Latin District's Bufferzone Project Time Schedule

Activity ID Activity Name Start Original Finish Total Float Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...


NEWPROJ-3 Latin District Summa
NEWPR
01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...
NEWPROJ-3.1 Milestones
NEWPR
A1000 Project Start 01-Jan-2023 0d 0d Project St...
A1015 Zone 1 Engineering Finished 0d 09-Jun-2023 191d Zone 1 Eng...
A1025 Zone 2 Engineering Finished 0d 27-Apr-2023 234d Zone 2 Eng...
A1035 Zone 3 Engineering Finished 0d 10-May-2023 221d Zone 3 Eng...
A1045 Zone 4 Engineering Finished 0d 24-Jul-2023 146d Zone 4 Eng...
A1050 Engineering stage finished 0d 24-Jul-2023 156d Engineerin...
A1060 Zone 1 Finished 0d 20-Sep-2023 88d Zone 1 Fin...
A1070 Zone 2 Finished 0d 20-Jun-2023 180d Zone 2 Fin...
A1080 Zone 3 Finished 0d 10-Aug-2023 129d Zone 3 Fin...
A1090 Zone 4 Finished 0d 17-Dec-2023 0d Zone 4 Fin...
A1100 Project Finish 0d 27-Dec-2023 0d Project Fi...
06-Jan-2023 200d 24-Jul-2023 118d 24-Jul-202...
NEWPROJ-3.2 Engineering
NEWPR
16-Jan-2023 145d 09-Jun-2023 143d 09-Jun-202...
NEWPROJ-3.2.1 Zone 1
NEWPR
06-Jan-2023 112d 27-Apr-2023 206d 27-Apr-202...
NEWPROJ-3.2.2 Zone 2
NEWPR
31-Jan-2023 100d 10-May-2023 193d 10-May-202...
NEWPROJ-3.2.3 Zone 3
NEWPR
07-Mar-2023 140d 24-Jul-2023 115d 24-Jul-202...
NEWPROJ-3.2.4 Zone 4
NEWPR
07-Mar-2023 175d 28-Aug-2023 108d 28-Aug-202...
NEWPROJ-3.3 Procurement
NEWPR
01-Apr-2023 150d 28-Aug-2023 88d 28-Aug-202...
NEWPROJ-3.3.1 Zone 1
NEWPR
07-Mar-2023 87d 01-Jun-2023 196d 01-Jun-202...
NEWPROJ-3.3.2 Zone 2
NEWPR
27-Mar-2023 65d 30-May-2023 198d 30-May-202...
NEWPROJ-3.3.3 Zone 3
NEWPR
21-May-2023 95d 23-Aug-2023 110d 23-Aug-202...
NEWPROJ-3.3.4 Zone 4
NEWPR
01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...
NEWPROJ-3.4 Construction
NEWPR
01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...
NEWPROJ-3.4.5 Preliminary works
NEWPR
A1260 Mobilization 01-Jan-2023 5d 05-Jan-2023 10d Mobilizati...
A1270 Demobilization 18-Dec-2023 10d 27-Dec-2023 0d Demobiliza...
16-May-2023 128d 20-Sep-2023 88d 20-Sep-202...
NEWPROJ-3.4.1 Zone 1
NEWPR
04-Apr-2023 78d 20-Jun-2023 180d 20-Jun-202...
NEWPROJ-3.4.2 Zone 2
NEWPR
06-Apr-2023 127d 10-Aug-2023 129d 10-Aug-202...
NEWPROJ-3.4.3 Zone 3
NEWPR
10-Jul-2023 161d 17-Dec-2023 0d 17-Dec-202...
NEWPROJ-3.4.4 Zone 4
NEWPR

Remaining Work Milestone Page 1 of 1 TASK filter: All Activities


Critical Remaining Work summary © Oracle Corporation
Latin District's Bufferzone Project Time Schedule
Activity ID Activity Name Start Original Finish Total Float Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...


NEWPROJ-3 Latin District Summa
NEWPR
01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...
NEWPROJ-3.1 Milestones
NEWPR
A1000 Project Start 01-Jan-2023 0d 0d Project St...
A1015 Zone 1 Engineering Finished 0d 09-Jun-2023 191d Zone 1 Eng...
A1025 Zone 2 Engineering Finished 0d 27-Apr-2023 234d Zone 2 Eng...
A1035 Zone 3 Engineering Finished 0d 10-May-2023 221d Zone 3 Eng...
A1045 Zone 4 Engineering Finished 0d 24-Jul-2023 146d Zone 4 Eng...
A1050 Engineering stage finished 0d 24-Jul-2023 156d Engineerin...
A1060 Zone 1 Finished 0d 20-Sep-2023 88d Zone 1 Fin...
A1070 Zone 2 Finished 0d 20-Jun-2023 180d Zone 2 Fin...
A1080 Zone 3 Finished 0d 10-Aug-2023 129d Zone 3 Fin...
A1090 Zone 4 Finished 0d 17-Dec-2023 0d Zone 4 Fin...
A1100 Project Finish 0d 27-Dec-2023 0d Project Fi...
06-Jan-2023 200d 24-Jul-2023 118d 24-Jul-202...
NEWPROJ-3.2 Engineering
NEWPR
16-Jan-2023 145d 09-Jun-2023 143d 09-Jun-202...
NEWPROJ-3.2.1 Zone 1
NEWPR
NEWP
NEWPROJ-3.2.1.1 Z1 Hardscape 16-Jan-2023 145d 09-Jun-2023 108d 09-Jun-202...

NEWPROJ-3.2.1.2 Z1 Softscape
NEWP 01-Apr-2023 40d 10-May-2023 173d 10-May-202...
06-Jan-2023 112d 27-Apr-2023 206d 27-Apr-202...
NEWPROJ-3.2.2 Zone 2
NEWPR
NEWP
NEWPROJ-3.2.2.1 Z2 Hardscape 06-Jan-2023 112d 27-Apr-2023 180d 27-Apr-202...

NEWPROJ-3.2.2.2 Z2 Softscape
NEWP 25-Feb-2023 36d 01-Apr-2023 232d 01-Apr-202...
31-Jan-2023 100d 10-May-2023 193d 10-May-202...
NEWPROJ-3.2.3 Zone 3
NEWPR
NEWP
NEWPROJ-3.2.3.1 Z3 Hardscape 31-Jan-2023 100d 10-May-2023 172d 10-May-202...

