SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

Table of Contents

Section Title Page


1 PURPOSE 3
2 SCOPE 3
3 REFERENCES 3
4 DEFIN ITIONS 3-4
5 GENERAL REQUIREMENT 4-6
5.1 Installer Requirement
5.2 Pipe and Fittings Materials
5.3 Elastomeric Seal Materials and Gaskets
5.4 Adhesives
6 EXECUTION 6-13
6.1 Trench
6.2 Pipe Foundation / Bedding
6.3 Placement of Pipe in the Trench
6.4 Pipe Joining
6.5 Thrust Blocks and Wrapping
6.6 Testing
6.7 Trench Backfilling
7 QUALITY CONTROL and INSPECTIONS 13
8 7.1 Quality Control
7.2 Inspections
8 STORAGE, HANDLING and PRESERVATION 14-15
9 RESPONSIBILITIES 15
10 HEALTH, SAFETY and ENVIRONMENT 15-16

Page 2 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

1. PURPOSE
The purpose of this procedure is to ensure that all works / activities for RTR and Non-Metallic Piping
installation are carried out in full compliance with specifications and applicable Aramco standards for
South Ghawar UR Early Works project requirement.

2. SCOPE
This procedure covers the methodology and execution of RTR and Non-Metallic Piping installation
activities such as Raw Water supply line; Drinking Water supply lines, Fire Water supply lines and
Sanitary Sewer/Drainage lines for South Ghawar UR Early Works & TCF project and is applicable
within the project duration.
This procedure covers the activities from trenching, pipe installation, testing (hydrotests & gravity test)
and backfilling.

3. REFERENCES
Saudi Aramco Standards
• 01-SAMSS-029 RTR (Fiberglass) Pipe and Fittings for Gravity Flow
• 01-SAMSS-034 RTR (Fiberglass) Pressure Pipe and Fittings
• 01-SAMSS-042 Reinforced Thermoset Resin (RTR) Pipe and Fittings in Water and
Hydrocarbon Services
• SAEP-384 Inspection Requirements for In-service RTR Piping and Pipelines
• SAEP-407 Qualification of Nonmetallic Pipe Installers, Supervisors and Inspectors
• SAES-L-620 Design of Reinforced Thermosetting Resins (RTR) Piping in Hydrocarbon
and Water Injection Systems
• SAES-A-004 General Requirements for Pressure Testing
• SAES-A-114 Excavation and Backfill
• SAES-B-017 Fire Water System Design
• SAES-S-010 Sanitary Sewers
• SAES-S-040 Saudi Aramco Water System
• SAES-S-060 Saudi Aramco Plumbing Code
• SAES-S-070 Installation of Utility Piping
4. DEFINITIONS
• Fiberglass Pipe (RTR) A nonmetallic, composite tubular product that basically contains glass
fiber reinforcement, resins, fillers and liners manufactured using semi-
automated filament winding machine.
• Reinforced Polymer Mortar Pipe (RPMP) Is a fiberglass pipe with aggregate.
• Reinforced Thermosetting Resin Pipe (RTRP) Is a fiberglass pipe without aggregate.
Page 3 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

• Gravity Flow Fluid flowing due to gravity forces alone and not to an applied pressure
head.

5. GENERAL REQUIREMENTS
5.1. Installer Requirement
5.1.1 Field installation and inspection testing shall be conducted by qualified and certified
personnel as per SAEP-407. (SAES-L-650 Para. 5.1)
5.1.2 Training certificate must be obtained from any RTR Saudi Aramco Approved Piping
Manufacturer. (SAES-L-650 Para. 5.1.1)
5.1.3 Certificate shall be valid for one year or the duration of the project, whichever is the
farthest. (SAES-L-650 Para. 5.1.2)
5.1.4 Certification shall be submitted to Saudi Aramco Inspection Department for review and
concurrence and a Job Clearance card (JCC) validity is for mentioned project only shall
then be issued to each qualified pipe and fitting installer. (SAES-L-650 Para. 5.1.3)
5.2. Pipe and Fittings Materials
5.2.1. RTR Pipe and fittings shall consist of thermosetting resin reinforced with glass fiber.
(01-SAMSS-042 Para. 5.2 a)

5.2.2. RTR Pipes and fittings shall be supplied with integral conductive carbon fibers when
electrical conductivity is needed. (01-SAMSS-042 Para. 5.2 c)
5.2.3. The inside surface of each pipe shall be free of bulges, dents, ridges, or other defects that
result in a variation of inside diameter of more than 3.2 mm from that obtained on
adjacent portions of the surface. (01-SAMSS-034 Para. 4.2.1)
5.2.4. No glass-fiber reinforcement shall penetrate the interior surface of the pipe wall.
(01-SAMSS-034 Para. 4.2.1)

5.2.5. Joint sealing surfaces shall be free of dents, gouges, or other surface irregularities that
will affect the integrity of the joints. (01-SAMSS-034 Para. 4.2.1)
5.2.6. Flanges, bends, reducers, tees, wyes and other fittings may be compression-molded,
manufactured from mitered section of pipe, or manufactured by the filament wound
process, using thermosetting polyester, vinyl ester or epoxy resin and fiberglass
reinforcement such that the resistance to chemical attack, the pressure rating, and the
temperature rating, are equal to or better than that of the pipe. (01-SAMSS-034 Para. 4.4.2.2)
5.3. Elastomeric Seal Materials and Gaskets
5.3.1 The chemical composition of the flexible elastomeric seals shall be compatible with the
type of service and environment to which it will be subjected. (01-SAMSS-034 Para. 4.4.1.5)
Page 4 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

5.3.2 The manufacturer shall specify the seal and gasket material compatibility in line with
fluid composition and design conditions, given the range of operating parameters.
Examples pf elastomeric seals and gasket materials listed in table E of 01-SAMSS-042.

Page 5 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

5.4. Adhesives
5.4.1 Adhesive for bonded joints shall be of a material suitable for the services and design
conditions specified. (01-SAMSS-034 Para. 4.4.1.4)
5.4.2 It shall be mutually compatible with the resin used to manufacture the pipe.
5.4.3 Adhesive shall be provided in a self-contained kit with all necessary materials and
instructions. (01-SAMSS-034 Para. 4.4.1.4)
5.4.4 Shelf life of adhesive kits, at 38°C, shall not be less than 9 months from the date of
shipment. Adhesive kit shall indicate the required storage conditions and date of
expiration of shelf life. (01-SAMSS-034 Para. 4.4.1.4)
5.4.5 Adhesive shall be suitable for use at 48°C working environment. (01-SAMSS-034 Para. 4.4.1.4)

5.4.6 Adhesive and solvent cement containers shall be tightly closed when not in use, and shall
be returned to the storage facilities to minimize exposure to excessive temperatures.
(SAES-S-070 Para. 5.9)

6. EXECUTION

6.1 Trench
A. Trench safety shall be in accordance with SAES-A-114. (SAES-L-650 Para.6.1 a)
B. The various parts of a soil trench (deep trench) are illustrated in Appendix A, Figure
A-1 of SAES-L-650.

Page 6 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

C. When trenching becomes a challenge specially in rocky area, shallow trench with
bern can be used as an alternative to the deep trench method. The dimensions of
shallow trench are illustrated in Appendix A, Figure A-2 of SAES-L-650

D. Surveys shall be conducted prior to excavation to confirm that there are no other
buried commodities which could interfere or be damaged by excavation.
(SAES-L-650 Para.6.1 c)

E. If the trench is excavated on the slides of a slope, the slope shall be less than 15
degrees. For steeper slopes and for excavation in a area of unstable soil, a
geotechnical feasibility investigation ism required prior to trenching, to verify short
term and long term stability. (SAES-L-650 Para.6.1 d)
F. Excavate trench and provide trench walls as necessary to ensure that sides are stable
under working conditions. (SAES-L-650 Para.6.1 e)
G. In situations where water is present in the trench, dewater the trench prior to
installation of bedding, pipe and backfill in accordance to SAES-A-114.
(SAES-L-650 Para.6.1 f)

