CONSTRUCTION OF DHARAHARA (DOUBLE BASEMENT WITH DHARAHARA TOWER) Contract ID: Dharahara001 06-Jul-20 13:09

Activity ID Activity Name Original Start Finish Remarks 2020 2021 2022
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
DD CONSTRUCTION OF DHARAHARA 471d 08-Jun-20 06-Oct-21 06-Oct-21, DD CONSTRUCTION OF DH

DD.1 DOUBLE BASEMENT WITH DHARAHARA 471d 08-Jun-20 06-Oct-21 06-Oct-21, DD.1 DOUBLE BASEMENT

DD.1.1 GENERAL REQUIREMENTS & PRELIMINARIES 403d 15-Aug-20 06-Oct-21 06-Oct-21, DD.1.1 GENERAL REQUIRE
DD.1.1.1 PROJECT MILESTONES 403d 15-Aug-20 06-Oct-21 06-Oct-21, DD.1.1.1 PROJECT MILEST
D1800 Final Closeout Double Basement with Tower 0d 06-Oct-21 Final Closeout Double Basement with To
D2150 Structural Works (Remaining Upper Basement Slab) 0d 15-Aug-20 Structural Works (Remaining Upper Basement Slab),
D2160 Structural works (Remaining floor of Dharahara tower) 0d 15-May-21 Structural works (Remaining floor of Dharahara tower),
DD.1.2 CONSTRUCTION WORKS 466d 08-Jun-20 30-Sep-21 30-Sep-21, DD.1.2 CONSTRUCTION WO
DD.1.2.2 SUBSTRUCTURE 200d 08-Jun-20 03-Jan-21 03-Jan-21, DD.1.2.2 SUBSTRUCTURE
DD.1.2.2.1 EARTH WORK 125d 23-Aug-20 03-Jan-21 03-Jan-21, DD.1.2.2.1 EARTH WORK
D1440 Backfilling at gaps between Skinwall & Shearwall 90d 27-Sep-20 03-Jan-21 Depends on Backfilling at gaps between Skinwall & Shearwall
Sundhara outlet plan
D1760 Gravel Sand Mixture 24d 27-Sep-20 21-Oct-20 Gravel Sand Mixture
D1770 Anti -Termite Spray 15d 23-Aug-20 07-Sep-20 Anti -Termite Spray
DD.1.2.2.2 SUBSTRUCTURE WATER PROOFING WROK 35d 23-Aug-20 27-Sep-20 27-Sep-20, DD.1.2.2.2 SUBSTRUCTURE WATER PROOFING WROK
D1040 Vertical Waterproofing Membrane 35d 23-Aug-20 27-Sep-20 Vertical Waterproofing Membrane
DD.1.2.2.3 PART-2 Remaining Double basement area 68d 08-Jun-20 15-Aug-20 15-Aug-20, DD.1.2.2.3 PART-2 Remaining Double basement area
DD.1.2.2.3.10 BASEMENT NO 01 (1B) 68d 08-Jun-20 15-Aug-20 15-Aug-20, DD.1.2.2.3.10 BASEMENT NO 01 (1B)
D1780 Steel Reinforcement. Formwork & Concrete Casting for 38d 08-Jun-20* 16-Jul-20 Steel Reinforcement. Formwork & Concrete Casting for Shear Wall & Columns
Shear Wall & Columns
D1790 Slab & Beam Reif, Formwork & Concrete Casting for 1B 30d 16-Jul-20 15-Aug-20 Slab & Beam Reif, Formwork & Concrete Casting for 1B
DD.1.2.3 SUPERSTRUCTURE 293d 15-Jul-20 15-May-21 15-May-21, DD.1.2.3 SUPERSTRUCTURE
DD.1.2.3.1 Dharahara Tower 293d 15-Jul-20 15-May-21 15-May-21, DD.1.2.3.1 Dharahara Tower
DD.1.2.3.1.11 Dharahara Tower 11F 20d 15-Jul-20 04-Aug-20 04-Aug-20, DD.1.2.3.1.11 Dharahara Tower 11F
D1910 Steel Reinforcement, Formwork & Concrete Casting for Wall 10d 15-Jul-20* 25-Jul-20 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
& Columns
D1920 Slab & Beam Reif, Formwork & Concrete Casting 9d 26-Jul-20 04-Aug-20 Slab & Beam Reif, Formwork & Concrete Casting
DD.1.2.3.1.12 Dharahara Tower 12F 20d 05-Aug-20 25-Aug-20 25-Aug-20, DD.1.2.3.1.12 Dharahara Tower 12F
D1930 Slab & Beam Reif, Formwork & Concrete Casting 10d 05-Aug-20 15-Aug-20 Slab & Beam Reif, Formwork & Concrete Casting
D1940 Steel Reinforcement, Formwork & Concrete Casting for Wall 9d 16-Aug-20 25-Aug-20 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
& Columns
DD.1.2.3.1.13 Dharahara Tower 13F 20d 26-Aug-20 15-Sep-20 15-Sep-20, DD.1.2.3.1.13 Dharahara Tower 13F
D1950 Steel Reinforcement, Formwork & Concrete Casting for Wall 10d 26-Aug-20 05-Sep-20 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
& Columns
D1960 Slab & Beam Reif, Formwork & Concrete Casting 9d 06-Sep-20 15-Sep-20 Slab & Beam Reif, Formwork & Concrete Casting