NEWPROJ-3.2.3.2 Z3 Softscape
NEWP 22-Mar-2023 36d 26-Apr-2023 207d 26-Apr-202...

NEWPROJ-3.2.4 Zone 4
NEWPR 07-Mar-2023 140d 24-Jul-2023 115d 24-Jul-202...

NEWP
NEWPROJ-3.2.4.1 Z4 Hardscape 07-Mar-2023 140d 24-Jul-2023 71d 24-Jul-202...

NEWPROJ-3.2.4.2 Z4 Softscape
NEWP 26-Apr-2023 40d 04-Jun-2023 165d 04-Jun-202...
07-Mar-2023 175d 28-Aug-2023 108d 28-Aug-202...
NEWPROJ-3.3 Procurement
NEWPR
01-Apr-2023 150d 28-Aug-2023 88d 28-Aug-202...
NEWPROJ-3.3.1 Zone 1
NEWPR
NEWP
NEWPROJ-3.3.1.1 Z1 Civil works Proc. 01-Apr-2023 105d 14-Jul-2023 118d 14-Jul-202...

NEWPROJ-3.3.1.2 Z1 Softscape Proc.


NEWP 04-Aug-2023 25d 28-Aug-2023 88d 28-Aug-202...
07-Mar-2023 87d 01-Jun-2023 196d 01-Jun-202...
NEWPROJ-3.3.2 Zone 2
NEWPR
NEWP
NEWPROJ-3.3.2.1 Z2 Civil works Proc. 07-Mar-2023 87d 01-Jun-2023 189d 01-Jun-202...

NEWPROJ-3.3.2.2 Z2 Softscape Proc.


NEWP 02-Apr-2023 25d 26-Apr-2023 232d 26-Apr-202...
27-Mar-2023 65d 30-May-2023 198d 30-May-202...
NEWPROJ-3.3.3 Zone 3
NEWPR
NEWP
NEWPROJ-3.3.3.1 Z3 Civil works Proc. 27-Mar-2023 65d 30-May-2023 183d 30-May-202...

NEWPROJ-3.3.3.2 Z3 Softscape Proc.


NEWP 27-Apr-2023 25d 21-May-2023 207d 21-May-202...
21-May-2023 95d 23-Aug-2023 110d 23-Aug-202...
NEWPROJ-3.3.4 Zone 4
NEWPR
NEWP
NEWPROJ-3.3.4.1 Z4 Civil works Proc. 21-May-2023 95d 23-Aug-2023 66d 23-Aug-202...

NEWPROJ-3.3.4.2 Z4 Softscape Proc.


NEWP 05-Jun-2023 25d 29-Jun-2023 165d 29-Jun-202...
01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...
NEWPROJ-3.4 Construction
NEWPR
NEWPROJ-3.4.5 Preliminary works
NEWPR 01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...

A1260 Mobilization 01-Jan-2023 5d 05-Jan-2023 10d Mobilizati...


A1270 Demobilization 18-Dec-2023 10d 27-Dec-2023 0d Demobiliza...

NEWPROJ-3.4.1 Zone 1
NEWPR 16-May-2023 128d 20-Sep-2023 88d 20-Sep-202...

NEWP
NEWPROJ-3.4.1.1 Z1 Civil works 16-May-2023 103d 26-Aug-2023 113d 26-Aug-202...

NEWPROJ-3.4.1.2 Z1 Softscape works


NEWP 29-Aug-2023 23d 20-Sep-2023 88d 20-Sep-202...
04-Apr-2023 78d 20-Jun-2023 180d 20-Jun-202...
NEWPROJ-3.4.2 Zone 2
NEWPR
NEWP
NEWPROJ-3.4.2.3 Z2 Civil works 04-Apr-2023 76d 18-Jun-2023 182d 18-Jun-202...

NEWPROJ-3.4.2.4 Z2 Softscape works


NEWP 29-May-2023 23d 20-Jun-2023 180d 20-Jun-202...
06-Apr-2023 127d 10-Aug-2023 129d 10-Aug-202...
NEWPROJ-3.4.3 Zone 3
NEWPR
NEWP
NEWPROJ-3.4.3.3 Z3 Civil works 06-Apr-2023 127d 10-Aug-2023 129d 10-Aug-202...

NEWPROJ-3.4.3.4 Z3 Softscape works


NEWP 19-Jul-2023 23d 10-Aug-2023 129d 10-Aug-202...
10-Jul-2023 161d 17-Dec-2023 0d 17-Dec-202...
NEWPROJ-3.4.4 Zone 4
NEWPR
NEWP
NEWPROJ-3.4.4.3 Z4 Civil works 10-Jul-2023 133d 19-Nov-2023 28d 19-Nov-202...

NEWPROJ-3.4.4.1 Water Feature


NEWP 24-Aug-2023 76d 07-Nov-2023 0d 07-Nov-202...

NEWPROJ-3.4.4.4 Z4 Softscape works


NEWP 10-Nov-2023 38d 17-Dec-2023 0d 17-Dec-202...

Remaining Work Milestone Page 1 of 1 TASK filter: All Activities


Critical Remaining Work summary © Oracle Corporation
Latin District's Bufferzone Project Time Schedule
Activity ID Activity Name Start Original Finish Total Float Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...


