Activity ID Activity Name Original Duration Total Float 2023

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
31-Aug-23, (New Project)
(New Project)
275 0

31-Aug-23, VILLANO.0060
VILLA NO.0060
275 0

23 0 27-Oct-22, Substructural Works


Substructural Works
M2-3C-B68-60-SB-2 Earth Work 8 0 Earth Work

M2-3C-B68-60-SB-4 Raft Foundation Work 15 0 Raft Foundation Work

125 13 22-Mar-23, Superstructural Works


Superstructural Works
M2-3C-B68-60-SS-6 Column Work GF 15 0 Column Work GF

M2-3C-B68-60-SS-8 Slab & MEP GF 21 0 Slab & MEP GF

M2-3C-B68-60-SS-12 Column Work FF 15 0 Column Work FF


M2-3C-B68-60-SS-10 Masoanry Works GF 14 19 Masoanry Works GF
M2-3C-B68-60-SS-14 Slab & MEP FF 21 0 Slab & MEP FF
M2-3C-B68-60-SS-18 Column Work RF 15 13 Column Work RF
M2-3C-B68-60-SS-16 Masoanry Works FF 14 0 Masoanry Works FF
M2-3C-B68-60-SS-20 Slab & MEP RF 16 13 Slab & MEP RF
M2-3C-B68-60-SS-22 Masoanry Works RF 14 13 Masoanry Works RF
159 0 27-Aug-23,Articture Works
Articture Works
M2-3C-B68-60-RF-24 Plaster Work 52 0 Plaster Work
M2-3C-B68-60-RF-26 Paint First Coat 25 0 Paint First Coat
M2-3C-B68-60-RF-28 Walls Tiles ( WetArea ) 15 0 Walls Tiles ( WetArea )
M2-3C-B68-60-RF-30 Waterproofing for ( Wet Area ) 10 0 Waterproofing for ( Wet Area )
M2-3C-B68-60-RF-32 Flooring Works 25 0 Flooring Works
M2-3C-B68-60-RF-34 Stairs & Handril Work 15 17 Stairs & Handril Work
M2-3C-B68-60-RF-38 Waterproofing for Roof 10 2 Waterproofing for Roof
M2-3C-B68-60-LF-40 Doors Work 12 0 Doors Work
M2-3C-B68-60-LF-36 Windows Work 12 0 Windows Work
M2-3C-B68-60-LF-42 Paint Final Coat 10 0 Paint Final Coat
70 2 13-Aug-23, External Works
External Works
M2-3C-B68-60-PF-44 External Plaster 25 5 External Plaster
M2-3C-B68-60-SD-46 Site Development Works & MEP 12 5 Site Development Works & MEP
M2-3C-B68-60-PF-48 External Paint 10 2 External Paint
166 12 01-Aug-23, MEP Works
MEP Works
M2-3C-B68-60-2F-50 MEP 1ST FIX - GF 10 19 MEP 1ST FIX - GF
M2-3C-B68-60-2F-52 MEP 1ST FIX - FF 12 103 MEP 1ST FIX - FF
M2-3C-B68-60-2F-54 MEP 1ST FIX - RF 10 80 MEP 1ST FIX - RF
M2-3C-B68-60-FF-56 Final Fix For MEP 10 12 Final Fix For MEP
149 5 26-Jul-23, External Facilities
External Facilities
M2-3C-B68-60-FS-58 Fence & Driver Room Skelaton 35 85 Fence & Driver Room Skelaton
M2-3C-B68-60-SD-60 Underground Tank 24 85 Underground Tank
M2-3C-B68-60-FF-62 Fence Finishes Lights & Driver Room Finishes 30 5 Fence Finishes Lights & Driver Room Finishes
4 0 31-Aug-23, Handing Over
Handing Over
M2-3C-B68-60-TC-64 Testing & Commissioning 2 0 Testing & Commissioning
M2-3C-B68-60-HH-66 Handing Over of Villa 2 0 Handing Over of Villa

Actual Level of Effort Remaining Work summary UPDATE SCHEDULE


(New Project) Date Revision Checked Approved
Primary Baseline Critical Remaining Work
UPDATE TIME SCHEDULE - 02-Oct-22 Planning Engineer Project Manager
Actual Work Milestone
Page 1 of 1 Eng / QUSAI ABUKHADRA Eng. / TAMIR SAMIR