You are on page 1of 45

Reinforcement Total Work Done Till 01/07/2016 for Kharkai Project

Total
Sr . No.Structure EL Upto Work Done Certified SECC
12 Dia 16 Dia 25 Dia 32 Dia Total Claimed Diffrence Remarks

Left Bank
1 Pier -1 146 4.16 68.61 143.91 216.68 203.42 -13.26
2 Pier -2 146 2.64 68.32 145.11 216.07 199.84 -16.23
3 Pier - 3 139.3 1.88 47.51 126.86 176.25 174.77 -1.48
4 Pier -4 143.9 2.53 61.04 141.45 205.01 207.30 2.29
5 Pier - 5 130 1.24 41.53 94.90 137.67 142.67 5.00
6 Pier - 6 130 0.78 33.75 69.74 104.27 105.98 1.71
7 Pier - 7 130 0.49 31.14 69.05 100.68 105.52 4.84
8 Pier 8 & 9 130 0.34 5.33 88.61 265.77 360.04 368.29 8.25
9 Left Abutment U/s & D/s 146.50/146 1.29 81.24 13.85 96.38 94.001 -2.38
10 Left Bank FOW U/s Complete 31.50 0.00 0.00 31.50 27.647 -3.85
11 Left Bank FOW D/s 137 4.85 0.17 0.00 5.02 5.531 0.51
Stilling Basin & Bay Left Side
12 (Excluding Bay 4 Top Mate) 12.11 300.98 0.13
336.35
Rock Anchoring for Left Side Stilling
13 Basin 0.00 0.00 23.13 337.58 1.23
Dia Wise Total 0.34 68.79 822.90 1093.89 1972.55
Bank Total 1985.92
Right Bank

Reinforcement on
Hold for Lift 143.90 to
146.00 as Concrete
1 Pier -15 143.9 2.50 65.69 152.80 220.99 227.80 6.81 not Completed
2 Pier -14 143.9 2.50 65.14 157.60 225.24 225.36 0.12
3 Pier -13 143.9 2.50 72.66 169.28 244.44 243.90 -0.54
4 Pier -12 132.4 1.51 52.32 118.10 171.92 171.96 0.03
5 Pier -11 130 42.31 90.13 132.44 131.60 -0.84
6 Pier -10 130 0.78 30.87 71.62 103.27 103.25 -0.01
7 Right Abutment U/s 145.5 1.39 36.45 5.15 42.99 36.89 -6.10
8 Head Regulator Footing 141.5 12.19 48.28 2.10 62.57 95.19 32.62
9 Right Abutment d/s 146.5 18.71 18.71 13.93 -4.78
Right Abutment U/s & D/s 130/133.5 45.46 11.5 56.96 56.96 0.00
10 RB FOW U/S Section 1 137 5.99 5.99 6.66 0.67
11 RB FOW U/S Section 2 134 4.40 4.40 5.01 0.61
12 RB FOW U/S Section 3 127 2.21 2.21 2.24 0.03
13 RB FOW U/S Section 4 131.5 4.82 4.82 4.90 0.08
14 RB FOW D/S Section 1 134.5 6.05 6.05 5.34 -0.72

Qty Measured But


Hold for the remaining
Concrete in Stilling
Patch of 20 m by 20 M
294.44 318.62 24.17 to be released after
work Done With the
Stilling Basin & Bay Right Side Reinforcement Qty of
15 (Excluding Bay 9 Top Mate) 130/128.50 12.40 249.97 19.28 MT
Rock Anchoring for Right Side
16 Stilling Basin 32.07