H. The bottom of the trench shall be dry or sufficient drained so that there is no standing
water before the support and bedding layers are placed and compacted. The bedding
layer must be sufficiently drained so that there is no standing water on the bedding
layer before the pipe is installed. (SAES-S-070 Para.9.3)
I. The trench shall be clean, free of organic materials, tree roots, and other extraneous
materials. (SAES-L-650 Para.6.1 g)

Page 7 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

J. Shoring sheeting may be placed between the native soil along the side of the trench
and the trench fill if the sides of the trench are unstable. (SAES-L-650 Para.6.1 h)
K. For single pipeline, the minimum width at the bottom of the pipeline shall be at least
(1.25 x the outside diameter + 300 mm). (SAES-L-650 Para.6.1 i)
L. For multiple pipes in the same trench, the space between pipes should be at least 1
meter. (SAES-L-650 Para.6.1 j)
M. The slope of the pipe trench shall be verified not to exceed the permitted curvature of
the pipe. (SAES-L-650 Para.6.1 k)
6.2 Pipe Foundation / Bedding
1. Bedding shall be installed in all cases below the pipe and shall be a minimum of 6
inches (150 mm) including haunch zone. (SAES-L-650 Para.6.2 c)
2. If necessary to achieve the required pipe depth and pipe slope, a foundation may be
installed at the bottom of the trench. The foundation shall be designed and installed as
per SAES-Q-005. (SAES-L-650 Para.6.2 b)
3. The bedding shall be clean (rock-free and fines-free) sand, or granular with 100 %
passing 19 mm (3/4”) sieve, 90 to 100% passing a 9.5 mm (3/8”) sieve and not more
than 4% passing 75 µm (no. 200 sieve). (SAES-L-650 Para.6.2 d)
4. Bedding shall have 70% Relative Density (ASTM D4253 & ASTM D4254)
cohesionless granular soil that do not exhibit well defined moisture density
relationship. (SAES-A-114)
5. The bedding shall be shaped to provide uniform support in the haunch (saddle) zone
along the full length of the pipe without voids between the bedding and the pipe.
(SAES-L-650 Para.6.2 e)

6. If the pipe joints are larger than the pipe, the bedding profile shall be shaped to
accommodate the joint. (SAES-L-650 Para.6.2 f)
7. The haunch (saddle) zone under the pipe shall be backfilled first. (SAES-L-650 Para.6.2 f)
6.3 Placement of Pipe in the Trench
A. Pipe 4 in. and smaller may be double joined outside the trench then lifted and placed
into the trench. Lift using wide nonmetallic straps not chains. (SAES-L-650 Para.6.3 a)
B. When lifting the pipe, do not exceed the curvature limit specified by the pipe and
lifting manufacturer. (SAES-L-650 Para.6.3 b)
C. For larger pipes (greater than ˃ 4 in.), heavy wall pipe or trenches deeper than 2 m.
pipes shall be joined in the trench. (SAES-L-650 Para.6.3 c)
Page 8 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

D. Protect the pipeline from water or foreign material penetrates or contaminates the
interior of the pipe and the surface of the joints. (SAES-L-650 Para.6.3 d)
E. When placing the pipe, the pipe shall be at the center of the trench.
(SAES-L-650 Para.6.3 e)

6.4 Pipe Joining


A. Only make-up tools and wrenches supplied by the pipe and fitting manufacturer (and
appropriate for the pipe size and joint type) shall be used in handling pipes and
fittings, and making joints. (SAES-L-650 Para. 7 a)
B. If pipe segments must be pulled, the pull force shall not exceed the manufacturer
specified tensile load limit. (SAES-L-650 Para. 7 b)
C. Joining shall be in accordance with the pipe and fitting manufacturer joining manual.
(SAES-L-650 Para. 7 c)