NEWPROJ-3 Latin District Summa
NEWPR
01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...
NEWPROJ-3.1 Milestones
NEWPR
A1000 Project Start 01-Jan-2023 0d 0d Project St...
A1015 Zone 1 Engineering Finished 0d 09-Jun-2023 191d Zone 1 Eng...
A1025 Zone 2 Engineering Finished 0d 27-Apr-2023 234d Zone 2 Eng...
A1035 Zone 3 Engineering Finished 0d 10-May-2023 221d Zone 3 Eng...
A1045 Zone 4 Engineering Finished 0d 24-Jul-2023 146d Zone 4 Eng...
A1050 Engineering stage finished 0d 24-Jul-2023 156d Engineerin...
A1060 Zone 1 Finished 0d 20-Sep-2023 88d Zone 1 Fin...
A1070 Zone 2 Finished 0d 20-Jun-2023 180d Zone 2 Fin...
A1080 Zone 3 Finished 0d 10-Aug-2023 129d Zone 3 Fin...
A1090 Zone 4 Finished 0d 17-Dec-2023 0d Zone 4 Fin...
A1100 Project Finish 0d 27-Dec-2023 0d Project Fi...
06-Jan-2023 200d 24-Jul-2023 118d 24-Jul-202...
NEWPROJ-3.2 Engineering
NEWPR
16-Jan-2023 145d 09-Jun-2023 143d 09-Jun-202...
NEWPROJ-3.2.1 Zone 1
NEWPR
NEWPROJ-3.2.1.1 Z1 Hardscape
NEWP 16-Jan-2023 145d 09-Jun-2023 108d 09-Jun-202...
NEWP
NEWPROJ-3.2.1.1.1 Z1 MEP Engineering 31-Jan-2023 130d 09-Jun-2023 88d 09-Jun-202...
NEWPROJ-3.2.1.1.2 Z1 Civil & Arch. Engineering
NEWP 16-Jan-2023 115d 10-May-2023 138d 10-May-202...
NEWPROJ-3.2.1.2 Z1 Softscape
NEWP 01-Apr-2023 40d 10-May-2023 173d 10-May-202...
06-Jan-2023 112d 27-Apr-2023 206d 27-Apr-202...
NEWPROJ-3.2.2 Zone 2
NEWPR
NEWPROJ-3.2.2.1 Z2 Hardscape
NEWP 06-Jan-2023 112d 27-Apr-2023 180d 27-Apr-202...
NEWP
NEWPROJ-3.2.2.1.1 Z2 MEP Engineering 14-Jan-2023 104d 27-Apr-2023 180d 27-Apr-202...
NEWPROJ-3.2.2.1.2 Z2 Civil & Arch. Engineering
NEWP 06-Jan-2023 95d 10-Apr-2023 196d 10-Apr-202...
NEWPROJ-3.2.2.2 Z2 Softscape
NEWP 25-Feb-2023 36d 01-Apr-2023 232d 01-Apr-202...
31-Jan-2023 100d 10-May-2023 193d 10-May-202...
NEWPROJ-3.2.3 Zone 3
NEWPR
NEWPROJ-3.2.3.1 Z3 Hardscape
NEWP 31-Jan-2023 100d 10-May-2023 172d 10-May-202...
NEWP
NEWPROJ-3.2.3.1.1 Z3 MEP Engineering 15-Feb-2023 85d 10-May-2023 172d 10-May-202...
NEWPROJ-3.2.3.1.2 Z3 Civil & Arch. Engineering
NEWP 31-Jan-2023 55d 26-Mar-2023 208d 26-Mar-202...
NEWPROJ-3.2.3.2 Z3 Softscape
NEWP 22-Mar-2023 36d 26-Apr-2023 207d 26-Apr-202...
07-Mar-2023 140d 24-Jul-2023 115d 24-Jul-202...
NEWPROJ-3.2.4 Zone 4
NEWPR
NEWPROJ-3.2.4.1 Z4 Hardscape
NEWP 07-Mar-2023 140d 24-Jul-2023 71d 24-Jul-202...
NEWP
NEWPROJ-3.2.4.1.1 Z4 MEP Engineering 06-May-2023 80d 24-Jul-2023 15d 24-Jul-202...
NEWPROJ-3.2.4.1.2 Z4 Civil & Arch. Engineering
NEWP 07-Mar-2023 110d 24-Jun-2023 101d 24-Jun-202...
NEWPROJ-3.2.4.2 Z4 Softscape
NEWP 26-Apr-2023 40d 04-Jun-2023 165d 04-Jun-202...
07-Mar-2023 175d 28-Aug-2023 108d 28-Aug-202...
NEWPROJ-3.3 Procurement
NEWPR
01-Apr-2023 150d 28-Aug-2023 88d 28-Aug-202...
NEWPROJ-3.3.1 Zone 1
NEWPR
NEWP
NEWPROJ-3.3.1.1 Z1 Civil works Proc. 01-Apr-2023 105d 14-Jul-2023 118d 14-Jul-202...

NEWPROJ-3.3.1.2 Z1 Softscape Proc.


NEWP 04-Aug-2023 25d 28-Aug-2023 88d 28-Aug-202...

NEWPROJ-3.3.2 Zone 2
NEWPR 07-Mar-2023 87d 01-Jun-2023 196d 01-Jun-202...

NEWP
NEWPROJ-3.3.2.1 Z2 Civil works Proc. 07-Mar-2023 87d 01-Jun-2023 189d 01-Jun-202...

NEWPROJ-3.3.2.2 Z2 Softscape Proc.


NEWP 02-Apr-2023 25d 26-Apr-2023 232d 26-Apr-202...
27-Mar-2023 65d 30-May-2023 198d 30-May-202...
NEWPROJ-3.3.3 Zone 3
NEWPR
NEWP
NEWPROJ-3.3.3.1 Z3 Civil works Proc. 27-Mar-2023 65d 30-May-2023 183d 30-May-202...

NEWPROJ-3.3.3.2 Z3 Softscape Proc.


NEWP 27-Apr-2023 25d 21-May-2023 207d 21-May-202...
21-May-2023 95d 23-Aug-2023 110d 23-Aug-202...
NEWPROJ-3.3.4 Zone 4
NEWPR
NEWP
NEWPROJ-3.3.4.1 Z4 Civil works Proc. 21-May-2023 95d 23-Aug-2023 66d 23-Aug-202...

NEWPROJ-3.3.4.2 Z4 Softscape Proc.


NEWP 05-Jun-2023 25d 29-Jun-2023 165d 29-Jun-202...
01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...
NEWPROJ-3.4 Construction
NEWPR
01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...
NEWPROJ-3.4.5 Preliminary works
NEWPR
A1260 Mobilization 01-Jan-2023 5d 05-Jan-2023 10d Mobilizati...
A1270 Demobilization 18-Dec-2023 10d 27-Dec-2023 0d Demobiliza...
16-May-2023 128d 20-Sep-2023 88d 20-Sep-202...
NEWPROJ-3.4.1 Zone 1
NEWPR
NEWPROJ-3.4.1.1 Z1 Civil works
NEWP 16-May-2023 103d 26-Aug-2023 113d 26-Aug-202...
NEWPROJ-3.4.1.1.1 Z1 MEP works
NEWP 16-May-2023 85d 08-Aug-2023 88d 08-Aug-202...
NEW
NEWPROJ-3.4.1.1.1.1 Z1 Mechanical 16-May-2023 52d 06-Jul-2023 120d 06-Jul-202...
NEWPROJ-3.4.1.1.1.2 Z1 Electrical
NEW 27-Jun-2023 43d 08-Aug-2023 88d 08-Aug-202...
NEWP
NEWPROJ-3.4.1.1.2 Z1 Structural works 31-May-2023 83d 21-Aug-2023 88d 21-Aug-202...
NEWPROJ-3.4.1.1.3 Z1 Hardscape works
NEWP 30-Jul-2023 28d 26-Aug-2023 113d 26-Aug-202...
NEWPROJ-3.4.1.2 Z1 Softscape works
NEWP 29-Aug-2023 23d 20-Sep-2023 88d 20-Sep-202...
04-Apr-2023 78d 20-Jun-2023 180d 20-Jun-202...
NEWPROJ-3.4.2 Zone 2
NEWPR
NEWPROJ-3.4.2.3 Z2 Civil works
NEWP 04-Apr-2023 76d 18-Jun-2023 182d 18-Jun-202...
NEWPROJ-3.4.2.3.1 Z2 MEP works
NEWP 04-Apr-2023 67d 09-Jun-2023 180d 09-Jun-202...
NEW
NEWPROJ-3.4.2.3.1.1 Z2 Mechanical 04-Apr-2023 50d 23-May-2023 196d 23-May-202...
NEWPROJ-3.4.2.3.1.2 Z2 Electrical
NEW 05-May-2023 36d 09-Jun-2023 180d 09-Jun-202...
NEWP
NEWPROJ-3.4.2.3.2 Z2 Structural works 21-Apr-2023 51d 10-Jun-2023 180d 10-Jun-202...
NEWPROJ-3.4.2.3.3 Z2 Hardscape works
NEWP 22-May-2023 28d 18-Jun-2023 182d 18-Jun-202...
NEWPROJ-3.4.2.4 Z2 Softscape works
NEWP 29-May-2023 23d 20-Jun-2023 180d 20-Jun-202...
06-Apr-2023 127d 10-Aug-2023 129d 10-Aug-202...
NEWPROJ-3.4.3 Zone 3
NEWPR
NEWPROJ-3.4.3.3 Z3 Civil works
NEWP 06-Apr-2023 127d 10-Aug-2023 129d 10-Aug-202...
NEWPROJ-3.4.3.3.1 Z3 MEP works
NEWP 01-May-2023 90d 29-Jul-2023 130d 29-Jul-202...
NEW
NEWPROJ-3.4.3.3.1.1 Z3 Mechanical 01-May-2023 90d 29-Jul-2023 129d 29-Jul-202...
NEWPROJ-3.4.3.3.1.2 Z3 Electrical
NEW 13-May-2023 36d 17-Jun-2023 172d 17-Jun-202...
NEWP
NEWPROJ-3.4.3.3.2 Z3 Structural works 06-Apr-2023 117d 31-Jul-2023 129d 31-Jul-202...
NEWPROJ-3.4.3.3.3 Z3 Hardscape works
NEWP 12-Jul-2023 30d 10-Aug-2023 129d 10-Aug-202...
NEWPROJ-3.4.3.4 Z3 Softscape works
NEWP 19-Jul-2023 23d 10-Aug-2023 129d 10-Aug-202...

NEWPROJ-3.4.4 Zone 4
NEWPR 10-Jul-2023 161d 17-Dec-2023 0d 17-Dec-202...

NEWPROJ-3.4.4.3 Z4 Civil works


NEWP 10-Jul-2023 133d 19-Nov-2023 28d 19-Nov-202...
NEWPROJ-3.4.4.3.1 Z4 MEP works
NEWP 10-Jul-2023 100d 17-Oct-2023 15d 17-Oct-202...
NEW
NEWPROJ-3.4.4.3.1.1 Z4 Mechanical 10-Jul-2023 70d 17-Sep-2023 44d 17-Sep-202...
NEWPROJ-3.4.4.3.1.2 Z4 Electrical
NEW 30-Jul-2023 80d 17-Oct-2023 15d 17-Oct-202...
NEWP
NEWPROJ-3.4.4.3.2 Z4 Structural works 13-Jul-2023 98d 18-Oct-2023 15d 18-Oct-202...
NEWPROJ-3.4.4.3.3 Z4 Hardscape works
NEWP 04-Oct-2023 47d 19-Nov-2023 28d 19-Nov-202...
NEWP
NEWPROJ-3.4.4.1 Water Feature 24-Aug-2023 76d 07-Nov-2023 0d 07-Nov-202...

NEWPROJ-3.4.4.4 Z4 Softscape works


NEWP 10-Nov-2023 38d 17-Dec-2023 0d 17-Dec-202...

Remaining Work Milestone Page 1 of 1 TASK filter: All Activities


Critical Remaining Work summary © Oracle Corporation
Latin District's Bufferzone Project Time Schedule
Activity ID Activity Name Start Original Finish Total Float Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...


NEWPROJ-3 Latin District Summa
NEWPR
01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...
NEWPROJ-3.1 Milestones
NEWPR
A1000 Project Start 01-Jan-2023 0d 0d Project St...
A1015 Zone 1 Engineering Finished 0d 09-Jun-2023 191d Zone 1 Eng...
A1025 Zone 2 Engineering Finished 0d 27-Apr-2023 234d Zone 2 Eng...
A1035 Zone 3 Engineering Finished 0d 10-May-2023 221d Zone 3 Eng...
A1045 Zone 4 Engineering Finished 0d 24-Jul-2023 146d Zone 4 Eng...
A1050 Engineering stage finished 0d 24-Jul-2023 156d Engineerin...
A1060 Zone 1 Finished 0d 20-Sep-2023 88d Zone 1 Fin...
A1070 Zone 2 Finished 0d 20-Jun-2023 180d Zone 2 Fin...
A1080 Zone 3 Finished 0d 10-Aug-2023 129d Zone 3 Fin...
A1090 Zone 4 Finished 0d 17-Dec-2023 0d Zone 4 Fin...
A1100 Project Finish 0d 27-Dec-2023 0d Project Fi...
06-Jan-2023 200d 24-Jul-2023 118d 24-Jul-202...
NEWPROJ-3.2 Engineering
NEWPR
16-Jan-2023 145d 09-Jun-2023 143d 09-Jun-202...
NEWPROJ-3.2.1 Zone 1
NEWPR
NEWPROJ-3.2.1.1 Z1 Hardscape
NEWP 16-Jan-2023 145d 09-Jun-2023 108d 09-Jun-202...
NEWP
NEWPROJ-3.2.1.1.1 Z1 MEP Engineering 31-Jan-2023 130d 09-Jun-2023 88d 09-Jun-202...
A111 Z1 Mechanical Shopdrawing Sub. and Approved 31-Jan-2023 65d 05-Apr-2023 30d Z1 Mechani...
A112 Z1 Electrical Shopdrawing Sub. and Approved 02-Mar-2023 65d 05-May-2023 15d Z1 Electri...
A115 Z1 Mechanical Material Sub. and Approved 06-Apr-2023 35d 10-May-2023 117d Z1 Mechani...