Dia Wise Total 59.25 727.86 810.34 1649.60


Bank Total 1597.45
Grand Total 3583.37
SEECPL Right Bank Grand Total of Reinforcement Upto 01/07/2016
Sr. No Description From EL To EL 16 Dia 25 Dia 32 Dia Sub Total Remarks
1 Pier -15 130 1.21 36.41 83.79 121.41
130 132.4 0.33 4.56 13.56 18.44
132.4 134.7 0.13 4.56 11.82 16.51
134.7 137 0.13 4.56 11.82 16.51
137 139.3 0.13 4.72 13.36 18.21
139.3 141.6 0.28 5.94 9.63 15.85
141.6 143.9 0.28 4.95 8.83 14.06
Work Done But
Concrete Not
143.9 146 0.46 4.41 6.36 11.23 Complete
Structure Total 232.21
2 Pier -14 130 1.21 36.93 88.59 126.73
130 132.4 0.33 4.56 13.56 18.44
132.4 134.7 0.13 4.56 11.82 16.51
134.7 137 0.13 4.56 11.82 16.51
137 139.3 0.13 4.72 13.36 18.21
139.3 141.6 0.28 4.87 9.63 14.78
141.6 143.9 0.28 4.95 8.83 14.06
Structure Total 225.24
3 Pier -13 130 1.21 44.45 100.27 145.93
130 132.4 0.33 4.56 13.56 18.44
132.4 134.7 0.13 4.56 11.82 16.51
134.7 137 0.13 4.56 11.82 16.51
137 139.3 0.13 4.72 13.36 18.21
139.3 141.6 0.28 4.87 9.63 14.78
141.6 143.9 0.28 4.95 8.83 14.06
Structure Total 244.44
4 Pier -12 130 1.21 47.76 104.54 153.51
130 132.4 0.30 4.56 13.56 18.41
Structure Total 171.92
5 Pier -11 41.883 90.13 132.01
Shear Zone 0.428 0.43
Structure Total 132.44
6 Pier -10 130 0.78 30.44 71.62 102.84
Shear Zone 0.426 0.43
Structure Total 103.27
Reinforcement used for
7 mould casting 1.19 1.19
8 Rock Anchoring for Right Side Stilling Basin 32.07 32.07
9 Stilling Basin and Bay
Bay 15 - Upto 32.50 0.253 38.46 0 38.71
Bay 14 - Upto 32.50 13.63 13.63
Bay 13 - Upto 32.50 13.76 13.76
Bay 12 - Upto 32.50 14.10 14.10
Bay 11 - Upto 32.50 13.60 13.60
Bay 10 - Upto 32.50 12.59 12.59
Bay 9 - Cut off trench 3.18 3.18
Stilling Basin(Pier & Bay Complete) 1.860 156.25 158.11
Chute Block & Basin Block as on date 01/08/2016 10.290 10.29
Structure Total 277.97
Sr. No Description From EL To EL 16 Dia 25 Dia 32 Dia Sub Total Remarks

Qty Measured But


Hold for the remaining
Concrete in Stilling
Patch of 20 m by 20 M
to be released after
Deduction -19.28 work Done
Final Bill Total 258.69

10 Right Abutment U/s & D/s 124 130.00/133.2 45.46 11.5 56.96
10A Head Regulator Footing 139 141.5 12.19 48.28 2.1 62.57
10B Right Abutment U/s
130 132.4 0.263 4.49 1.36 6.11
132.4 134.7 4.94 1.36 6.30
134.7 137 0.18 4.93 1.36 6.47
137 139.4 0.17 5.87 1.07 7.11
139.4 141.5 0.21 6.72 6.93
141.5 143.8 0.21 5.72 5.93
143.8 145.5 0.36 3.78 4.14
10C Right Abutment D/s 133.2 146.5 18.71 18.71
Structure Total 181.23
11 Right Bank FOW U/s
11A RB FOW U/S Section 1 123 137 5.99 5.99
11 B RB FOW U/S Section 2 123 134 4.40 4.40
11 C RB FOW U/S Section 3 123 127 2.21 2.21
11 D RB FOW U/S Section 4 123 131.5 4.82 4.82
Structure Total 17.43
12 Right Bank FOW D/s
12A RB FOW D/S Section 1 123 134.5 6.05 6.05
Structure Total 6.05
SEECPL Left Bank Grand Total of Reinforcement Upto 01/07/2016
Sr. No Description From EL To EL 12 Dia 16 Dia 25 Dia 32 Dia Sub Total Remarks
1 Pier -1 139.3 3.14 53.31 119.69 176.14
139.3 141.6 0.28 5.94 9.03 15.25
141.6 143.9 0.28 4.95 8.83 14.06
143.9 146 0.46 4.41 6.36 11.23
Structure Total 216.68
2 Pier -2 132.4 1.23 38.68 82.85 122.76
132.4 134.7 0.13 4.56 11.82 16.51
134.7 137 0.13 4.56 11.82 16.51
137 139.3 0.13 5.22 13.58 18.93 1.078
139.3 141.6 0.28 5.94 10.85 17.07
141.6 143.9 0.28 4.95 7.83 13.06
143.9 146 0.46 4.41 6.36 11.23
Structure Total 216.07
3 Pier -3 130 1.16 28.61 75.91 105.68
130 132.4 0.33 4.56 11.82 16.71 0.506667
132.4 134.7 0.13 4.56 11.82 16.51
134.7 137 0.13 4.56 13.73 18.42 40
137 139.3 0.13 5.22 13.58 18.93 174
Structure Total 176.25
4 Pier -4 130 1.2 30.75 71.59 103.54 180
130 132.4 0.33 5.06 11.96 17.35
132.4 134.7 0.18 4.56 11.82 16.56 32.45
134.7 137 0.13 4.56 15.50 20.19 162.25
137 139.3 0.13 5.22 12.54 17.89 625.3115
139.3 141.6 0.28 5.94 10.85 17.07
141.6 143.9 0.28 4.95 7.19 12.42
Structure Total 205.01
5 Pier 5 0.78 31.91 70.89 103.58
130 132.4 0.33 5.06 12.19 17.58
132.4 134.7 0.13 4.56 11.82 16.51
Structure Total 137.67
6 Pier -6 130 0.78 33.32 69.74 103.84
Shear Zone 0.439 0.44
Structure Total 104.27
7 Pier -7 130 0.49 30.72 69.05 100.26
Shear Zone 0.42 0.42
Structure Total 100.68
8 Pier 8 & 9 (Zone 1) 130 0.82 41.37 103.42 145.61
Pier 8 & 9 (Zone 2) 128.5 28.42 77.43 105.85
128.5 130 2.03 8.3 10.33
Pier 8 & 9 (Zone 3) 130 0.34 4.51 16.79 76.62 98.25
Structure Total 360.04
Reinforcement used for
9 mould casting 1.426 1.43
10 Rock Anchoring for Right Side Stilling Basin 23.13 23.13
11 Stilling Basin and Bay 12.11 300.98 0.13 313.22

Qty Measured in Last


Deduction 126.92 Season For Work Done
Final Bill Total 186.30 Footing 2.05 0.171
130 132.4 1.07
12 Left Abutment U/s & D/s 124 139.5/138 0.72 58.64 13.1 72.46 7.5 24.5 132.1 134.5 0.599
12A Left Abutment U/s 139.5 146 0.57 11.68 0.75 13.00 30 335 134.5 136.3 0.605 129.5
12B Left Abutment D/s 138 146.5 10.92 10.92 32 25 528.63 136.3 137 0.528 133.2
Structure Total 96.38 309.288 184 4.852 136.4
13 Left Bank FOW U/s 290.352
13A RB FOW U/S Section 1 128 148.5 7.97 7.97
13 B RB FOW U/S Section 2 128 148.5 9.19 9.19
13 C RB FOW U/S Section 3 128 142.5 8.25 8.25
13 D RB FOW U/S Section 4 128 136.5 6.10 6.10
Inclusive Work Done Certified Last Season (9.23 MT)
Structure Total 31.50
14 Right Bank FOW D/s
RB FOW D/S Section 1 127 137 4.85 0.17 5.02 0.464
Structure Total 5.02
Work Done Quantity for Right bank Stilling basin Complete
SL. Bar Dia. Specing No of No of Total Cut. Length Total Length Dia Wise Weight in MT
Description of Bar Size and Shape of Bar Members Remark's
No Mkd. (mm) (mm) Bar Bar (mtr) (mtr) 16 mm 25 mm 32 mm
1 2 3 4 5 6 7 8 9=7*8 10 11=9*10 12 = 11* Unit Weight 13
Bay 15 Cut Off Trench U/s End to 0.00 to 0.00
1250

