ATTACHMENT I
1 CIVIL/STRUCTURAL
1.1 Soil Excavation
Excavation including, but not limited, to shoring, dewatering, hauling and disposal of
unsuitable or unneeded materials at a dump site.
1.1.1 Non-Rock, by hand
1.1.2 Non-Rock, by machine.
1.1.3 Rock, by machine or blasting.
1.2 Backfilling & Compaction
Provide back-filling material from a Saudi Aramco approved source, including cost of
material if any, loading & transporting irrespective of distance from jobsite, handling, placing,
compaction in layers 15 to 30 cm as required regardless of the method used, and testing.
This work shall include, but is not limited to, complete installation of vehicle or camel
crossings over pipelines in accordance with Standard Drawing AC-36660, Sheet 4. Including
installation as pipe protection, anode installation for casing. Crossing shall be 5m wide with
1m covers over the pipe and capped with 150mm layer of compacted marl.
This work shall include, but is not limited to, complete installation of road crossings including
installation of detour roads, installation of warning signs, excavation, installation of pipe and
protection (FBE coated steel casing or reinforced concrete slab), anode installation, backfill
and compaction, hydrostatic testing and re-paving the road.
Open Cut
1.14.8 4”-6”
1.14.9 8"-10"
1.14.10 12"-16"
1.14.11 18"-20"
1.14.12 20"-24"
1.14.13 26"-30"
1.14.14 32"-48"
2 PIPING
2.2 Underground Piping
Provide & install underground carbon steel piping including, but not limited to survey, ditch
excavation including rock, sand or subkha padding, bending, welding, lowering-in,
backfilling, tie-in where applicable, pre-heating & post weld heating if required, cleaning,
coating, painting and hydro testing. . Different Wall Thickness
Normal Soil
2.2.1 2”
2.2.2 4”
2.2.3 6”
2.2.4 8”
2.2.5 10”
2.2.6 12”
2.2.7 20”
2.2.8 24”
2.2.9 32”
2.2.10 40"
2.2.11 42”
2.2.12 48”
Rock
2.2.13 2”
2.2.14 4”
2.2.15 6”
2.2.16 8”
2.2.17 10”
2.2.18 12”
2.2.19 20”
2.2.20 24”
2.2.21 32”
2.2.22 40"
2.2.23 42”
2.2.24 48”
Subkha
2.2.25 2”
2.2.26 4”
2.2.27 6”
2.2.28 8”
2.2.29 10”
2.2.30 12”
2.2.31 20”
2.2.32 24”
2.2.33 32”
2.2.34 40"
2.2.35 42"
2.2.36 48"
1 LABOR RATES
1.1 Construction Manager
1.2 Construction Superintendent
1.3 General Foreman
1.4 Craft Foreman – Civil
1.8 Sheet Metal Fabricator
1.9 Fabricator Steel
1.12 Certified Structural Welder
1.13 Welder Helper
1.22 Ironworker
1.23 Carpenter
1.26 Rigger
1.28 Mason
1.29 Rebarman
1.30 Scaffolder
1.31 Survey Party Chief
1.32 Material Man
1.33 Labor, Skilled
1.34 Laborer, Non-skilled
1.36 Light Equipment Operator
1.37 Heavy Equipment Operator
1.38 Crane Operator
1.39 QA/QC Inspector
1.40 QA/QC Engineer
1.41 Project Engineer
1.42 Discipline Engineer
1.45 Safety Engineer
1.49 CADD Operator complete with work station *
1.50 Draftsman
1.51 Work Permit Receiver
1.52 Scaffolding Supervisor
1.53 Certified Scaffolder
1.54 Technician
* Rate to include complete CADD Systems inclusive of all required equipment and
consumables.