D. RTR flanges when used shall be of flat face. Mating flanges of different approved
material shall be of flat face. They shall be assembled with full-face elastomeric
gaskets, 3 mm thick, and 50 to 60 Shore A Durometer hardness. (SAES-S-070 Para. 11.2)
E. Flange pressure rating requirement, and bolt tightening procedures and maximum
torque requirements shall be in accordance with SAES-L-610 or as per RTR flange
manufacturer’s recommendations. (SAES-S-070 Para. 11.4)
F. Each threaded joint shall be inspected for evidence of proper penetration of male-
female threads, within the limits specified by manufacturer. (SAES-L-650 Para. 7 c)
G. Each threaded joint shall be inspected for evidence of proper penetration of male-
female threads, within the limits specified by the manufacturer. (SAES-L-650 Para. 7 d)
H. Pipes and fittings from different manufacturers shall not be inter-mixed.
(SAES-L-650 Para. 7 e)

I. Joining shall be performed by personnel trained and certified by manufacturer in


accordance with construction manual. (SAES-L-650 Para. 7 f)
J. Thread protectors shall be left in place until ready for joining. (SAES-L-650 Para. 7 g)
K. Threads shall be cleaned and carefully inspected before joining and shall be free from
any visible damaged. Thread damaged evaluation shall be in accordance with the
manufacturer construction manual. (SAES-L-650 Para. 7 h)
L. Thread fittings shall be assembled with lubricants and sealants specified by the
manufacturer for the fluid and pressure. Do not inter-mix lubricants or sealants from
different manufacturer. (SAES-L-650 Para. 7 i)

Page 9 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

M. Pipes shall be aligned prior to joining in accordance with manufacturer installation


procedure. (SAES-L-650 Para. 7 j)
N. Once jointed, threaded joints shall be inspected in accordance with manufacturer
recommendations. In particular, thread engagement shall be within the limits
specified by the manufacturer. (SAES-L-650 Para. 7 m)
6.5 Thrust Blocks and Wrapping
a. Thrust blocks shall be placed between undisturbed earth and fittings to be restrained
at every change in direction for thermoplastic and RTR piping with the following
exceptions: (SAES-S-070 Para. 17.1)
a.1 Thrust blocks are not necessary for gravity flow system
a.2 Thrust blocks are not required for 75 mm nominal pipe size and
smaller piping with restrained joints, as defined in Section 10 & 11
of SAES-S-070.
b. If thrust block is required for RTR piping and thermoplastic piping in accordance
with paragraph (SAES-S-070 Para. 17.1), temporary thrust resistance is required at
pipe bends, tees and reducers and other change of direction prior to hydrostatic test.
Details are to be presented, locations are to be identified and submitted as part of the
hydrostatic test procedure. (SAES-S-070 Para. 17.2)
c. Thrust blocks design for RTR piping shall follow AWWA M45. Thrust blocks
material and constructability shall follow SAES-Q-001 (SAES-S-070 Para. 17.3)
d. Cast in place thrust blocks shall not be directly embedded with thermoplastic and
RTR Piping joints. (SAES-S-070 Para. 17.4)
e. Non-metallic Pipes such as PVC, UPVC, CPVC, RTRP, HDPE, PP, etc., shall be
protected from contact with concrete by tape wrapping. Use 9COM material number
for tape wrap 1000199982/1000199986/1000200030 or equivalent.
(SAES-S-070 Para. 17.5)

f. At the edges where a thermoplastic or an RTR pipe or fitting enters or leaves a thrust
block it shall be wrapped with neoprene wrapping that will protrude slightly from the
block. The thickness and the width of wrap shall comply with Table 5 of SAES-S-
070, unless the manufacturer requires more than one piece of wrapping.
(SAES-S-070 Para. 17.6)

Page 10 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

g. Vibrators shall be kept clear of the piping while casting concrete thrust blocks.
(SAES-S-070 Para. 17.7)

6.6 Testing
6.1.6.1 Hydrostatic Testing
A. Unless prevailing conditions or regulations require full backfilling of piping
prior to the hydrotest, underground piping shall be partially backfilled with all
joints exposed during the hydrotest. The exposed joint shall be shaded from
direct sunlight, and the hydro test shall be performed so that the temperature
of the thermoplastic piping material or the temperature of the test water does
not exceed 40°C during the test period. (SAES-S-070 Para. 18.1)
B. Potable water (drinking water and raw water) piping systems shall be
hydrotested with fresh potable water as defined in SAES-S-040.
(SAES-S-070 Para. 18.2 a)

C. No thermoplastic piping shall be pressurized until it has cured for 24 hours at


a surface temperature of 10°C or higher or 48 hours at a surface temperature
below 10°C. (SAES-S-070 Para. 18.3)
D. No adhesive-bonded RTR piping shall be pressurized until it has cured in
accordance with the manufacturer’s recommendation. (SAES-S-070 Para. 18.3)
E. The test pump shall be placed on firm ground away from the piping system
(piping and equipment) shall be protected from over-pressure or a maximum
of 170 kPa (25 psig) above the test pressure for pressure piping system. The
relief valve shall be tested dated and tagged prior to the test. Sizing of relief
valve(s) used for testing shall be in accordance with SAES-A-004. (SAES-S-070
Para. 18.5)

F. Requirements of pressure gauges and pressure recorders for pressure piping


system, calibration intervals, and calibration certificates shall be in accordance
with SAES-A-004. Calibrated and tagged relief valve(s) may be used as the
pressure test instrument upon written approval of the Manager, Inspection
Department. (SAES-S-070 Para. 18.6)
G. Pipes shall be air cleaned prior to testing and then shall be verified by runs of
soft pigs propelled by water in accordance with SAES-S-007. The line shall
be flushed prior to hydrotesting. (SAES-L-650 Para. 10.2 c)
H. The line shall be filled with hydrotest water, vented, and be free or air or gas.
(SAES-L-650 Para. 10.2 e)

I. The test shall not be conducted below freezing temperature.


(SAES-L-650 Para. 10.2 f)

Page 11 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

J. When the first 500 m pipe is installed it shall be hydrotested prior to


continuing installation of the system. (SAES-L-650 Para. 9.1)
K. During hydrotest, all exposed pipe, joints fittings valves and hydrants shall be
carefully examined for leakage. (SAES-L-650 Para. 19.1)

L. Leaking pipe and fittings shall be replaced. (SAES-L-650 Para. 19.2)

M. The hydrostatic test shall be repeated after the repair of any defect until the
system is proved satisfactory. (SAES-L-650 Para. 19.3)
N. Construction of the rest of the line may proceed following the successful
initial hydrotest. (SAES-L-650 Para. 9.2 a)
O. The piping shall satisfactory if there is no evidence of leakage or pressure loss
after the specified test period. (SAES-L-650 Para. 19.4)
P. When the complete line has been installed in the trench, it shall be prepared
for full system hydrotest. (SAES-L-650 Para. 9.2 b)
6.1.6.2 Gravity Testing
A. Gravity sewer shall be tested from manhole to manhole, or manhole to sump
inlet. The upstream manhole maybe tested at the same time.
(SAES-L-070 Para. 18.7)
B. Gravity sanitary sewer pipe tested separately: a column of water equivalent to
the rim elevation of the upstream manhole. (SAES-L-070 Para. 18.8 e)

C. All water and sewage (sanitary, chemical and industrial drainage and sewer as
per SAES-S-020) retaining structures under atmospheric pressure such as
tanks / holding tanks, manholes, sumps, catch basins, interceptors, lift stations,
grease-traps, etc., maybe tested separately or as part of the piping system test:
filled to top of rim with water for 8 , then topped off to top of rim. Site testing
shall take place prior to backfill and / or application of protective coating.

6.7 Trench Backfilling


A. A minimum of one bucket of fill shall be placed in the middle of each pipe run.
(SAES-L-650 Para. 9.2 c)

B. Each connecting joint, and approximately 0.60 m (2 ft.) on each side of the
connecting joint shall be left uncovered for hydrotest. (SAES-L-650 Para. 9.2 c)
C. Following successful completion of the hydrotest, the line shall be covered and
the trench filled. (SAES-L-650 Para. 9.2 f)

Page 12 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

D. Backfill should be placed and compacted in lifts not exceeding 6 in. (150 mm),
and compacted in accordance with the Engineering Design. (SAES-L-650 Para. 9.2 g)
E. The compacting equipment shall not contact the pipe. If contact does occur, the
Construction Engineer shall be notified for inspection and repair or disposal.
(SAES-L-650 Para. 9.2 h)

F. To assure the compaction quality, vibration from moving heavy trucks shall be
avoided during backfilling. (SAES-L-650 Para. 9.2 k)
G. Color coding of utility piping above or below ground shall be in accordance with
SAES-A-104 and SAES-B-067). (SAES-L-070 Para. 4.4)
H. Detection Method is required to identify the location of underground utility line
after backfilling and shall comply with AWWA C605 section backfill.
(SAES-L-070 Para. 4.5)

7. QUALITY CONTROL and INSPECTIONS

7.1 Quality Control


1) The manufacturer shall have an independent Quality Control inspection function.
(01-SAMSS-042 Para. 11 e)

2) All equipment and instruments used in Quality Control shall be identified, controlled and
calibrated at least every 6 months. (01-SAMSS-042 Para. 11 f)
3) Pressure gages shall be accurate within 2% of full-scale range. (01-SAMSS-042 Para. 11 g)

4) All pipes, fittings and components shall be traceable, through their markings, to the
manufacturing plant, the lot and its raw material. (01-SAMSS-042 Para. 11 h)

7.2 Inspections
The below Saudi Aramco SATIP & its applicable SAIC can be utilized:
• SATIP-S-070-03 Thermoplastic and RTR Piping
• SAIC S-4054 RTR & Thermoplastic Installers Qualifications
• SAIC S-4055 Piping and Fittings Receiving Inspection
• SAIC S-4056 Pipe and Fittings Handling, Storage and Preservation
• SAIC S-4057 Thermoplastic Piping Installation and Assembly Inspection
• SAIC S-4058 RTR piping Laying and Assembly Inspection
• SATIP-A-004-02 Hydrostatic Testing of On-Plot Piping
• SATIP-A-114-01 Earthwork - Site Preparation, Excavation and Backfill During
Construction.

Page 13 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

8. STORAGE, HANDLING and PRESERVATION


A. Unless otherwise specified in the Purchase Order, pipe, fittings, O-rings, gaskets, locking rings,
and adhesives shall be packed in a manner to withstand rough handling. The size and type of
packing shall permit long term storage. (01-SAMSS-029 Para. 13.1.1)
B. End protectors shall be provided and securely attached to open ends of all pipes.
(01-SAMSS-029 Para. 13.2.1)

C. All threaded connections shall be protected with protective caps. (01-SAMSS-034 Para. 6.2.2.4)
D. End protector shall be design to protect the pipe ends from impact damage, contamination, and
weathering of machined bonding surfaces due to ultraviolet exposure. They shall have an open
center permitting inspection of the pipe bore. (01-SAMSS-029 Para. 13.2.2)
E. Flange faces on fabricated piping shall have protective cover not smaller than the flange outside
diameter. (01-SAMSS-029 Para. 13.2.3)
F. The pipe shall be set on a flat surface, free of sharp edges. (01-SAMSS-042 Para. 10 d)

G. Support pipe on a minimum of four equally spaced racks. (01-SAMSS-042 Para. 10 e)

H. If they are to be bundled, pipes shall be secured by straps; chains are not permitted.
(01-SAMSS-042 Para. 10 g)

I. Gaskets and adhesive systems and lubricants shall be stored in their original packing in
accordance with the manufacturer recommendations. (01-SAMSS-042 Para. 10 i)
J. Gaskets, O-rings, and locking keys shall be stored flat on racks below 38°C and out of direct
sunlight. (SAES-S-070 Para. 5.5)
K. The stored adhesives systems or lubricants shall be discarded if they have an expired shelf life.
(01-SAMSS-042 Para. 10 j)