A116 Z1 Electrical Material Sub. and Approved 06-May-2023 35d 09-Jun-2023 88d Z1 Electri...
NEWP
NEWPROJ-3.2.1.1.2 Z1 Civil & Arch. Engineering 16-Jan-2023 115d 10-May-2023 138d 10-May-202...
A113 Z1 Structural Shopdrawing Sub. and Approved 02-Mar-2023 45d 15-Apr-2023 35d Z1 Structu...
A114 Z1 Archtictural Shopdrawing Sub. and Approved 16-Jan-2023 50d 06-Mar-2023 0d Z1 Archtic...
A117 Z1 Structural Material Sub. and Approved 16-Apr-2023 25d 10-May-2023 117d Z1 Structu...

A118 Z1 Archtictural Material Sub. and Approved 07-Mar-2023 25d 31-Mar-2023 178d Z1 Archtic...

NEWPROJ-3.2.1.2 Z1 Softscape
NEWP 01-Apr-2023 40d 10-May-2023 173d 10-May-202...
A1190 Z1 Softscape Shopdrawing Sub. and Approved 01-Apr-2023 25d 25-Apr-2023 165d Z1 Softsca...
A1200 Z1 Softscape Material Sub. and Approved 26-Apr-2023 15d 10-May-2023 173d Z1 Softsca...
06-Jan-2023 112d 27-Apr-2023 206d 27-Apr-202...
NEWPROJ-3.2.2 Zone 2
NEWPR
NEWPROJ-3.2.2.1 Z2 Hardscape
NEWP 06-Jan-2023 112d 27-Apr-2023 180d 27-Apr-202...
NEWP
NEWPROJ-3.2.2.1.1 Z2 MEP Engineering 14-Jan-2023 104d 27-Apr-2023 180d 27-Apr-202...
A180 Z2 Mechanical Shopdrawing Sub. and Approved 14-Jan-2023 65d 19-Mar-2023 196d Z2 Mechani...
A18 Z2 Electrical Shopdrawing Sub. and Approved 18-Jan-2023 65d 23-Mar-2023 180d Z2 Electri...
A1840Z2 Mechanical Material Sub. and Approved 28-Feb-2023 35d 03-Apr-2023 196d Z2 Mechani...

A185 Z2 Electrical Material Sub. and Approved 24-Mar-2023 35d 27-Apr-2023 180d Z2 Electri...

NEWP
NEWPROJ-3.2.2.1.2 Z2 Civil & Arch. Engineering 06-Jan-2023 95d 10-Apr-2023 196d 10-Apr-202...
A182 Z2 Structural Shopdrawing Sub. and Approved 31-Jan-2023 45d 16-Mar-2023 193d Z2 Structu...
A183 Z2 Archtictural Shopdrawing Sub. and Approved 06-Jan-2023 50d 24-Feb-2023 180d Z2 Archtic...

A186 Z2 Structural Material Sub. and Approved 17-Mar-2023 25d 10-Apr-2023 193d Z2 Structu...
A187 Z2 Archtictural Material Sub. and Approved 10-Feb-2023 25d 06-Mar-2023 231d Z2 Archtic...

NEWPROJ-3.2.2.2 Z2 Softscape
NEWP 25-Feb-2023 36d 01-Apr-2023 232d 01-Apr-202...
A1880 Z2 Softscape Shopdrawing Sub. and Approved 25-Feb-2023 25d 21-Mar-2023 232d Z2 Softsca...
A1890 Z2 Softscape Material Sub. and Approved 18-Mar-2023 15d 01-Apr-2023 232d Z2 Softsca...
31-Jan-2023 100d 10-May-2023 193d 10-May-202...
NEWPROJ-3.2.3 Zone 3
NEWPR
NEWPROJ-3.2.3.1 Z3 Hardscape
NEWP 31-Jan-2023 100d 10-May-2023 172d 10-May-202...
NEWP
NEWPROJ-3.2.3.1.1 Z3 MEP Engineering 15-Feb-2023 85d 10-May-2023 172d 10-May-202...
A1900Z3 Mechanical Shopdrawing Sub. and Approved 15-Feb-2023 65d 20-Apr-2023 129d Z3 Mechani...

A19 Z3 Electrical Shopdrawing Sub. and Approved 20-Feb-2023 65d 25-Apr-2023 172d Z3 Electri...

A194 Z3 Mechanical Material Sub. and Approved 01-Apr-2023 35d 05-May-2023 129d Z3 Mechani...
A195 Z3 Electrical Material Sub. and Approved 06-Apr-2023 35d 10-May-2023 172d Z3 Electri...
NEWP
NEWPROJ-3.2.3.1.2 Z3 Civil & Arch. Engineering 31-Jan-2023 55d 26-Mar-2023 208d 26-Mar-202...
A192 Z3 Structural Shopdrawing Sub. and Approved 31-Jan-2023 45d 16-Mar-2023 208d Z3 Structu...
A193 Z3 Archtictural Shopdrawing Sub. and Approved 31-Jan-2023 50d 21-Mar-2023 129d Z3 Archtic...
A196 Z3 Structural Material Sub. and Approved 02-Mar-2023 25d 26-Mar-2023 208d Z3 Structu...
A197 Z3 Archtictural Material Sub. and Approved 02-Mar-2023 25d 26-Mar-2023 201d Z3 Archtic...
NEWPROJ-3.2.3.2 Z3 Softscape
NEWP 22-Mar-2023 36d 26-Apr-2023 207d 26-Apr-202...
A1980 Z3 Softscape Shopdrawing Sub. and Approved 22-Mar-2023 25d 15-Apr-2023 207d Z3 Softsca...
A1990 Z3 Softscape Material Sub. and Approved 12-Apr-2023 15d 26-Apr-2023 207d Z3 Softsca...
07-Mar-2023 140d 24-Jul-2023 115d 24-Jul-202...
NEWPROJ-3.2.4 Zone 4
NEWPR
NEWPROJ-3.2.4.1 Z4 Hardscape
NEWP 07-Mar-2023 140d 24-Jul-2023 71d 24-Jul-202...
NEWP
NEWPROJ-3.2.4.1.1 Z4 MEP Engineering 06-May-2023 80d 24-Jul-2023 15d 24-Jul-202...
A200 Z4 Mechanical Shopdrawing Sub. and Approved 06-May-2023 65d 09-Jul-2023 0d Z4 Mechani...
A20 Z4 Electrical Shopdrawing Sub. and Approved 21-May-2023 65d 24-Jul-2023 15d Z4 Electri...
A204 Z4 Mechanical Material Sub. and Approved 11-May-2023 35d 14-Jun-2023 0d Z4 Mechani...
A205 Z4 Electrical Material Sub. and Approved 26-May-2023 35d 29-Jun-2023 20d Z4 Electri...
NEWP
NEWPROJ-3.2.4.1.2 Z4 Civil & Arch. Engineering 07-Mar-2023 110d 24-Jun-2023 101d 24-Jun-202...
A202 Z4 Structural Shopdrawing Sub. and Approved 16-Apr-2023 45d 30-May-2023 35d Z4 Structu...

A203 Z4 Archtictural Shopdrawing Sub. and Approved 07-Mar-2023 50d 25-Apr-2023 0d Z4 Archtic...
A206 Z4 Structural Material Sub. and Approved 31-May-2023 25d 24-Jun-2023 35d Z4 Structu...
A207 Z4 Archtictural Material Sub. and Approved 26-Apr-2023 25d 20-May-2023 136d Z4 Archtic...
NEWPROJ-3.2.4.2 Z4 Softscape
NEWP 26-Apr-2023 40d 04-Jun-2023 165d 04-Jun-202...
A2080 Z4 Softscape Shopdrawing Sub. and Approved 26-Apr-2023 25d 20-May-2023 165d Z4 Softsca...
A2090 Z4 Softscape Material Sub. and Approved 21-May-2023 15d 04-Jun-2023 165d Z4 Softsca...
07-Mar-2023 175d 28-Aug-2023 108d 28-Aug-202...
NEWPROJ-3.3 Procurement
NEWPR
01-Apr-2023 150d 28-Aug-2023 88d 28-Aug-202...
NEWPROJ-3.3.1 Zone 1
NEWPR
NEWPROJ-3.3.1.1 Z1 Civil works Proc.
NEWP 01-Apr-2023 105d 14-Jul-2023 118d 14-Jul-202...
A1210 Z1 Mechanical Material Supply 11-May-2023 25d 04-Jun-2023 117d Z1 Mechani...
A1220 Z1 Electrical Material Supply 10-Jun-2023 35d 14-Jul-2023 88d Z1 Electri...
A1230 Z1 Structural Material Supply 11-May-2023 40d 19-Jun-2023 117d Z1 Structu...
A1240 Z1 Hardscape Material Supply 01-Apr-2023 45d 15-May-2023 178d Z1 Hardsca...
NEWPROJ-3.3.1.2 Z1 Softscape Proc.
NEWP 04-Aug-2023 25d 28-Aug-2023 88d 28-Aug-202...
A1250 Z1 Softscape Material Supply 04-Aug-2023 25d 28-Aug-2023 88d Z1 Softsca...
07-Mar-2023 87d 01-Jun-2023 196d 01-Jun-202...
NEWPROJ-3.3.2 Zone 2
NEWPR
NEWPROJ-3.3.2.1 Z2 Civil works Proc.
NEWP 07-Mar-2023 87d 01-Jun-2023 189d 01-Jun-202...
A2100 Z2 Mechanical Material Supply 04-Apr-2023 25d 28-Apr-2023 196d Z2 Mechani...
A2110 Z2 Electrical Material Supply 28-Apr-2023 35d 01-Jun-2023 180d Z2 Electri...
A2120 Z2 Structural Material Supply 11-Apr-2023 40d 20-May-2023 193d Z2 Structu...
A2130 Z2 Hardscape Material Supply 07-Mar-2023 45d 20-Apr-2023 231d Z2 Hardsca...
NEWPROJ-3.3.2.2 Z2 Softscape Proc.
NEWP 02-Apr-2023 25d 26-Apr-2023 232d 26-Apr-202...
A2140 Z2 Softscape Material Supply 02-Apr-2023 25d 26-Apr-2023 232d Z2 Softsca...
27-Mar-2023 65d 30-May-2023 198d 30-May-202...
NEWPROJ-3.3.3 Zone 3
NEWPR
NEWPROJ-3.3.3.1 Z3 Civil works Proc.
NEWP 27-Mar-2023 65d 30-May-2023 183d 30-May-202...
A2150 Z3 Mechanical Material Supply 01-May-2023 20d 20-May-2023 129d Z3 Mechani...
A2160 Z3 Electrical Material Supply 06-May-2023 25d 30-May-2023 172d Z3 Electri...
A2170 Z3 Structural Material Supply 27-Mar-2023 40d 05-May-2023 208d Z3 Structu...
A2180 Z3 Hardscape Material Supply 27-Mar-2023 45d 10-May-2023 201d Z3 Hardsca...

Remaining Work Milestone Page 1 of 2 TASK filter: All Activities


Critical Remaining Work summary © Oracle Corporation
Latin District's Bufferzone Project Time Schedule
Activity ID Activity Name Start Original Finish Total Float Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

NEWPROJ-3.3.3.2 Z3 Softscape Proc.


NEWP 27-Apr-2023 25d 21-May-2023 207d 21-May-202...
A2190 Z3 Softscape Material Supply 27-Apr-2023 25d 21-May-2023 207d Z3 Softsca...

NEWPROJ-3.3.4 Zone 4
NEWPR 21-May-2023 95d 23-Aug-2023 110d 23-Aug-202...

NEWPROJ-3.3.4.1 Z4 Civil works Proc.


