Pit Pasopati
Daily WTD MTD
NO Description Weekly Plan Monthly Plan Outlook
Plan Actual Ach (%) Plan Act Ach (%) Plan Act Ach (%)
XCE3174
1 OB Bcm 20,120 26,978 134% 202,860 115,920 112,235 97% 603,595 160,959 211,097 131% 791,613
2 Coal Getting Ton 1,900 1,453 76% 22,213 12,693 6,384 50% 57,000 15,200 10,618 70% 39,816
3 Coal Expose Ton 1,667 842 51% 25,066 14,323 7,226 50% 50,000 13,333 11,460 86% 42,973
4 SR 10.59 18.56 175% 9.13 9.13 17.58 193% 10.59 10.59 19.88 188% 19.88
5 Distance m 1,612 1,752 109% 1,612 1,612 1,752 109% 1,612 1,612 1,781 110% 1,612
6 Rain Hrs 3.28 - 0% 22.96 13.12 - 0% 98.4 26.2 - 0% -
7 Rain Freq 1.00 - 0% 7.00 7.00 - 0% 30.0 8.0 - 0% -
8 Slippery OB Hrs 0.71 - 0% 4.98 2.84 - 0% 21.3 5.7 - 0% -
9 Slippery Freq 1.00 - 0% 7.00 7.00 - 0% 30.0 8.0 - 0% -
Act WTD PSU
Remark OB Remark Coal Getting
YTD Plan YTD Actual actual
1,109,871.00 973,339.41 88%
1. Seam tipis dan batubara tidak menerus
Issue Operational
1. Closing temuan BA Serah terima spriding soil dan mencari area spreading soil pada area final disposal
CE4265 2. Progres SP 03 Menunggu closing inspeksi (menunggu progres SP06 selesai)
3. Continue progres SP 06 (estimasi week 3)
CE4077 4. follow up pembuatan tanggul untuk pembentukan area lowest point (open) dan estimasi pemompaan dengan pompa yang ada
CE4064
Issue Safety
1. Pengawas melekat pada area front sempit (continue)
2. Cek fatigue dilakukan 2 kali pershift (sebelum dan sesudah rest time) (waiting info CK)
3. Continue Penyiraman
CE3143
Issue Operational
1. Progres pembentukan base divert 3 Elevasi Actual 43 ke Elevasi 45 (90%) -> XCE 3143
2. Continue pengambilan seam H area PPA ( continue Optimalisasi (on progress)) -> XCE 1312
3. clearing pit GRW 100%, continue Dispsoal GRW 10%
4. counter weight 2 fleet estimasi Selesai (10/11/2023)
5. Uji petik untuk DT Trintin (coal) -> waiting info
6. Percepatan pemenuhan radio Analog DT Trintin (13 unit sudah ready)
7. Perapian tanggul jalan embankment dan jalan CE 4271
6 CE6163 7 GH 12 15 OPD OB 600 6. Pemasangan rambu nama jalan dan rambu simpang (progress menyesuaikan update map November 2023)