L. Adhesive for RTR piping shall be stored in an enclosure where temperature do not exceed 38°C.
(SAES-S-070 Para. 5.6)

M. Pipe shall be stored out of direct sunlight in a building or under a cover. (SAES-S-070 Para. 5 a)
N. Racks shall conform to factory shipping packages for each pipe size. Shelves shall be provided
for continuous support of the pipe. (SAES-S-070 Para. 5 b)
O. If loose pipes are stacked on each other, the stack height shall not exceed 1.5 m. Adequate side
support shall be provided to prevent slipping or rolling. (SAES-S-070 Para. 5 c)
P. If pipe is stored on racks or bearing boards, the support shall be at least 75 mm wide. Support
shall be spaced on 3 m centers maximum with the first support 1.5 m from the end of the pipe.
(SAES-S-070 Para. 5 d)

Page 14 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

Q. All supporting surfaces shall be free of sharp objects. (SAES-S-070 Para. 5 e)

9. RESPONSIBILITIES
QA/QC Manager Shall ensure that the work was carried out as per the approved
procedure.
QC Supervisor Responsible in supervising and leading the QC inspector in
monitoring the work.
QC Inspector To ensure that works is carried out according to the approved
procedures and monitor compliance during execution.
Construction Managers Responsible in giving guidance to his site engineers in
implementing the work as per the approved procedure.
Site Engineers Responsible in leading the construction team in implementing the
work as per the approved procedure.
Safety Officers Monitor the activity and ensure that proper safety procedures are
being implemented and hold any activity which could be found in
unsafe situation.

10. HEALTH, SAFETY and ENVIRONMENT


10.1 Uncontrolled releases of stored energy from compressed air or other gas can take the form of
explosions. High velocity streams of fluid can be created or piping and equipment can be moved.
The degree of these hazards is determined primarily by the test pressure and the volume of air,
gas or other fluid involved. (GI-0002.102 Section 4)
10.2 Avoid the following typical examples of poor practices which may result in possible mishaps:
A. Striking or working on equipment while it is under pressure, to stop leaks.
B. Improper or missing test equipment, such as testing without a relief valve, having an
inadequately sized relief valve, or having no pressure gauges\(s).
C. Omitting or changing steps in the test sequence such as failing to conduct a low-
pressure tightness test to check for leaks prior to strength pressure tests at higher
pressures.
D. Failure to vent air from the system prior to the test
E. Use of gas instead of water as a test medium.
F. Metal temperature below that which the impact requirements cannot be met by the
material.

Page 15 of 16
SAUDI ARAMCO OIL COMPANY

ABDUL MOHSEN AH AL-TAMIMI


PARTNERS COMPANY
RTR & NON-METALLIC PIPES DOC-NO- AMT-SGP-NMP-001
UNDERGROUND PIPING INSTALLATION Rev 00
PROCEDURE Date of Issue: April. 15, 2020

G. System not adequately supported to withstand the weight of water during the test.
H. Pressure gauge(s) and relief valve(s) not calibrated and tested.
I. Pressure gauge located too far from pressurizing equipment for reading.
J. Appurtenances not adequate for the test pressure, not isolated from the test.
K. Pressure increased too rapidly to be controlled.
L. Relief valve inoperative because of a closed block valve.
M. Temporary test piping not designed for the test pressure.
N. No bleed valve provided in the test piping.
O. Failure to pressure test equipment and piping to putting them in service.
P. Testing equipment with the test gauge located at the bottom reading the test pressure,
including the head of test water.
10.3 Health, Safety and Environment issues shall be guided by AMT safety procedures & ARAMCO
Standard.
10.4 Safety talk shall be conducted to remind the workers about the risk involved before commencing
the activity.

(END OF THE PROCEDURE)