3 EQUIPMENT RATES
3.1 LIGHT VEHICLE
3.1.1 Pick-Up Truck - ¾ Ton 4 x 2
3.1.2 Carry All – ¾ ton 4 x 2
3.2 LIGHT TRUCKS
3.2.1 Flatbed Truck - 5 Tons
3.2.2 Flatbed Truck - 10 Tons
3.2.3 Flatbed Truck C/W Crane - 3 Tons
3.3 HEAVY DUTY TRUCK
3.3.1 Dump Truck - 5 C.M.
3.3.2 Dump Truck - 15 C.M.
3.3.3 Dump Truck - 20 C.M.
3.3.4 Tractor Unit - 4 x 2
3.3.5 Tractor Unit - 6 x 4
3.4 TANKERS
3.4.1 Water - 22,700 Liters with Pump (6,000 GAL)
3.4.2 Water - 37,800 Liters with Pump (10,000 GAL)
3.4.3 Vacuum - 22,700 Liters (6,000 GAL)
3.5 TRAILERS
3.5.1 Flatbed - 50 Tons with Tractor
3.5.2 Lowboy - 100 Tons with Tractor
3.5.3 Lowboy - 200 Tons with Tractor
3.6 FRONT END LOADERS
3.6.1 Bobcat
3.6.2 Backhoe/Excavator
3.6.3 Cat D8 or Equivalent
3.6.4 Cat D9 or Equivalent
3.6.5 Cat 950 or Equivalent
3.6.6 Cat 966 or Equivalent
3.6.7 Cat 980 or Equivalent
3.6.8 Cat with Rock Drill
3.7 COMPACTORS
3.7.1 Vibratory Plate
3.7.2 Jumping Jack
3.7.3 Trench Roller - Self Propelled - 2 Tons
3.7.4 Vibratory Roller - 10 Tons
3.7.5 Vibratory Roller - 20 Tons
3.9 CRANES
(Including minimum of two (2) sets of rigging for each crane comprising a total of
eight (8) slings and eight (8) shackles per crane, lengths and strengths compatible
with crane capacity and reach)
