The document outlines the schedule and key activities for hooking up an ESP wellhead over 5 weeks from May 2nd to May 18th. It involves collecting materials, fabrication work in the workshop, installation work on site, hydrotesting, mechanical completion activities like inspection and punchlisting, and final commissioning and handover. The schedule is broken down into phases for logistics, construction, mechanical completion, and commissioning with over 20 distinct activities assigned durations and float times.
The document outlines the schedule and key activities for hooking up an ESP wellhead over 5 weeks from May 2nd to May 18th. It involves collecting materials, fabrication work in the workshop, installation work on site, hydrotesting, mechanical completion activities like inspection and punchlisting, and final commissioning and handover. The schedule is broken down into phases for logistics, construction, mechanical completion, and commissioning with over 20 distinct activities assigned durations and float times.
The document outlines the schedule and key activities for hooking up an ESP wellhead over 5 weeks from May 2nd to May 18th. It involves collecting materials, fabrication work in the workshop, installation work on site, hydrotesting, mechanical completion activities like inspection and punchlisting, and final commissioning and handover. The schedule is broken down into phases for logistics, construction, mechanical completion, and commissioning with over 20 distinct activities assigned durations and float times.
WHC-1.1 Keys of project 11 2/May/20 18/May/20 0 18/May/20
A1010 issue and collecting materials from client yard and construction 0 starting 2/May/20 0 A1020 pre-commissioning & mechanical comletion 0 11/May/20* 3 A1000 award of contract and PO issued to MIK CO. 0 2/May/20 0 A1030 commissioning & end of project 0 18/May/20 0 WHC-1.2 Logistic 5 2/May/20 6/May/20 0 6/May/20 A1040 collect and transport construction materials to workshop 1 2/May/20 2/May/20 0 collect and transport construction materials to workshop A1050 Transportion of piping spools to site 1 6/May/20 6/May/20 0 Transportion of piping spools to site WHC-1.3 construction 8 2/May/20 10/May/20 0 10/May/20
WHC-1.3.4 fabrication work in workshop 4 2/May/20 5/May/20 0 5/May/20
A1060grinding & leveling pipe spools and welding of joints 4 2/May/20 5/May/20 0 grinding & leveling pipe spools and welding of joints A1070RT activities 4 2/May/20 5/May/20 0 RT activities WHC-1.3.5 work in site 8 2/May/20 10/May/20 0 10/May/20 A1080PRC from client 1 2/May/20 2/May/20 4 PRC from client A1090site lay out & survey 1 2/May/20 2/May/20 4 site lay out & survey A1100piping support & spools installation 1 6/May/20 6/May/20 0 piping support & spools installation A1140hydrotest activities 1 10/May/20 10/May/20 0 hydrotest activities A1150reinstatement 1 10/May/20 10/May/20 0 reinstatement A1110field joints welding 3 6/May/20 9/May/20 0 field joints welding A1120RT activities 3 6/May/20 9/May/20 0 RT activities A1130valves installation & preparation for hydrotest 3 6/May/20 9/May/20 0 valves installation & preparation for hydrotest WHC-1.4 mechanical completetion certificate work3 11/May/20 18/May/20 0 18/May/20 A1170 final inspection 1 18/May/20 18/May/20 0 final inspection A1160 internal punchlist 2 11/May/20 17/May/20 0 internal punchlist WHC-1.5 commissioning & end of project 1 18/May/20 18/May/20 0 18/May/20 A1180 handover of well head project 1 18/May/20 18/May/20 0 handover of well head project
Date Revision Checked Approved
Actual Work Remaining Work Maraba AL-IRAQ DR.CONCRETE 27/Feb/20 R1 ENG. Wael...