NEWP 21-May-2023 95d 23-Aug-2023 66d 23-Aug-202...
A2200 Z4 Mechanical Material Supply 15-Jun-2023 25d 09-Jul-2023 45d Z4 Mechani...
A2205 Z4 Water Feature Material Supply 20-Jul-2023 35d 23-Aug-2023 0d Z4 Water ...
A2210 Z4 Electrical Material Supply 30-Jun-2023 25d 24-Jul-2023 20d Z4 Electri...
A2220 Z4 Structural Material Supply 25-Jun-2023 25d 19-Jul-2023 35d Z4 Structu...
A2230 Z4 Hardscape Material Supply 21-May-2023 25d 14-Jun-2023 136d Z4 Hardsca...
NEWPROJ-3.3.4.2 Z4 Softscape Proc.
NEWP 05-Jun-2023 25d 29-Jun-2023 165d 29-Jun-202...
A2240 Z4 Softscape Material Supply 05-Jun-2023 25d 29-Jun-2023 165d Z4 Softsca...
01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...
NEWPROJ-3.4 Construction
NEWPR
NEWPROJ-3.4.5 Preliminary works
NEWPR 01-Jan-2023 361d 27-Dec-2023 0d 27-Dec-202...

A1260 Mobilization 01-Jan-2023 5d 05-Jan-2023 10d Mobilizati...


A1270 Demobilization 18-Dec-2023 10d 27-Dec-2023 0d Demobiliza...

NEWPROJ-3.4.1 Zone 1
NEWPR 16-May-2023 128d 20-Sep-2023 88d 20-Sep-202...

NEWPROJ-3.4.1.1 Z1 Civil works


NEWP 16-May-2023 103d 26-Aug-2023 113d 26-Aug-202...
NEWPROJ-3.4.1.1.1 Z1 MEP works
NEWP 16-May-2023 85d 08-Aug-2023 88d 08-Aug-202...
NEWPROJ-3.4.1.1.1.1 Z1 Mechanical
NEW 16-May-2023 52d 06-Jul-2023 120d 06-Jul-202...
A1 Z1 Sewage Network 16-May-2023 45d 29-Jun-2023 117d Z1 Sewage ...
A1 Z1 Storm Network 23-May-2023 45d 06-Jul-2023 117d Z1 Storm N...
A1 Z1 Water Network 26-May-2023 35d 29-Jun-2023 122d Z1 Water N...
A1 Z1 Irrigation Network 31-May-2023 35d 04-Jul-2023 122d Z1 Irrigat...
A1 Z1 Firefighting Network 05-Jun-2023 30d 04-Jul-2023 122d Z1 Firefig...
NEWPROJ-3.4.1.1.1.2 Z1 Electrical
NEW 27-Jun-2023 43d 08-Aug-2023 88d 08-Aug-202...
A1 Z1 LV Network 27-Jun-2023 33d 29-Jul-2023 88d Z1 LV Netw...
A1 Z1 Earthing & Connecting 05-Jul-2023 35d 08-Aug-2023 88d Z1 Earthin...
NEWP
NEWPROJ-3.4.1.1.2 Z1 Structural works 31-May-2023 83d 21-Aug-2023 88d 21-Aug-202...
A135 Z1 Retaining walls 31-May-2023 35d 04-Jul-2023 117d Z1 Retaini...
A136 Z1 Backfilling & Grading 06-Jul-2023 35d 09-Aug-2023 88d Z1 Backfil...
A137 Z1 Stairs 10-Aug-2023 12d 21-Aug-2023 88d Z1 Stairs
NEWP
NEWPROJ-3.4.1.1.3 Z1 Hardscape works 30-Jul-2023 28d 26-Aug-2023 113d 26-Aug-202...
A138 Z1 Hardscape finishing works 30-Jul-2023 25d 23-Aug-2023 88d Z1 Hardsca...
A139 Z1 Site Furniture 20-Aug-2023 7d 26-Aug-2023 113d Z1 Site Fu...
NEWPROJ-3.4.1.2 Z1 Softscape works
NEWP 29-Aug-2023 23d 20-Sep-2023 88d 20-Sep-202...
A1400 Z1 Palms, Trees & Ground cover 29-Aug-2023 20d 17-Sep-2023 88d Z1 Palms, ...
A2280 Z1 Final Survey for Softscape 18-Sep-2023 3d 20-Sep-2023 88d Z1 Final S...
04-Apr-2023 78d 20-Jun-2023 180d 20-Jun-202...
NEWPROJ-3.4.2 Zone 2
NEWPR
NEWPROJ-3.4.2.3 Z2 Civil works
NEWP 04-Apr-2023 76d 18-Jun-2023 182d 18-Jun-202...
NEWPROJ-3.4.2.3.1 Z2 MEP works
NEWP 04-Apr-2023 67d 09-Jun-2023 180d 09-Jun-202...
NEWPROJ-3.4.2.3.1.1 Z2 Mechanical
NEW 04-Apr-2023 50d 23-May-2023 196d 23-May-202...
A1 Z2 Sewage Network 04-Apr-2023 45d 18-May-2023 196d Z2 Sewage ...
A1 Z2 Storm Network 11-Apr-2023 35d 15-May-2023 201d Z2 Storm N...
A1 Z2 Water Network 14-Apr-2023 35d 18-May-2023 196d Z2 Water N...
A1 Z2 Irrigation Network 19-Apr-2023 35d 23-May-2023 196d Z2 Irrigat...
A1 Z2 Firefighting Network 14-Apr-2023 30d 13-May-2023 206d Z2 Firefig...
NEWPROJ-3.4.2.3.1.2 Z2 Electrical
NEW 05-May-2023 36d 09-Jun-2023 180d 09-Jun-202...
A1 Z2 LV Network 05-May-2023 33d 06-Jun-2023 180d Z2 LV Netw...
A1 Z2 Earthing & Connecting 06-May-2023 35d 09-Jun-2023 180d Z2 Earthin...
NEWP
NEWPROJ-3.4.2.3.2 Z2 Structural works 21-Apr-2023 51d 10-Jun-2023 180d 10-Jun-202...
A148 Z2 Retaining walls 21-Apr-2023 35d 25-May-2023 193d Z2 Retaini...
A149 Z2 Backfilling & Grading 07-May-2023 35d 10-Jun-2023 180d Z2 Backfil...
NEWP
NEWPROJ-3.4.2.3.3 Z2 Hardscape works 22-May-2023 28d 18-Jun-2023 182d 18-Jun-202...
A15 Z2 Hardscape finishing works 22-May-2023 25d 15-Jun-2023 180d Z2 Hardsca...
A152 Z2 Site Furniture 12-Jun-2023 7d 18-Jun-2023 182d Z2 Site Fu...
NEWPROJ-3.4.2.4 Z2 Softscape works
NEWP 29-May-2023 23d 20-Jun-2023 180d 20-Jun-202...
A1530 Z2 Palms, Trees & Ground cover 29-May-2023 20d 17-Jun-2023 180d Z2 Palms, ...
A1630 Z2 Final Survey for Softscape 18-Jun-2023 3d 20-Jun-2023 180d Z2 Final S...
06-Apr-2023 127d 10-Aug-2023 129d 10-Aug-202...
NEWPROJ-3.4.3 Zone 3
NEWPR
NEWPROJ-3.4.3.3 Z3 Civil works
NEWP 06-Apr-2023 127d 10-Aug-2023 129d 10-Aug-202...
NEWPROJ-3.4.3.3.1 Z3 MEP works
NEWP 01-May-2023 90d 29-Jul-2023 130d 29-Jul-202...
NEWPROJ-3.4.3.3.1.1 Z3 Mechanical
NEW 01-May-2023 90d 29-Jul-2023 129d 29-Jul-202...
A1 Z3 Sewage Network 01-May-2023 45d 14-Jun-2023 129d Z3 Sewage ...
A1 Z3 Storm Network 11-May-2023 45d 24-Jun-2023 161d Z3 Storm N...
A1 Z3 Water Network 16-May-2023 35d 19-Jun-2023 129d Z3 Water N...
A1 Z3 Irrigation Network 25-Jun-2023 35d 29-Jul-2023 129d Z3 Irrigat...
A1 Z3 Firefighting Network 21-May-2023 30d 19-Jun-2023 169d Z3 Firefig...
NEWPROJ-3.4.3.3.1.2 Z3 Electrical
NEW 13-May-2023 36d 17-Jun-2023 172d 17-Jun-202...
A1 Z3 LV Network 13-May-2023 33d 14-Jun-2023 172d Z3 LV Netw...
A1 Z3 Earthing & Connecting 13-May-2023 36d 17-Jun-2023 172d Z3 Earthin...
NEWP
NEWPROJ-3.4.3.3.2 Z3 Structural works 06-Apr-2023 117d 31-Jul-2023 129d 31-Jul-202...
A16 Z3 Retaining walls 06-Apr-2023 35d 10-May-2023 208d Z3 Retaini...
A162 Z3 Backfilling & Grading 22-Jun-2023 40d 31-Jul-2023 129d Z3 Backfil...
NEWP
NEWPROJ-3.4.3.3.3 Z3 Hardscape works 12-Jul-2023 30d 10-Aug-2023 129d 10-Aug-202...
A164 Z3 Hardscape finishing works 12-Jul-2023 25d 05-Aug-2023 129d Z3 Hardsca...
A165 Z3 Site Furniture 04-Aug-2023 7d 10-Aug-2023 129d Z3 Site Fu...
NEWPROJ-3.4.3.4 Z3 Softscape works
NEWP 19-Jul-2023 23d 10-Aug-2023 129d 10-Aug-202...
A1660 Z3 Palms, Trees & Ground cover 19-Jul-2023 20d 07-Aug-2023 129d Z3 Palms, ...
A2260 Z2 Final Survey for Softscape 08-Aug-2023 3d 10-Aug-2023 129d Z2 Final S...
10-Jul-2023 161d 17-Dec-2023 0d 17-Dec-202...
NEWPROJ-3.4.4 Zone 4
NEWPR
NEWPROJ-3.4.4.3 Z4 Civil works
NEWP 10-Jul-2023 133d 19-Nov-2023 28d 19-Nov-202...
NEWPROJ-3.4.4.3.1 Z4 MEP works
NEWP 10-Jul-2023 100d 17-Oct-2023 15d 17-Oct-202...
NEWPROJ-3.4.4.3.1.1 Z4 Mechanical
NEW 10-Jul-2023 70d 17-Sep-2023 44d 17-Sep-202...
A1 Z4 Sewage Network 10-Jul-2023 45d 23-Aug-2023 44d Z4 Sewage ...
A1 Z4 Storm Network 17-Jul-2023 45d 30-Aug-2023 59d Z4 Storm N...
A1 Z4 Water Network 04-Aug-2023 35d 07-Sep-2023 44d Z4 Water N...
A1 Z4 Irrigation Network 09-Aug-2023 35d 12-Sep-2023 44d Z4 Irrigat...
A1 Z4 Firefighting Network 14-Aug-2023 35d 17-Sep-2023 44d Z4 Firefig...
NEWPROJ-3.4.4.3.1.2 Z4 Electrical
NEW 30-Jul-2023 80d 17-Oct-2023 15d 17-Oct-202...
A1 Z4 LV Network 30-Jul-2023 65d 02-Oct-2023 15d Z4 LV Netw...
A1 Z4 Earthing & Connecting 12-Sep-2023 36d 17-Oct-2023 15d Z4 Earthin...
NEWP
NEWPROJ-3.4.4.3.2 Z4 Structural works 13-Jul-2023 98d 18-Oct-2023 15d 18-Oct-202...
A174 Z4 Retaining walls 13-Jul-2023 35d 16-Aug-2023 75d Z4 Retaini...
A175 Z4 Backfilling & Grading 05-Aug-2023 75d 18-Oct-2023 15d Z4 Backfil...
NEWP
NEWPROJ-3.4.4.3.3 Z4 Hardscape works 04-Oct-2023 47d 19-Nov-2023 28d 19-Nov-202...
A177 Z4 Hardscape finishing works 04-Oct-2023 35d 07-Nov-2023 0d Z4 Hardsca...
A178 Z4 Site Furniture 13-Nov-2023 7d 19-Nov-2023 28d Z4 Site Fu...
NEWPROJ-3.4.4.1 Water Feature
NEWP 24-Aug-2023 76d 07-Nov-2023 0d 07-Nov-202...
A2250 Water Feature & Pump Room 24-Aug-2023 45d 07-Oct-2023 0d Water Feat...
A2290 Water Feature Final fix & Finishing 08-Oct-2023 31d 07-Nov-2023 0d Water Feat...
NEWPROJ-3.4.4.4 Z4 Softscape works
NEWP 10-Nov-2023 38d 17-Dec-2023 0d 17-Dec-202...
A1790 Z4 Palms, Trees & Ground cover 10-Nov-2023 35d 14-Dec-2023 0d Z4 Palms, ...
A2270 Z2 Final Survey for Softscape 15-Dec-2023 3d 17-Dec-2023 0d Z2 Final S...