3.9.1 18 Tons – Grove or Equivalent
3.9.2 35 Tons – Grove or Equivalent
3.9.3 55 Tons –Grove or Equivalent
3.9.4 80 Tons – Grove or Equivalent
3.9.5 140 Tons – Grove or Equivalent
3.9.6 300 Tons – Grove or Equivalent
3.1 COMPRESSORS AND TOOLS
3.10.3 Diesel-750 CFM w/Filter and Oiler ACC w/100 ft hose
3.10.5 Jackhammer - 65 lbs min with breaking tools and 100 ft. length hose including
coupling
3.10.8 Portable Fan Blower/Exhauster, 11,000 CFM and 100 ft. of hose
3.10.9 Additional 100 ft length hose for items 10.3
3.10.10 Additional 100 ft length hose for items 10.5, and 10.8
3.11.7 Wellpoint Dewatering System, 3” header and 6 wellpoints at 10 ft on center x 22 ft
deep, complete with vacuum pump to deliver 5 psi absolute pressure
3.12 WELDING/CUTTING EQUIPMENT
3.12.1 Diesel - 300 AMPS w/200 ft of Leads
3.12.2 Diesel - 400 AMPS w/200 ft of Leads
3.12.3 Tig Welding Set complete with accessories including, but not limited to, gas
3.12.4 Air Arc Cutting Equipment Set
3.12.5 Oxy/Acetylene Cutting Set complete with accessories including, but not limited to,
gauges, gases, bottle rack, cutting torch
3.12.6 Stress Relief, Heat Blankets and Power Supply
3.12.7 Grinder, pedestal – 6 in.
3.12.8 Grinder, pedestal – 12 in.
3.12.9 Grinder, electric – 6 in.
3.13 FLOODLIGHTS/LTG EQUIPMENT
3.13.1 Portable Diesel Light Tower, 5 to 9 kW
3.13.2 Portable Diesel Light Tower, 10 to 25 kW
3.13.3 Portable Diesel Light Tower, 26 to 50 kW
3.14 PILE DRIVING EQUIPMENT
3.14.1 Pile Driving Hammer, Steam or Air, 4150 ft-lb @225 BPM
3.14.2 Pile Driving Hammer, Steam or Air, 15,000 ft-lb @ 60 BPM
3.14.3 Pile Driving Hammer, Steam or Air, 24,450 ft-lb @ 111 BPM
3.14.4 Diesel Type Hammer, 22,400 ft-lb
3.14.5 Diesel Type Hammer, 41,300 ft-lb
3.15 CONCRETE EQUIPMENT
3.15.1 Concrete Pump, Truck Mounted, 4” Line, 80’ Boom
3.15.2 Concrete Mixer, 6 cu ft
3.15.3 Ready Mix Truck
3.15.4 Concrete Vibrator
3.15.5 Concrete Finisher
3.15.6 Curbing Machine
3.17 GENERATOR SETS COMPLETE WITH CONTROL PANEL, TANKS
3.17.1 10 kW
3.17.2 60 kW
3.17.3 100 - 150 kW
3.17.4 400 - 600 kW
3.18 TOOLS/EQUIPMENT MISC.
3.18.1 Rebar Bender
3.18.2 Rebar Shear
3.18.3 Torque Wrenches 8000 PSI with Full Rangee Sockets 3/4" Drive
3.18.4 Impact Wrenches 1/2" Drive with Full range of Sockets (Imperial 1-3/8" to 4-3/4"
Metric 41 mm - 135mm)
3.18.7 Chain Hoist (up to 1-1/2 tons)
3.18.8 Come-A-Long (up to 1-1/2 tons)
3.18.18 Scaffolding (Bay 6'X6'X6-1/2')
5 The Labor Rates for the design, procurement and support personnel and Software
are:
5.1 DESIGN PERSONNEL
5.1.1 Project Manager
5.1.2 Senior / Lead Engineer
5.1.3 Discipline Engineer
5.1.4 Specialist Engineer
5.1.5 Senior Designer
5.1.6 Designer
5.1.7 Senior Draftsman
5.1.8 Draftsman
5.1.9 CADD Operator w/complete work station*
5.2 PROCUREMENT PERSONNEL
5.2.1 Buyer
5.2.2 QA/QC Engineer
5.2.3 Senior Inspector
5.2.4 Expediter
5.2.5 Traffic Coordinator
5.2.6 Senior Materials Engineer
5.2.7 Materials Engineer
5.2.8 Materials Control/Coordinator
5.2.9 Spare Parts Coordinator
5.3 SUPPORT PERSONNEL
5.3.1 Senior Secretary
5.3.2 Secretary
5.3.3 Document Control Clerk
5.3.4 Clerk
5.3.5 IT Specialist
DISCIPLINE:
PAY ITEM NO. DESCRIPTION OF ITEM UOM Estimated Quantity Unit Rate Total Amount REMARKS
2.2 FOUNDATION
2.2.1 Full Thrust Anchor ( 4-units )
Estimated
PAY ITEM NO. DESCRIPTION OF ITEM UOM Unit Rate Total Amount REMARKS
Quantity
2.2 BACKFILL
2.2.2 Structural Supports,Platforms,Pipe Supports & others
PAY ITEM NO. DESCRIPTION OF ITEM UOM Estimated Quantity Unit Rate Total Amount
Estimated
PAY ITEM NO. DESCRIPTION OF ITEM UOM Unit Rate Total Amount
Quantity
Estimate
Unit
PAY ITEM NO. DESCRIPTION OF ITEM UOM d Total Amount
Rate
Quantity
2.2 REINFORCEMENT
2.2.5 Structural Supports,Platforms,Pipe Supports & others
2.2.5.1 Reinforcement works tons 279.91 4718.12 1,320,639.83
---- Nothing Follows ----
Sub-Total - - - 1,320,640
PROJECT : Mazalij Pipelines 3000548992 BIDDER :
SUBJECT : SCHEDULE OF QUANTITIES AND PRICES DATE :
OWNER : SAUDI ARAMCO SIGNATURE : AUM
DISCIPLINE:
Estimated
PAY ITEM NO. DESCRIPTION OF ITEM UOM Unit Rate Total Amount
Quantity
Estimated
PAY ITEM NO. DESCRIPTION OF ITEM UOM Unit Rate Total Amount
Quantity
NOTE: ROW price does not include Maintenance & Repair of the ROW during the construction period
PROJECT : Mazalij Pipelines 3000548992 BIDDER :
SUBJECT : SCHEDULE OF QUANTITIES AND PRICES DATE :
OWNER : SAUDI ARAMCO SIGNATURE : AUM
DISCIPLINE:
Estimated
PAY ITEM NO. DESCRIPTION OF ITEM UOM Unit Rate Total Amount REMARKS
Quantity
PAY ITEM NO. DESCRIPTION OF ITEM Estimated Quantity UOM Unit Rate Total Amount REMARKS
using
3.6.2 Backfill Regular 19,612.50 CM 18.33 359,400.87 excavated
material
3.6.3 Compacted Marl 5,883.75 CM 47.34 278,522.90
3.6.4 Guardrail /Crash Barrier 207.00 lm 1,067.60 220,993.06
---- Nothing Follows ----
Sub-Total - - - 946,594
PROJECT : Mazalij Pipelines 3000548992 BIDDER :
SUBJECT : SCHEDULE OF QUANTITIES AND PRICES DATE :
OWNER : SAUDI ARAMCO SIGNATURE : AUM
DISCIPLINE:
PAY ITEM NO. DESCRIPTION OF ITEM Estimated Quantity UOM Unit Rate Total Amount REMARKS
Estimated
PAY ITEM NO. DESCRIPTION OF ITEM UOM Unit Rate Total Amount REMARKS
Quantity
Estimated
PAY ITEM NO. DESCRIPTION OF ITEM UOM Unit Rate Total Amount REMARKS
Quantity
3.11 Crossing
3.11.1 Camel Crossing 132.00 Each 53,109.39 7,010,439.69
3.11.2 Marl Road Crossing 109.00 Each 37,163.73 4,050,846.95 open cut only
3.11.3 Pipeline crossing 134.00 Each 47,640.02 6,383,762.32 open cut only
---- Nothing Follows ----
Sub-Total - 17,445,049
PROJECT : Mazalij Pipelines 3000548992 BIDDER :
SUBJECT : SCHEDULE OF QUANTITIES AND PRICES DATE :
OWNER : SAUDI ARAMCO SIGNATURE : AUM
DISCIPLINE: