3rd floor
31-Aug-20, Plumbing
supply water pipe 3rd floor
Test water pipe 3rd floor
drainage pipe 3rd floor
Test drainage pipe 3rd floor
Actual Level of Effort Remaining Work Page 8 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
floor
Actual Level of Effort Remaining Work Page 9 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
Activity ID Activity Name OriginalRemaining Schedule Start Finish Total 2020
Duration % Jun 06
Float Jun 13 Jun 20 Jun 27 Jul 04
Duration Complete T W T F S S M T W T F S S M T W T F S S M T W T F S SM
A2760
install Grill 2nd floor 7d 7d 0% 25-Oct-20 02-Nov-20 34d
Plumbing 36d 36d 0% 22-Jul-20 08-Sep-20 106d
A2770
supply water pipe 2nd floor 15d 15d 0% 22-Jul-20 13-Aug-20 73d
A2810
Test water pipe 2nd floor 3d 3d 0% 15-Aug-20 17-Aug-20 106d
A2790
drainage pipe 2nd floor 12d 12d 0% 23-Aug-20 05-Sep-20 106d
A2800
Test drainage pipe 2nd floor 3d 3d 0% 06-Sep-20 08-Sep-20 106d
By owner 3d 3d 0% 18-Aug-20 22-Aug-20 106d
A2780 Floor insulation 2nd floor 3d 3d 0% 18-Aug-20 22-Aug-20 106d
First floor 111d 111d 0% 05-Aug-20 15-Dec-20 24d
Actual Level of Effort Remaining Work Page 10 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
08-Sep-20, Plumbing
supply water pipe 2nd floor
Test water pipe 2nd floor
drainage pipe 2nd floor
Test drainage pipe 2nd floor
22-Aug-20, By owner
Floor insulation 2nd floor
30-Aug-20, By owner
Floor insulation 1st floor
Pipe installation
Actual Level of Effort Remaining Work Page 11 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
install Grill 2nd floor
08-Sep-20, Plumbing
Actual Level of Effort Remaining Work Page 12 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
Activity ID Activity Name OriginalRemaining Schedule Start Finish Total 2020
Duration % Jun 06
Float Jun 13 Jun 20 Jun 27 Jul 04
Duration Complete T W T F S S M T W T F S S M T W T F S S M T W T F S SM
A3000
install refrigerant pipe 1st floor 14d 14d 0% 27-Aug-20 12-Sep-20 103d
A3010
duct work 1st floor 14d 14d 0% 27-Aug-20 12-Sep-20 103d
A3020
install Grill 1st floor 7d 7d 0% 03-Nov-20 10-Nov-20 34d
Plumbing 38d 38d 0% 05-Aug-20 19-Sep-20 97d
A3030
supply water pipe 1st floor 13d 13d 0% 05-Aug-20 19-Aug-20 73d
A3070
Test water pipe 1st floor 4d 4d 0% 22-Aug-20 25-Aug-20 97d
A3050
drainage pipe 1st floor 13d 13d 0% 31-Aug-20 14-Sep-20 97d
A3060
Test drainage pipe 1st floor 4d 4d 0% 15-Sep-20 19-Sep-20 97d
Ground floor 109d 109d 0% 13-Aug-20 21-Dec-20 19d
Actual Level of Effort Remaining Work Page 13 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
install refrigeran
duct work 1st flo
10-Sep-20, By owner
Floor insulation Gr floo
Actual Level of Effort Remaining Work Page 14 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
install refrigerant pipe 1st floor
duct work 1st floor
install Grill 1st floor
19-Sep-20, Plumbing
10-Sep-20, By owner
Floor insulation Gr floor
22-N
14-Nov-20, Fire Fighting
Pipe installation Gr floor
Zone installation Gr floor
install sprinkler Gr floor
Test Network Gr floor
install cabinet Gr floor
22-N
install CCD Gr floor
Actual Level of Effort Remaining Work Page 15 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
Activity ID Activity Name OriginalRemaining Schedule Start Finish Total 2020
Duration % Jun 06
Float Jun 13 Jun 20 Jun 27 Jul 04
Duration Complete T W T F S S M T W T F S S M T W T F S S M T W T F S SM
A3260
install refrigerant pipe Gr floor 13d 13d 0% 13-Sep-20 27-Sep-20 90d
A3270
duct work Gr floor 13d 13d 0% 13-Sep-20 27-Sep-20 90d
A3280
install Grill Gr floor 10d 10d 0% 11-Nov-20 22-Nov-20 34d
Plumbing 44d 44d 0% 13-Aug-20 04-Oct-20 84d
A3290
supply water pipe Gr floor 15d 15d 0% 13-Aug-20 31-Aug-20 73d
A3330
Test water pipe Gr floor 5d 5d 0% 01-Sep-20 06-Sep-20 84d
A3310
drainage pipe Gr floor 15d 15d 0% 12-Sep-20 28-Sep-20 84d
A3320
Test drainage pipe Gr floor 5d 5d 0% 29-Sep-20 04-Oct-20 84d
Basement floor 108d 108d 0% 23-Aug-20 28-Dec-20 13d
Actual Level of Effort Remaining Work Page 16 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Actual Level of Effort Remaining Work Page 17 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
install refrigerant pipe Gr floor
duct work Gr floor
insta
04-Oct-20, Plumbing
oor
t water pipe Gr floor
drainage pipe Gr floor
Test drainage pipe Gr floor
23-Sep-20, By owner
Floor insulation B floor
19-Nov-20, F
Pipe installation B floor
Zone installation B floor
install sprinkler B floor
Test Network B floor
install cabinet
Actual Level of Effort Remaining Work Page 18 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
Activity ID Activity Name OriginalRemaining Schedule Start Finish Total 2020
Duration % Jun 06
Float Jun 13 Jun 20 Jun 27 Jul 04
Duration Complete T W T F S S M T W T F S S M T W T F S S M T W T F S SM
A3520
install refrigerant pipe B floor 15d 15d 0% 28-Sep-20 15-Oct-20 75d
A3530
duct work B floor 15d 15d 0% 28-Sep-20 15-Oct-20 75d
A3540
install Grill B floor 10d 10d 0% 23-Nov-20 03-Dec-20 34d
Plumbing 48d 48d 0% 23-Aug-20 18-Oct-20 73d
A3550
supply water pipe B floor 17d 17d 0% 23-Aug-20 10-Sep-20 73d
A3590
Test water pipe B floor 6d 6d 0% 12-Sep-20 17-Sep-20 73d
A3570
drainage pipe B floor 15d 15d 0% 24-Sep-20 12-Oct-20 73d
A3580
Test drainage pipe B floor 5d 5d 0% 13-Oct-20 18-Oct-20 73d
Delivary 10d 10d 0% 29-Dec-20 10-Jan-21 3d
Actual Level of Effort Remaining Work Page 19 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Actual Level of Effort Remaining Work Page 20 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
install refrigerant pipe B floor
duct work B floor
18-Oct-20, Plumbing
supply water pipe B floor
Test water pipe B floor
drainage pipe B floor
Test drainage pipe B floor
Actual Level of Effort Remaining Work Page 21 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation