You are on page 1of 21

Date Revision Checked Approved

Star Care Hospital Project Classic Schedule Layout


Activity ID Activity Name OriginalRemaining Schedule Start Finish Total 2020
Duration % Jun 06
Float Jun 13 Jun 20 Jun 27 Jul 04
Duration Complete T W T F S S M T W T F S S M T W T F S S M T W T F S SM
Kattameya Medical
Star Care Hospital Project Centre (Seashel
172d Hospital)
172d 0% 13-Jun-20 10-Jan-21 3d

Starting up 50d 50d 0% 13-Jun-20 16-Aug-20 125d

A1000 Mobilization 20d 20d 0% 13-Jun-20* 06-Jul-20 13d Mobilization


A1510 Shop drawings 50d 50d 0% 13-Jun-20 16-Aug-20 125d
Material submittals And Supplying
116d 116d 0% 07-Jul-20 28-Nov-20 39d

Electrical 116d 116d 0% 07-Jul-20 28-Nov-20 39d


A3600 L.V panel's Submittal 13d 13d 0% 07-Jul-20 21-Jul-20 13d
A3650 L.C system's Submittal 13d 13d 0% 07-Jul-20 21-Jul-20 21d
A3620 L.V panel's Supplying 100d 100d 0% 22-Jul-20 24-Nov-20 16d
A3630 Earthing system's Submittal 10d 10d 0% 22-Jul-20 08-Aug-20 102d
A3660 L.C system's Supplying 100d 100d 0% 22-Jul-20 24-Nov-20 21d
A3670 Wiring device's Submittal 13d 13d 0% 22-Jul-20 11-Aug-20 13d
A3640 Earthing system's Supplying & Installing
30d 30d 0% 09-Aug-20 13-Sep-20 102d
A3680 Wiring device's Supplying 90d 90d 0% 12-Aug-20 28-Nov-20 13d
A3910 1st fix mock up room Approval 10d 10d 0% 24-Aug-20* 03-Sep-20 27d
A1300 Supply lighting fixture by owner 10d 10d 0% 28-Oct-20 09-Nov-20 34d
Mechanical 110d 110d 0% 07-Jul-20 21-Nov-20 45d
HVAC 100d 100d 0% 07-Jul-20 09-Nov-20 55d
A3690
chiller's Submittal 10d 10d 0% 07-Jul-20 18-Jul-20 45d
A3700
chiller's Supplying 80d 80d 0% 19-Jul-20 27-Oct-20 65d
A3710
Pump's Submittal 10d 10d 0% 19-Jul-20 04-Aug-20 45d
A3720
Pump's Supplying 50d 50d 0% 05-Aug-20 03-Oct-20 85d
A3730
AHU's Submittal 10d 10d 0% 05-Aug-20 16-Aug-20 55d
A3770
BMS's Submittal 10d 10d 0% 05-Aug-20 16-Aug-20 45d
A3740
AHU's Supplying 70d 70d 0% 17-Aug-20 09-Nov-20 55d
A3750
MCC's Submittal 10d 10d 0% 17-Aug-20 29-Aug-20 65d
A3780
BMS's Supplying 45d 45d 0% 17-Aug-20 10-Oct-20 80d
A3760
MCC's Supplying 50d 50d 0% 30-Aug-20 27-Oct-20 65d
F.F 90d 90d 0% 07-Jul-20 27-Oct-20 46d
A3790
sprinkler's Submittal 10d 10d 0% 07-Jul-20 18-Jul-20 61d
A3800
sprinkler's Supplying 60d 60d 0% 19-Jul-20 03-Oct-20 61d
A3810
Zone Controller's Submittal 10d 10d 0% 19-Jul-20 04-Aug-20 61d

Actual Level of Effort Remaining Work Page 1 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

16-Aug-20, Starting up

Mobilization
Shop drawings

L.V panel's Submittal


L.C system's Submittal

Earthing system's Submittal

Wiring device's Submittal


Earthing sys

1st fix mock up room Approval

chiller's Submittal

Pump's Submittal

AHU's Submittal
BMS's Submittal

MCC's Submittal

sprinkler's Submittal

Zone Controller's Submittal

Actual Level of Effort Remaining Work Page 2 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW

Earthing system's Supplying & Installing

p room Approval
Supply lighting fixture by owner
21-Nov
09-Nov-20, HVAC

chiller's Supplying

Pump's Supplying

AHU's Supplying

BMS's Supplying
MCC's Supplying
27-Oct-20, F.F

sprinkler's Supplying

Actual Level of Effort Remaining Work Page 3 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
Activity ID Activity Name OriginalRemaining Schedule Start Finish Total 2020
Duration % Jun 06
Float Jun 13 Jun 20 Jun 27 Jul 04
Duration Complete T W T F S S M T W T F S S M T W T F S S M T W T F S SM
A3820
Zone Controller's Supplying 50d 50d 0% 05-Aug-20 03-Oct-20 61d
A3830
Fire Cabinet's Submittal 10d 10d 0% 17-Aug-20 29-Aug-20 46d
A3840
Fire Cabinet's Supplying 50d 50d 0% 30-Aug-20 27-Oct-20 46d
Plumbing 100d 100d 0% 19-Jul-20 21-Nov-20 45d
A3850
Water Pump's Submittal 10d 10d 0% 19-Jul-20 04-Aug-20 65d
A3860
Water Pump's Supplying 70d 70d 0% 05-Aug-20 27-Oct-20 65d
A3870
submersible pump's Submittal 10d 10d 0% 17-Aug-20 29-Aug-20 45d
A3880
submersible pump's Supplying 70d 70d 0% 30-Aug-20 21-Nov-20 45d
Third floor 115d 115d 0% 14-Jul-20 03-Dec-20 34d

Electrical Work 76d 76d 0% 05-Sep-20 03-Dec-20 34d


A1260 1st Fix steel conduit 3rd floor 25d 25d 0% 05-Sep-20* 03-Oct-20 27d
A1270 cable tray for corridor 3rd floor 10d 10d 0% 16-Sep-20 27-Sep-20 90d
A1280 Pulling cables 3rd floor 10d 10d 0% 04-Oct-20 15-Oct-20 75d
A1310 install lighting fixture 3rd floor 5d 5d 0% 10-Nov-20 15-Nov-20 50d
A1290 installation panel 3rd floor 5d 5d 0% 25-Nov-20 30-Nov-20 16d
A1330 Fire alarm devices 3rd floor 4d 4d 0% 25-Nov-20 29-Nov-20 21d
A1340 Nurse call devices 3rd floor 4d 4d 0% 25-Nov-20 29-Nov-20 38d
A1350 Data devices 3rd floor 4d 4d 0% 25-Nov-20 29-Nov-20 38d
A1360 CCTV devices 3rd floor 4d 4d 0% 25-Nov-20 29-Nov-20 38d
A1370 Sound devices 3rd floor 4d 4d 0% 25-Nov-20 29-Nov-20 38d
A1320 wiring devices 3rd floor 5d 5d 0% 29-Nov-20 03-Dec-20 13d
By owner 3d 3d 0% 10-Aug-20 12-Aug-20 113d
A1480 Floor insulation 3rd floor 3d 3d 0% 10-Aug-20 12-Aug-20 113d
Mechanical work 87d 87d 0% 14-Jul-20 01-Nov-20 62d
Fire Fighting 87d 87d 0% 14-Jul-20 01-Nov-20 62d
A1380
Pipe installation 3rd floor 20d 20d 0% 14-Jul-20 11-Aug-20 75d
A1390
Zone installation 3rd floor 3d 3d 0% 04-Oct-20 07-Oct-20 61d
A1420
install sprinkler 3rd floor 4d 4d 0% 04-Oct-20 08-Oct-20 61d
A1400
Test Network 3rd floor 3d 3d 0% 08-Oct-20 11-Oct-20 79d
A1410
install cabinet 3rd floor 3d 3d 0% 28-Oct-20 01-Nov-20 46d
HVAC 81d 81d 0% 14-Jul-20 24-Oct-20 68d
A1430
install CCD 3rd floor 20d 20d 0% 14-Jul-20 11-Aug-20 34d

Actual Level of Effort Remaining Work Page 4 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Fire Cabinet's Submittal

Water Pump's Submittal

submersible pump's Submittal

12-Aug-20, By owner
Floor insulation 3rd floor

Pipe installation 3rd floor

install CCD 3rd floor

Actual Level of Effort Remaining Work Page 5 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
Zone Controller's Supplying

Fire Cabinet's Supplying


21-Nov

Water Pump's Supplying


l
subme

1st Fix steel conduit 3rd floor


cable tray for corridor 3rd floor
Pulling cables 3rd floor
install lighting fixture 3rd flo

01-Nov-20, Mechanical work


01-Nov-20, Fire Fighting

Zone installation 3rd floor


install sprinkler 3rd floor
Test Network 3rd floor
install cabinet 3rd floor
24-Oct-20, HVAC

Actual Level of Effort Remaining Work Page 6 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
Activity ID Activity Name OriginalRemaining Schedule Start Finish Total 2020
Duration % Jun 06
Float Jun 13 Jun 20 Jun 27 Jul 04
Duration Complete T W T F S S M T W T F S S M T W T F S S M T W T F S SM
A1440
install refrigerant pipe 3rd floor 12d 12d 0% 25-Jul-20 11-Aug-20 129d
A1450
duct work 3rd floor 12d 12d 0% 25-Jul-20 11-Aug-20 129d
A1460
install Grill 3rd floor 7d 7d 0% 17-Oct-20 24-Oct-20 34d
Plumbing 36d 36d 0% 14-Jul-20 31-Aug-20 113d
A1470
supply water pipe 3rd floor 15d 15d 0% 14-Jul-20 05-Aug-20 73d
A2510
Test water pipe 3rd floor 3d 3d 0% 06-Aug-20 09-Aug-20 113d
A1490
drainage pipe 3rd floor 12d 12d 0% 13-Aug-20 27-Aug-20 113d
A1500
Test drainage pipe 3rd floor 3d 3d 0% 29-Aug-20 31-Aug-20 113d
Second floor 113d 113d 0% 22-Jul-20 09-Dec-20 29d

Electrical Work 68d 68d 0% 20-Sep-20 09-Dec-20 29d


A2560 1st Fix steel conduit 2nd floor 20d 20d 0% 20-Sep-20* 13-Oct-20 27d
A2570 cable tray for corridor 2nd floor 6d 6d 0% 01-Oct-20 08-Oct-20 81d
A2580 Pulling cable 2nd floor 6d 6d 0% 14-Oct-20 20-Oct-20 71d
A2610 install lighting fixture 2nd floor 5d 5d 0% 10-Nov-20 15-Nov-20 34d
A2630 Fire alarm devices 2nd floor 4d 4d 0% 30-Nov-20 03-Dec-20 21d
A2640 Nurse call devices 2nd floor 4d 4d 0% 30-Nov-20 03-Dec-20 34d
A2650 Data devices 2nd floor 4d 4d 0% 30-Nov-20 03-Dec-20 34d
A2660 CCTV devices 2nd floor 4d 4d 0% 30-Nov-20 03-Dec-20 34d
A2670 Sound devices 2nd floor 4d 4d 0% 30-Nov-20 03-Dec-20 34d
A2590 installation panel 2nd floor 5d 5d 0% 01-Dec-20 06-Dec-20 16d
A2620 wiring devices 2nd floor 5d 5d 0% 05-Dec-20 09-Dec-20 13d
Mechanical work 83d 83d 0% 22-Jul-20 04-Nov-20 59d
Fire Fighting 77d 77d 0% 04-Aug-20 04-Nov-20 59d
A2680
Pipe installation 2nd floor 17d 17d 0% 04-Aug-20 24-Aug-20 75d
A2690
Zone installation 2nd floor 3d 3d 0% 08-Oct-20 11-Oct-20 61d
A2720
install sprinkler 2nd floor 4d 4d 0% 10-Oct-20 13-Oct-20 61d
A2700
Test Network 2nd floor 3d 3d 0% 12-Oct-20 14-Oct-20 76d
A2710
install cabinet 2nd floor 3d 3d 0% 02-Nov-20 04-Nov-20 46d
HVAC 75d 75d 0% 04-Aug-20 02-Nov-20 61d
A2730
install CCD 2nd floor 17d 17d 0% 04-Aug-20 24-Aug-20 34d
A2740
install refrigerant pipe 2nd floor 12d 12d 0% 10-Aug-20 24-Aug-20 119d
A2750
duct work 2nd floor 12d 12d 0% 10-Aug-20 24-Aug-20 119d

Actual Level of Effort Remaining Work Page 7 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
install refrigerant pipe 3rd floor
duct work 3rd floor

31-Aug-20, Plumbing
supply water pipe 3rd floor
Test water pipe 3rd floor
drainage pipe 3rd floor
Test drainage pipe 3rd floor

Pipe installation 2nd floor

install CCD 2nd floor


install refrigerant pipe 2nd floor
duct work 2nd floor

Actual Level of Effort Remaining Work Page 8 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW

install Grill 3rd floor

floor

1st Fix steel conduit 2nd floor


cable tray for corridor 2nd floor
Pulling cable 2nd floor
install lighting fixture 2nd fl

04-Nov-20, Mechanical work


04-Nov-20, Fire Fighting

Zone installation 2nd floor


install sprinkler 2nd floor
Test Network 2nd floor
install cabinet 2nd floor
02-Nov-20, HVAC

Actual Level of Effort Remaining Work Page 9 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
Activity ID Activity Name OriginalRemaining Schedule Start Finish Total 2020
Duration % Jun 06
Float Jun 13 Jun 20 Jun 27 Jul 04
Duration Complete T W T F S S M T W T F S S M T W T F S S M T W T F S SM
A2760
install Grill 2nd floor 7d 7d 0% 25-Oct-20 02-Nov-20 34d
Plumbing 36d 36d 0% 22-Jul-20 08-Sep-20 106d
A2770
supply water pipe 2nd floor 15d 15d 0% 22-Jul-20 13-Aug-20 73d
A2810
Test water pipe 2nd floor 3d 3d 0% 15-Aug-20 17-Aug-20 106d
A2790
drainage pipe 2nd floor 12d 12d 0% 23-Aug-20 05-Sep-20 106d
A2800
Test drainage pipe 2nd floor 3d 3d 0% 06-Sep-20 08-Sep-20 106d
By owner 3d 3d 0% 18-Aug-20 22-Aug-20 106d
A2780 Floor insulation 2nd floor 3d 3d 0% 18-Aug-20 22-Aug-20 106d
First floor 111d 111d 0% 05-Aug-20 15-Dec-20 24d

Electrical Work 60d 60d 0% 05-Oct-20 15-Dec-20 24d


A2820 1st Fix steel conduit 1st floor 17d 17d 0% 05-Oct-20* 25-Oct-20 27d
A2830 cable tray for corridor 1st floor 7d 7d 0% 18-Oct-20 25-Oct-20 67d
A2840 Pulling cable 1st floor 7d 7d 0% 26-Oct-20 03-Nov-20 60d
A2870 install lighting fixture 1st floor 5d 5d 0% 16-Nov-20 21-Nov-20 34d
A2890 Fire alarm devices 1st floor 4d 4d 0% 05-Dec-20 08-Dec-20 21d
A2900 Nurse call devices 1st floor 4d 4d 0% 05-Dec-20 08-Dec-20 30d
A2910 Data devices 1st floor 4d 4d 0% 05-Dec-20 08-Dec-20 30d
A2920 CCTV devices 1st floor 4d 4d 0% 05-Dec-20 08-Dec-20 30d
A2930 Sound devices 1st floor 4d 4d 0% 05-Dec-20 08-Dec-20 30d
A2850 installation panel 1st floor 5d 5d 0% 07-Dec-20 12-Dec-20 16d
A2880 wiring devices 1st floor 5d 5d 0% 10-Dec-20 15-Dec-20 13d
By owner 4d 4d 0% 26-Aug-20 30-Aug-20 97d
A3040 Floor insulation 1st floor 4d 4d 0% 26-Aug-20 30-Aug-20 97d
Mechanical work 81d 81d 0% 05-Aug-20 10-Nov-20 54d
Fire Fighting 68d 68d 0% 19-Aug-20 09-Nov-20 55d
A2940
Pipe installation 1st floor 20d 20d 0% 19-Aug-20 12-Sep-20 75d
A2950
Zone installation 1st floor 4d 4d 0% 12-Oct-20 15-Oct-20 61d
A2980
install sprinkler 1st floor 5d 5d 0% 14-Oct-20 19-Oct-20 61d
A2960
Test Network 1st floor 4d 4d 0% 17-Oct-20 20-Oct-20 71d
A2970
install cabinet 1st floor 4d 4d 0% 05-Nov-20 09-Nov-20 46d
HVAC 69d 69d 0% 19-Aug-20 10-Nov-20 54d
A2990
install CCD 1st floor 20d 20d 0% 19-Aug-20 12-Sep-20 34d

Actual Level of Effort Remaining Work Page 10 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

08-Sep-20, Plumbing
supply water pipe 2nd floor
Test water pipe 2nd floor
drainage pipe 2nd floor
Test drainage pipe 2nd floor
22-Aug-20, By owner
Floor insulation 2nd floor

30-Aug-20, By owner
Floor insulation 1st floor

Pipe installation

install CCD 1st

Actual Level of Effort Remaining Work Page 11 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
install Grill 2nd floor
08-Sep-20, Plumbing

ge pipe 2nd floor


Test drainage pipe 2nd floor

1st Fix steel conduit 1st floor


cable tray for corridor 1st floor
Pulling cable 1st floor
install li

10-Nov-20, Mechanical work


09-Nov-20, Fire Fighting
Pipe installation 1st floor
Zone installation 1st floor
install sprinkler 1st floor
Test Network 1st floor
install cabinet 1st floor
10-Nov-20, HVAC
install CCD 1st floor

Actual Level of Effort Remaining Work Page 12 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
Activity ID Activity Name OriginalRemaining Schedule Start Finish Total 2020
Duration % Jun 06
Float Jun 13 Jun 20 Jun 27 Jul 04
Duration Complete T W T F S S M T W T F S S M T W T F S S M T W T F S SM
A3000
install refrigerant pipe 1st floor 14d 14d 0% 27-Aug-20 12-Sep-20 103d
A3010
duct work 1st floor 14d 14d 0% 27-Aug-20 12-Sep-20 103d
A3020
install Grill 1st floor 7d 7d 0% 03-Nov-20 10-Nov-20 34d
Plumbing 38d 38d 0% 05-Aug-20 19-Sep-20 97d
A3030
supply water pipe 1st floor 13d 13d 0% 05-Aug-20 19-Aug-20 73d
A3070
Test water pipe 1st floor 4d 4d 0% 22-Aug-20 25-Aug-20 97d
A3050
drainage pipe 1st floor 13d 13d 0% 31-Aug-20 14-Sep-20 97d
A3060
Test drainage pipe 1st floor 4d 4d 0% 15-Sep-20 19-Sep-20 97d
Ground floor 109d 109d 0% 13-Aug-20 21-Dec-20 19d

Electrical Work 52d 52d 0% 21-Oct-20 21-Dec-20 19d


A3080 1st Fix steel conduit Gr floor 22d 22d 0% 21-Oct-20* 16-Nov-20 27d
A3090 cable tray for corridor Gr floor 7d 7d 0% 03-Nov-20 10-Nov-20 54d
A3100 Pulling cable Gr floor 6d 6d 0% 17-Nov-20 23-Nov-20 43d
A3130 install lighting fixture Gr floor 5d 5d 0% 22-Nov-20 26-Nov-20 34d
A3150 Fire alarm devices Gr floor 4d 4d 0% 09-Dec-20 13-Dec-20 21d
A3160 Nurse call devices Gr floor 4d 4d 0% 09-Dec-20 13-Dec-20 26d
A3170 Data devices Gr floor 4d 4d 0% 09-Dec-20 13-Dec-20 26d
A3180 CCTV devices Gr floor 4d 4d 0% 09-Dec-20 13-Dec-20 26d
A3190 Sound devices Gr floor 4d 4d 0% 09-Dec-20 13-Dec-20 26d
A3110 installation panel Gr floor 5d 5d 0% 13-Dec-20 17-Dec-20 16d
A3140 wiring devices Gr floor 5d 5d 0% 16-Dec-20 21-Dec-20 13d
By owner 4d 4d 0% 07-Sep-20 10-Sep-20 84d
A3300 Floor insulation Gr floor 4d 4d 0% 07-Sep-20 10-Sep-20 84d
Mechanical work 84d 84d 0% 13-Aug-20 22-Nov-20 44d
Fire Fighting 59d 59d 0% 05-Sep-20 14-Nov-20 51d
A3200
Pipe installation Gr floor 20d 20d 0% 05-Sep-20 27-Sep-20 75d
A3210
Zone installation Gr floor 4d 4d 0% 17-Oct-20 20-Oct-20 61d
A3240
install sprinkler Gr floor 5d 5d 0% 20-Oct-20 25-Oct-20 61d
A3220
Test Network Gr floor 4d 4d 0% 21-Oct-20 25-Oct-20 67d
A3230
install cabinet Gr floor 4d 4d 0% 10-Nov-20 14-Nov-20 46d
HVAC 66d 66d 0% 05-Sep-20 22-Nov-20 44d
A3250
install CCD Gr floor 20d 20d 0% 05-Sep-20 27-Sep-20 34d

Actual Level of Effort Remaining Work Page 13 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
install refrigeran
duct work 1st flo

supply water pipe 1st floor


Test water pipe 1st floor
drainage

10-Sep-20, By owner
Floor insulation Gr floo

Actual Level of Effort Remaining Work Page 14 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
install refrigerant pipe 1st floor
duct work 1st floor
install Grill 1st floor
19-Sep-20, Plumbing

drainage pipe 1st floor


Test drainage pipe 1st floor

1st Fix steel conduit Gr


cable tray for corridor Gr floor
P

10-Sep-20, By owner
Floor insulation Gr floor
22-N
14-Nov-20, Fire Fighting
Pipe installation Gr floor
Zone installation Gr floor
install sprinkler Gr floor
Test Network Gr floor
install cabinet Gr floor
22-N
install CCD Gr floor

Actual Level of Effort Remaining Work Page 15 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
Activity ID Activity Name OriginalRemaining Schedule Start Finish Total 2020
Duration % Jun 06
Float Jun 13 Jun 20 Jun 27 Jul 04
Duration Complete T W T F S S M T W T F S S M T W T F S S M T W T F S SM
A3260
install refrigerant pipe Gr floor 13d 13d 0% 13-Sep-20 27-Sep-20 90d
A3270
duct work Gr floor 13d 13d 0% 13-Sep-20 27-Sep-20 90d
A3280
install Grill Gr floor 10d 10d 0% 11-Nov-20 22-Nov-20 34d
Plumbing 44d 44d 0% 13-Aug-20 04-Oct-20 84d
A3290
supply water pipe Gr floor 15d 15d 0% 13-Aug-20 31-Aug-20 73d
A3330
Test water pipe Gr floor 5d 5d 0% 01-Sep-20 06-Sep-20 84d
A3310
drainage pipe Gr floor 15d 15d 0% 12-Sep-20 28-Sep-20 84d
A3320
Test drainage pipe Gr floor 5d 5d 0% 29-Sep-20 04-Oct-20 84d
Basement floor 108d 108d 0% 23-Aug-20 28-Dec-20 13d

Electrical Work 45d 45d 0% 07-Nov-20 28-Dec-20 13d


A3340 1st Fix steel conduit B floor 25d 25d 0% 07-Nov-20* 05-Dec-20 27d
A3350 cable tray for corridor B floor 7d 7d 0% 18-Nov-20 25-Nov-20 41d
A3390 install lighting fixture B floor 6d 6d 0% 28-Nov-20 03-Dec-20 34d
A3360 Pulling cables B floor 6d 6d 0% 06-Dec-20 12-Dec-20 27d
A3410 Fire alarm devices B floor 5d 5d 0% 14-Dec-20 19-Dec-20 21d
A3420 Nurse call devices B floor 5d 5d 0% 14-Dec-20 19-Dec-20 21d
A3430 Data devices B floor 5d 5d 0% 14-Dec-20 19-Dec-20 21d
A3440 CCTV devices B floor 5d 5d 0% 14-Dec-20 19-Dec-20 21d
A3450 Sound devices B floor 5d 5d 0% 14-Dec-20 19-Dec-20 21d
A3370 installation panel B floor 6d 6d 0% 19-Dec-20 24-Dec-20 16d
A3400 wiring devices B floor 6d 6d 0% 22-Dec-20 28-Dec-20 13d
By owner 5d 5d 0% 19-Sep-20 23-Sep-20 73d
A3560 Floor insulation B floor 5d 5d 0% 19-Sep-20 23-Sep-20 73d
Mechanical work 87d 87d 0% 23-Aug-20 03-Dec-20 34d
Fire Fighting 51d 51d 0% 20-Sep-20 19-Nov-20 46d
A3460
Pipe installation B floor 22d 22d 0% 20-Sep-20 15-Oct-20 75d
A3470
Zone installation B floor 5d 5d 0% 21-Oct-20 26-Oct-20 61d
A3500
install sprinkler B floor 6d 6d 0% 26-Oct-20 02-Nov-20 61d
A3480
Test Network B floor 5d 5d 0% 27-Oct-20 02-Nov-20 61d
A3490
install cabinet B floor 5d 5d 0% 15-Nov-20 19-Nov-20 46d
HVAC 63d 63d 0% 20-Sep-20 03-Dec-20 34d
A3510
install CCD B floor 22d 22d 0% 20-Sep-20 15-Oct-20 34d

Actual Level of Effort Remaining Work Page 16 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

supply water pipe Gr floor


Test water pipe Gr floor

Actual Level of Effort Remaining Work Page 17 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
install refrigerant pipe Gr floor
duct work Gr floor
insta
04-Oct-20, Plumbing
oor
t water pipe Gr floor
drainage pipe Gr floor
Test drainage pipe Gr floor

23-Sep-20, By owner
Floor insulation B floor

19-Nov-20, F
Pipe installation B floor
Zone installation B floor
install sprinkler B floor
Test Network B floor
install cabinet

install CCD B floor

Actual Level of Effort Remaining Work Page 18 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
Activity ID Activity Name OriginalRemaining Schedule Start Finish Total 2020
Duration % Jun 06
Float Jun 13 Jun 20 Jun 27 Jul 04
Duration Complete T W T F S S M T W T F S S M T W T F S S M T W T F S SM
A3520
install refrigerant pipe B floor 15d 15d 0% 28-Sep-20 15-Oct-20 75d
A3530
duct work B floor 15d 15d 0% 28-Sep-20 15-Oct-20 75d
A3540
install Grill B floor 10d 10d 0% 23-Nov-20 03-Dec-20 34d
Plumbing 48d 48d 0% 23-Aug-20 18-Oct-20 73d
A3550
supply water pipe B floor 17d 17d 0% 23-Aug-20 10-Sep-20 73d
A3590
Test water pipe B floor 6d 6d 0% 12-Sep-20 17-Sep-20 73d
A3570
drainage pipe B floor 15d 15d 0% 24-Sep-20 12-Oct-20 73d
A3580
Test drainage pipe B floor 5d 5d 0% 13-Oct-20 18-Oct-20 73d
Delivary 10d 10d 0% 29-Dec-20 10-Jan-21 3d

A3890 initial Delivary 10d 10d 0% 29-Dec-20* 10-Jan-21 3d

Actual Level of Effort Remaining Work Page 19 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

supply water pipe B flo

Actual Level of Effort Remaining Work Page 20 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation
Date Revision Checked Approved
Star Care Hospital Project Classic Schedule Layout
2020
05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
install refrigerant pipe B floor
duct work B floor

18-Oct-20, Plumbing
supply water pipe B floor
Test water pipe B floor
drainage pipe B floor
Test drainage pipe B floor

Actual Level of Effort Remaining Work Page 21 of 21 TASK filter: All Activities
Actual Work Critical Remaining W... © Oracle Corporation