Al Tasnim Handrails Fabrication & Painting Progress

Start Date: 3/28/2023 Status on : 2-Jul-23


Blasting &
JO No 2277 SCOPE FABRICATION (Nos) Activity %
Painting (Nos) Dispatch
Completed Completed Dispatch
Completion Weight Remarks
No of No of Running Weight Fit Up Welidng & Visual Painting Weight (MT) (RM) (RM)
S.No Priority ATM WO No (MT)
Dwgs Handrails Meter (MT)
30% 40% 30% 100%
1 P1 DWO-878 9 10 53.065 0.855 10.0 10.0 10.0 100% 0.85 53.07 0.85 53.07

2 P2 DWO-879 24 42 210.084 3.373 42.0 42.0 42.0 100% 3.37 210.08 3.37 210.08

3 P3 DWO-880 7 11 61.105 0.977 11.0 11.0 11.0 100% 0.98 61.11 0.98 61.11

4 P4 DWO-881 43 52 263.192 4.252 52.0 52.0 52.0 100% 4.25 263.19 4.25 263.19

5 P5 DWO-253A 15 66 175.027 2.449 66.0 66.0 66.0 100% 2.45 175.03 2.45 175.03

6 P5 DWO-404 10 12 50.706 0.824 12.0 12.0 12.0 100% 0.82 50.71 0.82 50.71

7 P5 DWO-504 54 70 253.915 4.103 70.0 70.0 70.0 100% 4.10 253.92 2.14 132.00

8 P6 DWO-890 27 52 138.42 2.280 45.0 45.0 40.0 84% 1.75 106.48

9 P6 DWO-891 27 52 136.387 2.279 24.0 24.0 19.0 43% 0.83 49.83

10 P6 DWO-892 37 53 142.112 2.315 14.0 5.0 5.0 15% 0.22 13.41


Fabrication & Painting ongoing
11 P6 DWO-893 33 55 147.131 2.390 8.0 4%

12 P6 DWO-894 24 39 107.433 1.730 11.0 8%

13 P7 DWO-271 10 78 757.994 10.720 78.0 78.0 5.0 72% 0.69 48.59

Grand Total 320 592 2497 38.55 443 415 332 20.33 1285.40 14.87 945.18
Inspection Stages :
1 After Welding - RFI
2 After Painting - RFI (Final Inspection)
NDT : Not in BG Scope