Hydraulic Analysis of Sewerage (BS EN 752: 2008)

Project: Boardwalk underneath Island Eastern Corridor - Design and Construction


Project No.:

Pipe & Manhole Details Catchment Pipe Flow

Head
Full bore Full Bore Design
USGL USIL DSIL Dia Length Grad. ADWF ADWF Accu. Peaking PWWF Losses Pipe Area Check
USMH DSMH 3 Vel. Cap. Cap.
(mPD) (mPD) (mPD) (mm) (m) (1 in ) (m /day) (l/s) ADWF (l/s) Factor (l/s) Roughness (m2) Cap.
(m/s) (l/s) (l/s)
(ks)
P1 P2 - 4.720 4.712 200 2.845 356 14.4 0.17 0.17 8 1.33 1.00 0.594 0.03 18.66 18.66 OK
P2 P3 - 4.712 4.686 200 7.325 282 0 0.00 0.17 8 1.33 1.00 0.668 0.03 21.00 21.00 OK
P3 P4 - 4.686 4.667 200 5.735 302 0 0.00 0.17 8 1.33 1.00 0.645 0.03 20.28 20.28 OK
P4 P5 - 4.667 4.635 200 8.780 274 0 0.00 0.17 8 1.33 1.00 0.677 0.03 21.28 21.28 OK
P5 P6 - 4.635 4.630 200 1.735 347 0 0.00 0.17 8 1.33 1.00 0.601 0.03 18.90 18.90 OK
P6 P7 - 4.630 4.488 200 15.200 107 0 0.00 0.17 8 1.33 1.00 1.090 0.03 34.24 34.24 OK
P7 P8 - 4.615 4.429 200 51.100 275 0 0.00 0.17 8 1.33 1.00 0.677 0.03 21.27 21.27 OK
P8 P9 - 4.429 4.293 200 32.200 237 0 0.00 0.17 8 1.33 1.00 0.730 0.03 22.93 22.93 OK
P9 P10 - 4.293 4.200 200 36.300 390 0 0.00 0.17 8 1.33 1.00 0.567 0.03 17.80 17.80 OK
P10 P11 - 4.200 4.000 200 49.800 249 0 0.00 0.17 8 1.33 1.00 0.712 0.03 22.35 22.35 OK
P11 P12 - 4.000 3.900 200 39.300 393 0 0.00 0.17 8 1.33 1.00 0.565 0.03 17.74 17.74 OK
P12 FMH13B - 3.900 3.000 200 23.200 26 0 0.00 0.17 8 1.33 1.00 2.230 0.03 70.05 70.05 OK

Formulas:-
1/2 1/2
v= -(8gDs) x log(ks/3.7D + 2.51v/R(2gDS) ) (Colebrook-White Equation)

Abbreviations:-
USMH Upstream Manhole USIL Upstream Invert Level
DSMH Downstream Manhole DSIL Downstream Invert Level

Notes:
*Min. velocity for sewer diameter <300mm should be at least 0.7m/s, or gradient of 1:DN. (BS EN 752:2008)
*Min. velocity for sewer diameter up to 900mm should be at least 1.0m/s. (BS EN 752:2008)
*Max. velocity for sewer should be less than 3.0m/s. (BS EN 752:2008)