DD.1.2.3.1.14 Dharahara Tower 14F 20d 16-Sep-20 06-Oct-20 06-Oct-20, DD.1.2.3.1.14 Dharahara Tower 14F
D1970 Steel Reinforcement, Formwork & Concrete Casting for Wall 10d 16-Sep-20 26-Sep-20 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
& Columns
D1980 Slab & Beam Reif, Formwork & Concrete Casting 9d 27-Sep-20 06-Oct-20 Slab & Beam Reif, Formwork & Concrete Casting
DD.1.2.3.1.15 Dharahara Tower 15F 21d 07-Oct-20 02-Nov-20 02-Nov-20, DD.1.2.3.1.15 Dharahara Tower 15F
D1990 Steel Reinforcement, Formwork & Concrete Casting for Wall 10d 07-Oct-20 17-Oct-20 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
& Columns
D2000 Slab & Beam Reif, Formwork & Concrete Casting 10d 18-Oct-20 02-Nov-20 Slab & Beam Reif, Formwork & Concrete Casting
DD.1.2.3.1.16 Dharahara Tower 16F 21d 03-Nov-20 27-Nov-20 27-Nov-20, DD.1.2.3.1.16 Dharahara Tower 16F
D2010 Steel Reinforcement, Formwork & Concrete Casting for Wall 10d 03-Nov-20 13-Nov-20 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
& Columns
D2020 Slab & Beam Reif, Formwork & Concrete Casting 10d 17-Nov-20 27-Nov-20 Slab & Beam Reif, Formwork & Concrete Casting
DD.1.2.3.1.17 Dharahara Tower 17F 21d 27-Nov-20 19-Dec-20 19-Dec-20, DD.1.2.3.1.17 Dharahara Tower 17F
D2030 Steel Reinforcement, Formwork & Concrete Casting for Wall 10d 27-Nov-20 08-Dec-20 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
& Columns
D2040 Slab & Beam Reif, Formwork & Concrete Casting 10d 09-Dec-20 19-Dec-20 Slab & Beam Reif, Formwork & Concrete Casting
DD.1.2.3.1.18 Dharahara Tower 18F 21d 20-Dec-20 10-Jan-21 10-Jan-21, DD.1.2.3.1.18 Dharahara Tower 18F

Actual Level of Effort Critical Remaining Work Page 1 of 3 TASK filter: All Activities
© GIETC-RAMAN JV
Actual Work Milestone Note: All the works depends upon site condition, return of the workers from their residence, longitivity of
Remaining Work summary
EPIDEMIC COVID 19 and earliest issuance of all detailed drawings.
CONSTRUCTION OF DHARAHARA (DOUBLE BASEMENT WITH DHARAHARA TOWER) Contract ID: Dharahara001 06-Jul-20 13:09
Activity ID Activity Name Original Start Finish Remarks 2020 2021 2022
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
D2050 Steel Reinforcement, Formwork & Concrete Casting for Wall 10d 20-Dec-20 30-Dec-20 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
& Columns
D2060 Slab & Beam Reif, Formwork & Concrete Casting 10d 31-Dec-20 10-Jan-21 Slab & Beam Reif, Formwork & Concrete Casting
DD.1.2.3.1.19 Dharahara Tower 19F 25d 11-Jan-21 05-Feb-21 05-Feb-21, DD.1.2.3.1.19 Dharahara Tower 19F
D2070 Steel Reinforcement, Formwork & Concrete Casting for Wall 12d 11-Jan-21 23-Jan-21 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
& Columns
D2080 Slab & Beam Reif, Formwork & Concrete Casting 12d 24-Jan-21 05-Feb-21 Slab & Beam Reif, Formwork & Concrete Casting
DD.1.2.3.1.20 Dharahara Tower 20F 25d 06-Feb-21 03-Mar-21 03-Mar-21, DD.1.2.3.1.20 Dharahara Tower 20F
D2090 Steel Reinforcement, Formwork & Concrete Casting for Wall 12d 06-Feb-21 18-Feb-21 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
& Columns
D2100 Slab & Beam Reif, Formwork & Concrete Casting 12d 19-Feb-21 03-Mar-21 Slab & Beam Reif, Formwork & Concrete Casting
DD.1.2.3.1.21 Dharahara Tower 21F 25d 04-Mar-21 29-Mar-21 29-Mar-21, DD.1.2.3.1.21 Dharahara Tower 21F
D2110 Steel Reinforcement, Formwork & Concrete Casting for Wall 12d 04-Mar-21 16-Mar-21 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
& Columns
D2120 Slab & Beam Reif, Formwork & Concrete Casting 12d 17-Mar-21 29-Mar-21 Slab & Beam Reif, Formwork & Concrete Casting
DD.1.2.3.1.22 Dharahara Tower 22F 25d 30-Mar-21 24-Apr-21 24-Apr-21, DD.1.2.3.1.22 Dharahara Tower 22F
D2130 Steel Reinforcement, Formwork & Concrete Casting for Wall 12d 30-Mar-21 11-Apr-21 Steel Reinforcement, Formwork & Concrete Casting for Wall & Columns
& Columns
D2140 Slab & Beam Reif, Formwork & Concrete Casting 12d 12-Apr-21 24-Apr-21 Slab & Beam Reif, Formwork & Concrete Casting
DD.1.2.3.1.23 Dharahara Tower Pinnacle 20d 25-Apr-21 15-May-21 15-May-21, DD.1.2.3.1.23 Dharahara Tower Pinnacle
D1000 Pinnacle Works 20d 25-Apr-21 15-May-21 Pinnacle Works
DD.1.2.4 ROUGH FINISHES INTERNAL 408d 23-Jul-20 17-Sep-21 17-Sep-21, DD.1.2.4 ROUGH FINISHES INT
DD.1.2.4.1 BASEMENT NO 02 (2B) 395d 23-Jul-20 03-Sep-21 03-Sep-21, DD.1.2.4.1 BASEMENT NO 02 (2B)
D1050 Masonary Work 60d 23-Jul-20* 21-Sep-20 Masonary Work
D1060 Plastering Work 70d 28-Jul-20 07-Oct-20 Plastering Work
D1080 Granite Flooring and wall cladding Work 50d 15-May-21* 04-Jul-21 Granite Flooring and wall cladding Work
D1090 Wall fin ishes & Skirting (Granit e) 20d 14-Jun-21 04-Jul-21 Wall fin ishes & Skirtin g (Granit e)
D1430 Wooden Flooring 60d 04-Jul-21 03-Sep-21 Wooden Flooring
DD.1.2.4.2 BASEMENT NO 01 (1B) 345d 21-Sep-20 13-Sep-21 13-Sep-21, DD.1.2.4.2 BASEMENT NO 01 (1
D1100 Masonary Work 60d 21-Sep-20 28-Nov-20 Masonary Work
D1110 Plastering Work 70d 07-Oct-20 24-Dec-20 Plastering Work
D1130 Granite Flooring and wall cladding Work 70d 04-Jul-21 13-Sep-21 Granite Flooring and wall cladding Work
D1140 Wall fin ishes & Skirting (Granit e) 20d 24-Aug-21 13-Sep-21 Wall fin ishes & Skirtin g (Granit e)
DD.1.2.4.3 DHARAHARA TOWER 408d 23-Jul-20 17-Sep-21 17-Sep-21, DD.1.2.4.3 DHARAHARA TOWE
D1150 Masonary Work 280d 23-Jul-20* 10-May-21 Masonary Work
D1160 Internal Plastering Work 280d 28-Jul-20 15-May-21 Internal Plastering Work
D1170 External Plastering Work 121d 17-May-21 17-Sep-21 External Plastering Work
D1190 Vitrified Tile Flooring 117d 20-May-21 15-Sep-21 Vitrified Tile Flooring
D1200 Granite flooring and wall cladding work 117d 20-May-21 15-Sep-21 Granite flooring and wall cladding work
D2170 Wooden Flooring 15d 31-Aug-21 15-Sep-21 Wooden Flooring
DD.1.2.5 FINAL FINISHES INTERNAL 300d 01-Dec-20 30-Sep-21 30-Sep-21, DD.1.2.5 FINAL FINISHES IN
DD.1.2.5.1 BASEMENT NO 02 (2B) 57d 04-Jul-21 31-Aug-21 31-Aug-21, DD.1.2.5.1 BASEMENT NO 02 (2B)
D1210 Paint Work 30d 04-Jul-21 04-Aug-21 Paint Work
D1220 Metal Works 25d 11-Jul-21 05-Aug-21 Metal Works
D1230 Doors & Windows (Wood & Alluminium) 25d 05-Aug-21 31-Aug-21 Doors & Windows (Wood & Alluminium)
D1730 Staircase finishing (Balustrades,Handrails & Marble for 20d 26-Jul-21 15-Aug-21 Staircase finishing (Balustrades,Handrails & Marble fo
Tread, Riser & Landing)
DD.1.2.5.2 BASEMENT NO 01 (1B) 57d 04-Aug-21 30-Sep-21 30-Sep-21, DD.1.2.5.2 BASEMENT NO 0
D1240 Paint Work 30d 04-Aug-21 03-Sep-21 Paint Work
D1250 Metal Works 25d 10-Aug-21 05-Sep-21 Metal Works
D1260 Doors & Windows (Wood & Alluminium) 25d 05-Sep-21 30-Sep-21 Doors & Windows (Wood & Alluminium)
D1740 Staircase finishing (Balustrades,Handrails & Marble for 20d 26-Aug-21 15-Sep-21 Staircase finishing (Balustrades,Handrails & M
Tread, Riser & Landing)

Actual Level of Effort Critical Remaining Work Page 2 of 3 TASK filter: All Activities
© GIETC-RAMAN JV
Actual Work Milestone Note: All the works depends upon site condition, return of the workers from their residence, longitivity of
Remaining Work summary
EPIDEMIC COVID 19 and earliest issuance of all detailed drawings.
