You are on page 1of 1

Activity ID Activity Name Original Start Finish Activity % 2019 2020

Duration Qtr 4
Complete Qtr 1 Qtr 2
Nov Dec Jan Feb Mar Apr May Jun
MOC-52-1 TO INSTALL ADDITIONAL ACCESS PLATFORM FOR 43.2d
MANUAL OPERATION OF11-Apr-20
COKE 31-May-20
DRUM MOV's 31-May-20, MOC-52-

MOC-52-1.1 MILESTONES 43.2d 11-Apr-20 31-May-20 31-May-20, MOC-52-


A1010 Project start 0.0d 11-Apr-20 0% Project start, 11-Apr-20
A1020 Project Finish 0.0d 31-May-20 0% Project Finish,
MOC-52-1.2 GENERAL ACTIVITIES 4.0d 11-Apr-20 14-Apr-20 14-Apr-20, MOC-52-1.2 GENERAL ACTIVITIES
A1000 Award of contract 0.8d 11-Apr-20 11-Apr-20 0% Award of contract
A1030 Kick off meeting 0.8d 11-Apr-20 12-Apr-20 0% Kick off meeting
A1040 Submission of project documents such as JSA,MOS,WPS etc for SATORP review and approval 2.4d 12-Apr-20 14-Apr-20 0% Submission of project documents such as JSA,MO
A1050 Submission of ID documents for manpower and equipments if necessary 1.6d 12-Apr-20 14-Apr-20 0% Submission of ID documents for manpower and eq
MOC-52-1.3 PROCUREMENT PHASE 5.6d 15-Apr-20 21-Apr-20 21-Apr-20, MOC-52-1.3 PROCUREMENT PH
A1070 Procurement of support platforms and grating fabrication materials and accesories 5.6d 15-Apr-20 21-Apr-20 0% Procurement of support platforms and grating
MOC-52-1.4 PREFABRICATION PHASE 12.0d 21-Apr-20 05-May-20 05-May-20, MOC-52-1.4 PREFABRIC
A1080 Prefabrication of support platforms and grating with reference to standard drawings 8.0d 21-Apr-20 30-Apr-20 0% Prefabrication of support platforms and g
A1090 Paintings of platform and grating after prefabricaiton 4.0d 30-Apr-20 05-May-20 0% Paintings of platform and grating afte
MOC-52-1.5 EXECUTION AT SITE 21.6d 03-May-20 27-May-20 27-May-20, MOC-52-1.5
A1110 Mobilisation of manpower and equipments to site 0.8d 03-May-20 03-May-20 0% Mobilisation of manpower and equipm
A1130 Scaffolding erection at required locaitons 2.4d 04-May-20 06-May-20 0% Scaffolding erection at required locait
MOC-52-1.5.1 Type II - Extension of additional platform at 4 locations 4.8d 05-May-20 11-May-20 11-May-20, MOC-52-1.5.1 Type I
A1120 Erection and installation of prefabricated platforms with exisitng as per approved drawing using crane 4.8d 05-May-20 11-May-20 0% Erection and installation of prefab
A1200 Inspection after installation of platforms 0.8d 10-May-20 11-May-20 0% Inspection after installation of plat
MOC-52-1.5.2 Type III-Extension of additional platform at 6 locations & laying of grating and handrail 4.8d 11-May-20 17-May-20 17-May-20, MOC-52-1.5.2 Ty
A1150 Erection and installation of prefabricated platforms and gratings with existing as per approved drawing using crane
4.8d 11-May-20 17-May-20 0% Erection and installation of pre
A1210 Inspection after installation of platforms and gratings 0.8d 16-May-20 17-May-20 0% Inspection after installation of
MOC-52-1.5.3 Type IV - Installation of 3 new platforms 4.8d 17-May-20 21-May-20 21-May-20, MOC-52-1.5.3
A1160 Erection and installation of prefabricated platforms as per approved drawing using crane 4.8d 17-May-20 21-May-20 0% Erection and installation of p
A1220 Inspection after installation of platforms 0.8d 21-May-20 21-May-20 0% Inspection after installation
MOC-52-1.5.4 Type V- Installation of 3 new platforms 4.8d 23-May-20 27-May-20 27-May-20, MOC-52-1.5
A1170 Erection and installation of prefabricated platforms as per approved drawing using crane 4.8d 23-May-20 27-May-20 0% Erection and installation
A1230 Inspection after installation of platforms 0.8d 27-May-20 27-May-20 0% Inspection after installat
MOC-52-1.6 PROJECT HANDOVER 2.4d 27-May-20 31-May-20 31-May-20, MOC-52-
A1190 submission of project documents 2.4d 27-May-20 31-May-20 0% submission of project
A1191 Demobilisation of manpower and equipments 1.6d 28-May-20 31-May-20 0% Demobilisation of ma

Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation