SHADEGAN STEEL COMPLEX

TIME SCHEDULE
Activity ID Activity Name Original Activity % Start Finish
Duration Complete 2020
un Jul Aug Sep Oct
SHADEGAN 93 27-Jun-20 27-Sep-20

1400-1 START OF PROJECT 0 0% 27-Jun-20

1400-2 FINISH OF PROJECT 0 0% 27-Sep-20

PROCESS 75 27-Jun-20 09-Sep-20


1400FDSPR54020001 Process Data Sheet for Desulfurization Unit Vessel DSV-02 15 0% 27-Jul-20 10-Aug-20

1400FDWPR54020001 Process Flow Diagram for Desulfurization Unit No. 2 15 0% 27-Jun-20 11-Jul-20

1400FDWPR54020002 Piping & Instrumentation Diagram for Desulfurization Unit No. 2 15 0% 27-Jun-20 11-Jul-20

1400FMLPR54020001 Instructions for Commissioning of Desulfurization Unit No. 2 15 0% 26-Aug-20 09-Sep-20

1400FMLPR54020002 Opperation Manual for Desulfurization Unit No. 2 15 0% 11-Aug-20 25-Aug-20

1400FTSPR54020001 Specifications for ZnO Catalyst and Ceramic Balls for Desulfurization Unit 15 0% 12-Jul-20 26-Jul-20
No. 2
CIVIL & STRUCTURE
STRUCTUR 70 12-Jul-20 19-Sep-20

DRAWING 70 12-Jul-20 19-Sep-20


1400FDWCI54020001 Foundation Plan at Ground level for Desulfurization Unit No. 2 10 0% 12-Jul-20 21-Jul-20

1400FDWCI54020002 Foundation & Piles Layout for Desulfurization Unit No. 2 10 0% 22-Jul-20 31-Jul-20

1400FDWCI54020003 Foundation Plan & Sections for Desulfurization Unit No. 2 10 0% 01-Aug-20 10-Aug-20

1400FDWCI54020004 Reinforcement Plan & Sections for Desulfurization Unit No. 2 10 0% 11-Aug-20 20-Aug-20

1400FDWCI54020005 Pile Details for Desulfurization Unit No. 2 10 0% 21-Aug-20 30-Aug-20

1400FDWSS54020001 General Arrangement for Structure of Desulfurization Unit No. 2 10 0% 31-Aug-20 09-Sep-20

1400FDWSS54020002 Marking Plans of Beams at +16:40M Level for Desulfurization Unit No. 2 10 0% 10-Sep-20 19-Sep-20

1400FDWSS54020003 Marking Plans of Beams at +11:40M Level for Desulfurization Unit No. 2 10 0% 10-Sep-20 19-Sep-20

1400FDWSS54020004 Marking Plans of Beams at +5:20M Level for Desulfurization Unit No. 2 10 0% 10-Sep-20 19-Sep-20

1400FDWSS54020005 Marking Plans of CHQ. Plates & Hand Railes at +5:20M Level for 10 0% 10-Sep-20 19-Sep-20
Desulfurization Unit No. 2
1400FDWSS54020006 Marking Plans of CHQ. Plates & Hand Railes at +11:40M Level for 10 0% 10-Sep-20 19-Sep-20
Desulfurization Unit No. 2
CALCULATION 40 11-Aug-20 19-Sep-20
1400FCBCI54020001 Foundation Calculation Book for Desulfurization Unit No. 2 10 0% 11-Aug-20 20-Aug-20

1400FCBSS54020001 Structure Calculation Book for Desulfurization Unit No. 2 10 0% 10-Sep-20 19-Sep-20

MECHANICAL 5 12-Jul-20 16-Jul-20


1400FDWSE54020001 General Arrangement Drawing for Desulfurization Unit Vessel. DSV-02 5 0% 12-Jul-20 16-Jul-20

Actual Work Critical Remaining Work Page 1 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
SHADEGAN STEEL COMPLEX
TIME SCHEDULE
Activity ID Activity Name Original Activity % Start Finish
Duration Complete 2020
un Jul Aug Sep Oct
INSTRUMENT & ELECTRICAL
EL 22 12-Jul-20 02-Aug-20
1400FDSIN54020001 PSV Data Sheet for Desulfurization Unit No. 2 12 0% 12-Jul-20 23-Jul-20

1400FDSIN54020002 Differential Pressure Indicator Data Sheet for Desulfurization Unit No. 2 12 0% 17-Jul-20 28-Jul-20

1400FDSIN54020003 Pressure Indicator Data Sheet for Desulfurization Unit No. 2 12 0% 22-Jul-20 02-Aug-20

1400FDSIN54020004 Temperature Indicator Data Sheet for Desulfurization Unit No. 2 12 0% 22-Jul-20 02-Aug-20

1400FDSIN54020005 Analyzer Data Sheet for Desulfurization Unit No. 2 12 0% 22-Jul-20 02-Aug-20

PIPING & DUCTING 78 12-Jul-20 27-Sep-20

CALCULATION & DATA SHEET 48 11-Aug-20 27-Sep-20


1400FDSPI54020001 Expansion Joints Data Sheet for Desulfurization Unit No. 2 18 0% 10-Sep-20 27-Sep-20

1400FMTPI54020001 Material Take Off for Piping of Desulfurization Unit No. 2 15 0% 11-Aug-20 25-Aug-20

1400FMTPI54020002 Material Take off for Valve of Desulfurization Unit No. 2 15 0% 11-Aug-20 25-Aug-20

1400FRPPI54020001 Stress Analysis for Desulfurization Unit No. 2 (if Required) 15 0% 26-Aug-20 09-Sep-20

1400FSOMO54020001 PDMS (3D Modeling) for Desulfurization Unit No. 2 15 0% 11-Aug-20 25-Aug-20

DRAWING 75 12-Jul-20 24-Sep-20


1400FDWPI54020001 General Layout for Desulfurization Unit No. 2 15 0% 12-Jul-20 26-Jul-20

1400FDWPI54020002 General Arrangement Drawing for the Piping of Desulfurization Unit No. 2 15 0% 27-Jul-20 10-Aug-20

1400FDWPI54020003 Support Details for Desulfurization Unit No. 2 15 0% 10-Sep-20 24-Sep-20

1400FISPI54020001 Isometric Drawings for Desulfurization Unit No. 2 15 0% 27-Jul-20 10-Aug-20

1400FLSPI54020001 Tie-in Schedule for Inlet/Outlet Lines for Desulfurization Unit No. 2 13 0% 10-Sep-20 22-Sep-20

PROCUREMENT SERVICES
S 53 03-Aug-20 24-Sep-20

1400FMTIN54020001 Inquiry for Instrument Items of Desulfurization Unit No. 2 15 0% 03-Aug-20 17-Aug-20

1400FMTPI54020001-1 Inquiry for Piping Items of Desulfurization Unit No. 2 15 0% 26-Aug-20 09-Sep-20

1400FMTPI54020002-1 Inquiry for Valves of Desulfurization Unit No. 2 15 0% 26-Aug-20 09-Sep-20

1400FMTPR54020001 Inquiry for Catalyst And Ceramic Balls of Desulfurization Unit N0.2 15 0% 10-Sep-20 24-Sep-20

1400FMTSE54020001 Inquiry for Vessel of Desulfurization Unit No. 2 15 0% 10-Sep-20 24-Sep-20

Actual Work Critical Remaining Work Page 2 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation