Project Name:
Contract No:
Version: 0
Principal: Sydney Trains
Scope of Works: Security Site: 322 Parramatta Road, Clyde
System Package Job no: 370
ABN: 19 128 617 774, Lic No 232745c REV: 0 Page: Page 1 of 10
Table of Contents
1 Project Description..................................................................................................................................................2
1.1 Description of Trade Scope: Security System Package....................................................................................2
1.2 Mobilisation & Demobilisation Works.............................................................................................................2
1.3 Detailed Trade Work Description:...................................................................................................................2
1.4 General Trade Work Description and Specific Allowances to be made:..........................................................3
1.5 Supply of Materials, Fixtures, Fittings and Equipment:...................................................................................3
1.6 Existing Services...............................................................................................................................................3
2 Programme and Staging of Works:..........................................................................................................................3
3 Deliveries, Material’s Handling, Site Access:...........................................................................................................4
4 Workshop Drawings:...............................................................................................................................................4
5 As Built and Works as Executed Drawings:..............................................................................................................4
6 Practical Completion:..............................................................................................................................................4
7 Warranty and Defect Liability Period:.....................................................................................................................4
8 Standards of Work, Compliance and Certification:..................................................................................................5
9 Meetings and Co ordination:...................................................................................................................................5
10 Design Requirements:.............................................................................................................................................5
11 Safety Management Requirements:........................................................................................................................5
12 Environmental Management Requirements:..........................................................................................................6
13 Quality Management Requirements:......................................................................................................................7
14 Cultural Heritage.....................................................................................................................................................7
15 Training Plan............................................................................................................................................................7
16 Insurances:..............................................................................................................................................................7
17 Commercial Terms:.................................................................................................................................................7
17.1 Form of Contract:............................................................................................................................................7
17.2 Payment Terms:..............................................................................................................................................7
17.3 Retention:........................................................................................................................................................7
17.4 Liquidated Damages........................................................................................................................................8
18 Document Register:.................................................................................................................................................8
1 Project Description
This scope of works is for the Security System Package for the Construction of a New interim Storage Facility at 322
Paramatta Road, Clyde. Existing sites at William St., Lidcombe and Strathfield triangle will be relocated to the new
facility.
A breakdown summary of the works is listed below.
1.1 Description of Trade Scope: Security System Package
The scope of works includes but is not limited to the supply and installation of all Swipe Access Entry, CCTV System,
Intercom and the likes. The works includes demolition and/or protection of existing structures, devices and systems
deemed necessary to complete this package.
1. Demolition/Removal
Remove existing intercom/swipe access to main entry gate.
2. Works
The works include the entirety of the security system package & services requirements to
arrive at the final completed building. The works below a high-level breakdown of what is included
but is not limited to the points mentioned below.
Security System: Connection and all the cabling works thereafter, including but not
limited to
o Swipe access entry to doors at office in plan A. (Dwg. No. 60592504-SHT-AU-MB-
101 Rev. 2)
o Swipe access entry to double door at locker room in plan B. (Dwg. No.
60592504-SHT-AU-MB-102 Rev. 2)
o Swipe access entry to doors on existing warehouse.
o Replace new intercom/swipe access facility of the main entry gate. Intercom
receiver/answer facility to be located within new office area in plan A.
o Sensor loop
CCTV System :
o Allow for new localised CCTV system to provide general coverage to site as well
as coverage of new storage area.
o Cable and fittings to be of suitable quality and approved.
o On completion of work, As built conduit drawings to be provided.
o Contractor is responsible for compliance and to meet the requirements set by
the Client.
3. Commissioning
1. Subcontractor is to site check, measure and confirm all dimensions / quantities and make
sufficient allowances for measured dimensions / quantities required onsite. Any dimensions /
quantities provided by VMG to the subcontractor are approximates only and must not be relied
upon.
4. Subcontractor to allow for the removal and disposal of trade waste:
5. Subcontractor to allow for the final clean of the work area.
6. Subcontractor to confirm and allow for all works to be in full compliance with the relevant
Australian Standards, Building Code Australia (BCA) / National Construction Code (NCC).
7. Subcontractor to allow for all works to be in full compliance with the relevant Australian
Standards, Building Code Australia (BCA) / National Construction Code (NCC). Subcontractor to
advise VMG PM in wiring if the proposed works are not full compliance of relevant Standards
and Codes.
8. Subcontractor to allow for co-ordination of works with other trades on site
4 Workshop Drawings:
1. Subcontractor to provide Workshop drawings for this trade package: YES. Remainder as
redlines.
24. Subcontractor to provide workshop drawings in a timely manner, prior to fabrication, for Client
review and approval.
25. Subcontractor to allow to update and modify drawings as required
6 Practical Completion:
1. Subcontractor to provide a standard of work that is fit for handover (final handover that
matches the head contract) being defect free.
27. Each area is to be signed off by both parties agreeing that the works in the area are complete
and defect free. For finishing trades this will include all waste and dust cleaned before leaving
the area and handing it over.
28. Practical completion sign off represents the finalisation of the works but the Defect Liability
Period (DLP) which is referred to as the “Warranty Period” will necessarily need to match the
/ Uncontrolled When Printed Template Rev: A Page 4 of 10
Status: NVM approved Temp Last Updated: 25/02/2018
conversion/tmp/activity_task_scratch/55399427
7.docx
Principal: Sydney Trains
Scope of Works: Security Site: 322 Parramatta Road, Clyde
System Package Job no: 370
ABN: 19 128 617 774, Lic No 232745c REV: 0 Page: Page 5 of 10
DLP for VMG. This will be 52 weeks from our Practical Completion Date. These figures are in
Section 13 in the Subcontract information in the contract.
10 Design Requirements:
1. Allow for all necessary design and documentation required to co ordinate, communicate and
complete the works.
2. Design development is considered a part of the contract. Where there are gaps and omissions in
the design and these do not constitute a structural warranty or compliance issue, then the
subcontractor is to construct as per the code and to gain compliance.
14 Cultural Heritage
1. Respect, protect and preserve any Heritage items and structures on site – Not relevant.
2. Any cultural heritage finds are to be reported immediately.
15 Training Plan
1. The project is subject to a training plan with the LAHC rules being applied:
a. Apprentices are to be 20%of the workforce,
b. Aboriginal and Torres Straight Islander(ABTSI) labour and expenditure targets apply.
3. All inductees will be asked if they are apprentices or identify as ATSI
16 Insurances:
1. Subcontractor to arrange and pay for all insurance premiums as required for the works. Make
allowances for the following:
67. Public and Products Liability Insurance: $20,000,000.00
68. Workers Compensation Insurance for all wages paid
69. Insurance for all materials, equipment and tools kept on site or in transit
17 Commercial Terms:
17.1 Form of Contract:
1. Subcontractor to provide an all inclusive, fixed price lump sum to complete the works as per the
Scope of Works. Contract is GC21 Subcontract.
17.3 Retention:
1. A maximum of 5% of contract value with be held
71. Half of the retention amount will be released at practical completion and upon all handover
documents, as built drawings, warranties, testing and certifications
72. The remaining half will be released at the end of the defect liability period, provided that the
works are defect free
73. Bank guarantees will be accepted
18 Document Register:
The contract documents are listed in the GC21 subcontract provided.