CONSTRUCTION OF DHARAHARA (DOUBLE BASEMENT WITH DHARAHARA TOWER) Contract ID: Dharahara001 06-Jul-20 13:09
Activity ID Activity Name Original Start Finish Remarks 2020 2021 2022
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
DD.1.2.5.3 DHARAHARA TOWER 300d 01-Dec-20 30-Sep-21 30-Sep-21, DD.1.2.5.3 DHARAHARA TO
D1270 Paint Work 87d 04-Jul-21 30-Sep-21 Paint Work
D1280 Metal Works 75d 16-Jul-21 30-Sep-21 Metal Works
D1290 Doors & Windows (Wood, Glass & Alluminium) 60d 01-Aug-21 30-Sep-21 Doors & Windows (Wood, Glass & Allumini
D1300 False Ceiling works (Wooden, Mineral Fiber, Gypsum, 210d 01-Dec-20* 01-Jul-21 False Ceiling works (Wooden, Mineral Fiber, Gypsum, Cement fib
Cement fibre board)
D1750 Staircase finishing (Balustrades,Handrails & Marble for 70d 20-Jul-21 29-Sep-21 Staircase finishing (Balustrades,Handrails &
Tread, Riser & Landing)
DD.1.2.6 EXTERNAL FINISHES 429d 15-Jul-20 30-Sep-21 30-Sep-21, DD.1.2.6 EXTERNAL FINISH
D1010 Boundary Wall (Stone Masonry Works) 296d 15-Jul-20* 18-May-21 Boundary wall at south Boundary Wall (Stone Masonry Works)
side to start
D1020 Plinth Protection Works 60d 18-May-21 18-Jul-21 Plinth Protection Works
D1310 Flagstone Works 90d 18-May-21 17-Aug-21 Flagstone Works
D1320 Ticket counter 40d 18-May-21 27-Jun-21 Ticket counter
D1690 Clay tile works 40d 28-Jun-21 07-Aug-21 Clay tile works
D1700 Pyramid Glass 90d 18-May-21 17-Aug-21 Pyramid Glass
D1710 Landscaping works 133d 18-May-21 30-Sep-21 Landscaping works
DD.1.3 CONVEYING SYSTEM 95d 14-Jun-21 18-Sep-21 18-Sep-21, DD.1.3 CONVEYING SYSTEM
DD.1.4 MEP WORKS 422d 23-Jul-20 30-Sep-21 30-Sep-21, DD.1.4 MEP WORKS
DD.1.5 TESTING AND COMMISSIONING 5d 01-Oct-21 06-Oct-21 06-Oct-21, DD.1.5 TESTING AND COM
DD.1.6 CLOSE OUT AND HANDING OVER 17d 18-Sep-21 06-Oct-21 06-Oct-21, DD.1.6 CLOSE OUT AND HA
D1360 Final Finished Closeout 0d 30-Sep-21 Final Finished Closeout,
D1370 Mechanical / HVAC Work Closeout 0d 06-Oct-21 Mechanical / HVAC Work Closeout,
D1380 Electrical Work Closeout 0d 06-Oct-21 Electrical Work Closeout,
D1390 Plumbing Work Closeout 0d 06-Oct-21 Plumbing Work Closeout,
D1400 Fire Fighting Work Closeout 0d 06-Oct-21 Fire Fighting Work Closeout,
D1410 Conveying System Closeout 0d 18-Sep-21 Conveying System Closeout,

Actual Level of Effort Critical Remaining Work Page 3 of 3 TASK filter: All Activities
© GIETC-RAMAN JV
Actual Work Milestone Note: All the works depends upon site condition, return of the workers from their residence, longitivity of
Remaining Work summary
EPIDEMIC COVID 19 and earliest issuance of all detailed drawings.