SHAFAQ AL GROUP UNITED L.L.

C
Client : - M/S L& T

Project :- VIBE STEAK HOUSE-CITY HOTELS-MUSCAT

BILL OF QUANTITY
PREPARED:- S.SUNDARAMOORTHY CHECKED:- ANEESH KUMAR.E.R DATE:- 24.08.17

SIZE QTY NO OF
(NO'S) WEIGHT PLATES
SI.NO DESCRIPTION MATERIAL LENGTH WIDTH THK
(in or Wt. (IN TON) REQUIRE
(in 'MM') (in 'MM') 'MM') per M D

BASE PLATE

1 BASE PLATE PLATE 250 250 16 14 0.11 0.0729

2 END PLATE PLATE 158 158 10 14 0.03 0.0291

3 CLEAT PLATE 332 82 10 56 0.12 0.1270

COLUMN'S FOR BIBE STEAK HOUSE - 14 NO'S

COLUMN-(UC-152X152X30)
1 (FOR LEVEL 3MTO10.4-3NO'S)
UC 24000 - - 30 0.72 -

2 COLUMN-(UC-152X152X30) UC 75000 - - 30 2.25 -


TIE BEAM - MB1-
3 (UB 356X171X45)
UB 58000 - - 45 2.61 -
TIE BEAM - MB2-
4 (UB 305X127X27)
UB 165000 - - 45 7.43 -

TOTAL Wt. in TON 13.26


TOTAL Wt. WITH MARGIN 5 % 13.93
FOUNDATION BOLT
ANCHOR BOLT -M16- 'J'
1 J' TYPE 550 - - 56 56 NO'S
TYPE

2 NUT-M16 NUT - - - 56 56 NO'S

3 LOCK NUT-M16 NUT - - - 56 56 NO'S

4 BOLT-M16-GR-8.8 BOLT 25 - - 170 170 NO'S

5 NUT NUT - - - 170 170 NO'S

6 WASHER WASHER - - - 340 340 NO'S

Project :- CITY HOLTES-MUSCAT


TOTAL Wt. OF STEEL 13.9 TON
SHAFAQ AL GROUP UNITED L.L.C
Client : - M/S L& T OMAN LLC

Project :- AQUA PANEL SUPPORT-CITY HOTELS-MUSCAT

BILL OF QUANTITY
PREPARED:- S.SUNDARAMOORTHY CHECKED:- NIKHIL VARKEY DATE:- 05.09.17

SIZE TOTAL
QTY Wt. Per WEIGHT M^2 OR CONSIDERING
SI.NO DESCRIPTION MATERIAL LENGTH WIDTH THK
(in (NO'S) 'M' (IN TON) RUNNING WASTAGE
(in 'MM') (in 'MM') 'MM') METER

BASE PLATE

1 BASE PLATE PLATE 350 350 12 20 - 0.23 2.45 2.98

2 SIDE PLATE PLATE 175 350 12 40 - 0.23 2.45 2.98

3 CONNECTING PLATE PLATE 175 350 12 36 - 0.21 2.21 2.98

TOTAL Wt. in TON & AREA IN M^2 0.67 7.11 8.94

TOTAL Wt. in TON (CONSIDERING WASTAGE) 0.84 - -

COLUMN'S & TIE BEAMS FOR AQUA PANNEL SUPPORT

1 COLUMN-(UC-254X254X73) UC 2900 - - 20 73 4.23 58.00 60.00

PRIMARY BEAM-
2 (UC-254X254X73)
UC 8550 - - 9 73 5.62 76.95 108.00

TOTAL Wt. in TON & RUNNING METER IN 'M' 9.85 134.95 168.00

TOTAL Wt. in TON (CONSIDERING WASTAGE) 12.26 - -

3 TIE BEAM-(RHS-200X100X8) RHS 9000 - - 44 35.1 13.90 396.0 528.00

TIE BEAM-(RHS-200X100X8)
4 (8550X4NO'S)
RHS 8550 - - 4 35.1 1.20 34.20 48.00

TOTAL Wt. in TON & RUNNING METER IN 'M' 15.10 430.20 576.00
TOTAL Wt. in TON (CONSIDERING WASTAGE) 20.22 - -
FOUNDATION BOLT

1 BOLT -M16 ROD 550 - - 40 - 40 NO'S

2 NUT-M16 NUT - - - 80 - 80 NO'S

3 WASHER-M16' NUT - - - 80 - 80 NO'S

4 BOLT-M16-GR-8.8 BOLT 50 - - 110 - 110 NO'S


(TENTATIVELY)

5 NUT (TENTATIVELY) NUT - - - 110 - 110 NO'S

6 WASHER (TENTATIVELY) WASHER - - - 220 - 220 NO'S

BOLT-M16-GR-8.8-HILTY HIT-
7 BOLT 50 - - 64 - 64 NO'S
V WITH HILTY HIT-RE 500V3

Project :- AQUA PANNEL SUPPORT-CITY HOLTES-MUSCAT


ACTUAL WT. OF STEEL 25.6 TON

TOTAL OF STEEL (CONSIDERING WASTAGE) 33.3 TON

TOTAL RUNNING METER OF UC(254X254X73) 168.0 M

TOTAL RUNNING METER OF RHS(200X100X8) 576.0 M


SHAFAQ AL GROUP UNITED L.L.C

Client : - M/S L& T

Project :- AQUA PANEL SUPPORT-CITY HOTELS-MUSCAT

CONSOLIDATED BOQ

PREPARED:- S.SUNDARAMOORTHY CHECKED:- NIKHIL VARKEY DATE:- 05.09.17

WITH NO OF
Wt. (IN AREA
SI.NO DESCRIPTION THK TON)
MARIGIN
(IN 'M^2')
PLATES
8% REQUIRED

COLUMN & RAFETER FOR GRID 2 TO 10

1 PLATE 12 0.67 0.72 7.67 0.64

TOTAL WT. In TON 0.67 0.72

COLUMN

1 UC-254X254X73 Lg. in 'M' #REF! #REF! - #REF!

ROOF SHEET-SANWICH PANEL-50THK


Area in
1 ROOFING-SANDWICH PANEL-50THK 3191 3446 - -
'M^2'
Area in
2 SIDE CLADDING-SANDWICH PANEL-50THK 1670 1804 - -
'M^2'
LAPPED GIRTS

1 LAPPED GIRTS-252 Z 2.5THK Lg. in 'M' 945 1021 - -

SAG ROD - Ø12

1 SAG ROD - Ø12 Lg. in 'M' 336 363 - -

BRACING PIPE - Ø114.3 X 3.2THK

1 PIPE-Ø114.3 X 3.2THK Lg. in 'M' 375 405 - -


``