You are on page 1of 2

TANK ROOF STRUCTURE FABRICATION SHEDULE FOR SPLICE BEAMS

14.Aug.2023
Activity ID Activity Name Start Finished Duration Priority Actual Start Actual Finish Activaties Satus %of Competion Target

Intermediate Rafter Fabrication - 84 Nos


14-Aug-23 18-Sep-23 35
Outer Rafter Fabrication - 126 Nos
Phase - 1 14-Aug-23 22-Aug-23 9
I - INTERMIDATE RAFTER IPE 270 : 9 NOS 14-Aug-23 20-Aug-23 7 P 01
Material Preparation (Material Shifting, Beam Cutting,
FAB - 110 14-Aug-23 14-Aug-23 1 P 01
Beveling and Splice Plate Cutting)
FAB - 111 Beam Fitup 14-Aug-23 15-Aug-23 2 P 01
FAB - 112 Beam to Beam Welding (Butt Joint) 15-Aug-23 16-Aug-23 2 P 01
FAB - 113 NDT - PT in Beam to Beam Joint 16-Aug-23 16-Aug-23 1 P 01
FAB - 114 Splice Plate Fitup (05 Nos) 17-Aug-23 19-Aug-23 3 P 01
FAB - 115 Splice Plate Welding 17-Aug-23 20-Aug-23 4 P 01
FAB - 116 NDT - PT in Splice Plate Joint 20-Aug-23 20-Aug-23 1 P 01
FAB - 117 Final Dimension & Release for Painting 20-Aug-23 20-Aug-23 1 P 01
II - OUTER RAFTER IPE 330 : 32 NOS 14-Aug-23 22-Aug-23 9 P 02
Material Preparation (Material Shifting, Beam Cutting,
FAB - 210 14-Aug-23 15-Aug-23 2 P 02
Beveling and Splice Plate Cutting)
FAB - 211 Beam Fitup 15-Aug-23 18-Aug-23 4 P 02
FAB - 212 Beam to Beam Welding (Butt Joint) 15-Aug-23 18-Aug-23 4 P 02
FAB - 213 NDT - PT in Beam to Beam Joint 17-Aug-18 18-Aug-23 2 P 02
FAB - 214 Splice Plate Fitup (05 Nos) 17-Aug-23 19-Aug-23 3 P 02
FAB - 215 Splice Plate Welding 18-Aug-23 21-Aug-23 4 P 02
FAB - 216 NDT - PT in Splice Plate Joint 22-Aug-23 22-Aug-23 1 P 02
FAB - 217 Final Dimension & Release for Painting 22-Aug-23 22-Aug-23 1 P 02
Phase - 2 21-Aug-23 31-Aug-23 11
III - INTERMIDATE RAFTER IPE 270 : 21 NOS 21-Aug-23 29-Aug-23 9 P 03
Material Preparation (Material Shifting, Beam Cutting,
FAB - 120 21-Aug-23 22-Aug-23 2 P 03
Beveling and Splice Plate Cutting)
FAB - 121 Beam Fitup 22-Aug-23 25-Aug-23 4 P 03
FAB - 122 Beam to Beam Welding (Butt Joint) 22-Aug-23 26-Aug-23 5 P 03
FAB - 123 NDT - PT in Beam to Beam Joint 25-Aug-23 26-Aug-23 2 P 03
FAB - 124 Splice Plate Fitup (05 Nos) 25-Aug-23 28-Aug-23 4 P 03
FAB - 125 Splice Plate Welding 26-Aug-23 28-Aug-23 3 P 03
FAB - 126 NDT - PT in Splice Plate Joint 29-Aug-23 29-Aug-23 1 P 03
FAB - 127 Final Dimension & Release for Painting 29-Aug-23 29-Aug-23 1 P 03
IV - OUTER RAFTER IPE 330 : 32 NOS 14-Aug-23 22-Aug-23 9 P 03
Material Preparation (Material Shifting, Beam Cutting,
FAB - 220 21-Aug-23 22-Aug-23 2 P 03
Beveling and Splice Plate Cutting)
FAB - 221 Beam Fitup 22-Aug-23 25-Aug-23 4 P 03
FAB - 222 Beam to Beam Welding (Butt Joint) 22-Aug-23 26-Aug-23 4 P 03
FAB - 223 NDT - PT in Beam to Beam Joint 25-Aug-23 26-Aug-23 2 P 03
FAB - 224 Splice Plate Fitup (05 Nos) 25-Aug-23 28-Aug-23 4 P 03
FAB - 225 Splice Plate Welding 26-Aug-23 30-Aug-23 5 P 03
FAB - 226 NDT - PT in Splice Plate Joint 31-Aug-23 31-Aug-23 1 P 03
FAB - 227 Final Dimension & Release for Painting 31-Aug-23 31-Aug-23 1 P 03

Phase - 3 29-Aug-23 8-Sep-23 11


V - INTERMIDATE RAFTER IPE 270 : 21 NOS 29-Aug-23 8-Sep-23 11 P 04
Material Preparation (Material Shifting, Beam Cutting,
FAB - 130 29-Aug-23 30-Aug-23 2 P 04
Beveling and Splice Plate Cutting)
FAB - 131 Beam Fitup 30-Aug-23 2-Sep-23 4 P 04
FAB - 132 Beam to Beam Welding (Butt Joint) 31-Aug-23 3-Sep-23 5 P 04
FAB - 133 NDT - PT in Beam to Beam Joint 2-Aug-23 3-Sep-23 2 P 04
FAB - 134 Splice Plate Fitup (05 Nos) 3-Sep-23 6-Sep-23 4 P 04
FAB - 135 Splice Plate Welding 4-Sep-23 7-Sep-23 3 P 04
FAB - 136 NDT - PT in Splice Plate Joint 8-Sep-23 8-Sep-23 1 P 04
FAB - 137 Final Dimension & Release for Painting 8-Sep-23 8-Sep-23 1 P 04
VI - OUTER RAFTER IPE 330 : 31 NOS 29-Aug-23 8-Sep-23 11 P 04
Material Preparation (Material Shifting, Beam Cutting,
FAB - 230 29-Aug-23 30-Aug-23 2 P 04
Beveling and Splice Plate Cutting)
FAB - 231 Beam Fitup 30-Aug-23 2-Sep-23 4 P 04
FAB - 232 Beam to Beam Welding (Butt Joint) 31-Aug-23 3-Sep-23 3 P 04
FAB - 233 NDT - PT in Beam to Beam Joint 2-Aug-23 3-Sep-23 2 P 04
FAB - 234 Splice Plate Fitup (05 Nos) 3-Sep-23 6-Sep-23 4 P 04
FAB - 235 Splice Plate Welding 4-Sep-23 7-Sep-23 4 P 04
FAB - 236 NDT - PT in Splice Plate Joint 8-Sep-23 8-Sep-23 1 P 04
FAB - 237 Final Dimension & Release for Painting 8-Sep-23 8-Sep-23 1 P 04

Phase - 4 7-Sep-23 18-Sep-23 12 P 05


VII - INTERMIDATE RAFTER IPE 270 : 21 NOS 7-Sep-23 18-Sep-23 12 P 05
Material Preparation (Material Shifting, Beam Cutting,
FAB - 140 7-Sep-23 8-Sep-23 2 P 05
Beveling and Splice Plate Cutting)
FAB - 141 Beam Fitup 8-Sep-23 11-Sep-23 4 P 05
FAB - 142 Beam to Beam Welding (Butt Joint) 9-Sep-23 13-Sep-23 5 P 05
FAB - 143 NDT - PT in Beam to Beam Joint 12-Sep-23 13-Sep-23 2 P 05
TANK ROOF STRUCTURE FABRICATION SHEDULE FOR SPLICE BEAMS
14.Aug.2023
Activity ID Activity Name Start Finished Duration Priority Actual Start Actual Finish Activaties Satus %of Competion Target

Intermediate Rafter Fabrication - 84 Nos


14-Aug-23 18-Sep-23 35
Outer Rafter Fabrication - 126 Nos
FAB - 144 Splice Plate Fitup (05 Nos) 13-Sep-23 16-Sep-23 4 P 05
FAB - 145 Splice Plate Welding 14-Sep-23 17-Sep-23 4 P 05
FAB - 146 NDT - PT in Splice Plate Joint 18-Sep-23 18-Sep-23 1 P 05
FAB - 147 Final Dimension & Release for Painting 18-Sep-23 18-Sep-23 1 P 05
VIII - OUTER RAFTER IPE 330 : 31 NOS 7-Sep-23 18-Sep-23 12 P 05
Material Preparation (Material Shifting, Beam Cutting,
FAB - 240 7-Sep-23 8-Sep-23 2 P 05
Beveling and Splice Plate Cutting)
FAB - 241 Beam Fitup 8-Sep-23 11-Sep-23 4 P 05
FAB - 242 Beam to Beam Welding (Butt Joint) 9-Sep-23 13-Sep-23 4 P 05
FAB - 243 NDT - PT in Beam to Beam Joint 12-Sep-23 13-Sep-23 2 P 05
FAB - 244 Splice Plate Fitup (05 Nos) 13-Sep-23 16-Sep-23 4 P 05
FAB - 245 Splice Plate Welding 14-Sep-23 17-Sep-23 4 P 05
FAB - 246 NDT - PT in Splice Plate Joint 18-Sep-23 18-Sep-23 1 P 05
FAB - 247 Final Dimension & Release for Painting 18-Sep-23 18-Sep-23 1 P 05

You might also like