You are on page 1of 1

ESP Well head hook up

Activity ID Activity Name Original Start Finish Total Week


Duration Float
1 2 3
WHC-1 ESP wellhead hook up 11 2/May/20 18/May/20 0 18/May/20

WHC-1.1 Keys of project 11 2/May/20 18/May/20 0 18/May/20


A1010 issue and collecting materials from client yard and construction 0
starting
2/May/20 0
A1020 pre-commissioning & mechanical comletion 0 11/May/20* 3
A1000 award of contract and PO issued to MIK CO. 0 2/May/20 0
A1030 commissioning & end of project 0 18/May/20 0
WHC-1.2 Logistic 5 2/May/20 6/May/20 0 6/May/20
A1040 collect and transport construction materials to workshop 1 2/May/20 2/May/20 0 collect and transport construction materials to workshop
A1050 Transportion of piping spools to site 1 6/May/20 6/May/20 0 Transportion of piping spools to site
WHC-1.3 construction 8 2/May/20 10/May/20 0 10/May/20

WHC-1.3.4 fabrication work in workshop 4 2/May/20 5/May/20 0 5/May/20


A1060grinding & leveling pipe spools and welding of joints 4 2/May/20 5/May/20 0 grinding & leveling pipe spools and welding of joints
A1070RT activities 4 2/May/20 5/May/20 0 RT activities
WHC-1.3.5 work in site 8 2/May/20 10/May/20 0 10/May/20
A1080PRC from client 1 2/May/20 2/May/20 4 PRC from client
A1090site lay out & survey 1 2/May/20 2/May/20 4 site lay out & survey
A1100piping support & spools installation 1 6/May/20 6/May/20 0 piping support & spools installation
A1140hydrotest activities 1 10/May/20 10/May/20 0 hydrotest activities
A1150reinstatement 1 10/May/20 10/May/20 0 reinstatement
A1110field joints welding 3 6/May/20 9/May/20 0 field joints welding
A1120RT activities 3 6/May/20 9/May/20 0 RT activities
A1130valves installation & preparation for hydrotest 3 6/May/20 9/May/20 0 valves installation & preparation for hydrotest
WHC-1.4 mechanical completetion certificate work3 11/May/20 18/May/20 0 18/May/20
A1170 final inspection 1 18/May/20 18/May/20 0 final inspection
A1160 internal punchlist 2 11/May/20 17/May/20 0 internal punchlist
WHC-1.5 commissioning & end of project 1 18/May/20 18/May/20 0 18/May/20
A1180 handover of well head project 1 18/May/20 18/May/20 0 handover of well head project

Date Revision Checked Approved


Actual Work
Remaining Work Maraba AL-IRAQ DR.CONCRETE 27/Feb/20 R1 ENG. Wael...

Critical Remaining Work


Milestone AL-KHADRA CO. CO.

You might also like