1250
8250 25 250 35 1 35 18.100 633.50 0.000 2.439 0.000
6500
Main Reinforcement Provided
on upstream 850 8.25 5.5 6.75

SD 1250
7500
25 250 17 1 17 8.750 148.75 0.000 0.573 0.000
Side Distribution rod Provided
from U/s End to 0.00 33 132

SD1 8650 25 250 17 1 17 8.650 147.05 0.000 0.566 0.000

Side Distribution SD 8500 25 250 34 1 34 8.500 289.00 0.000 1.113 0.000


Reinforcement Provided in
Slope Section & Bottom
Bay 15 Cut Off Trench U/s End to 0.00 to 19.90
1250
1250
8250 25 250 74 1 74 14.100 1043.40 0.000 4.017 0.000
Main Reinforcement Provided 6500
on upstream from Chainage
0.00 to 19.50 850 257.6 60 11.5
1250

1250
7600 25 250 18 1 18 13.450 242.10 0.000 0.932 0.000
Main Reinforcement Provided 5000
on upstream from Chainage
19.90. to 24.40 850 7 18
1250
1250
6750 25 250 166 1 166 11.100 1842.60 0.000 7.094 0.000
Main Reinforcement Provided 3500
on upstream from Chainage
24.40. to 64.40 850 6.75

Side Distribution rod Provided SD1 64.40 + 6 Laps 25 250 23 1 23 71.500 1644.50 0.000 6.331 0.000
from U/s End to 0.00 TO 64.40
FROM EL 123.00 to 128.50 0.75 22

SD1 22.15 + 1 Laps 25 250 6 1 6 23.400 140.40 0.000 0.541 0.000

Side Distribution SD 64.40 + 6 Laps 25 250 14 1 14 71.500 1001.00 0.000 3.854 0.000
Reinforcement Provided in
Slope Section & Bottom 6.375 40

Side Distribution SD 22.150 + 1 Laps 25 250 6 1 6 23.400 140.40 0.000 0.541 0.000
Reinforcement Provided in
Slope Section & Bottom 6.375 40 44.3
Bay 15( u/S End From 0.00 to 32.50)
8500
Top reinforcement Provided Td 400 25 250 131 1 131 9.400 1231.40 0.000 4.741 0.000
Across the river 500
3690 2180 880
400 1250
Td1 25 250 35 1 35 36.000 1260.00 0.000 4.851 0.000
Top reinforcement Provided 12000 1720 680 4750
Along the river 7250 Upto 31.65-1.25 -5 130
Support Rods 25 8 1 8 3.700 29.60 0.000 0.114 0.000
25 24 1 24 3.300 79.20 0.000 0.305 0.000 31.65
25 5 1 5 3.200 16.00 0.000 0.062 0.000 14.44
25 35 1 35 2.200 77.00 0.000 0.296 0.000
25 9 1 9 2.500 22.50 0.000 0.087 0.000
Dowel Rods on Construction 16 100 1 100 1.600 160.00 0.253 0.000 0.000
Joint
Sub -total 0.253 38.455 0.000

Bay 14 Cut Off Trench U/s End to 0.00 to 0.00


1250

1250
8250 25 250 30 1 30 18.100 543.00 0.000 2.091 0.000
6500
Main Reinforcement Provided
on upstream 850 8.25 5.5 6.75

SD1 7500 25 250 34 1 34 6.000 204.00 0.000 0.785 0.000


Side Distribution rod Provided
from U/s End to 0.00

Side Distribution SD 7500 25 250 34 1 34 6.000 204.00 0.000 0.785 0.000


Reinforcement Provided in
Slope Section & Bottom
Bay 14( u/S End From 0.00 to 32.50)
7300
Td 450 450 25 250 131 1 131 9.600 1257.60 0.000 4.842 0.000
Top reinforcement Provided 700 700
Across the river
3690 2180 880 1250
Td1 400 25 250 30 1 30 36.000 1080.00 0.000 4.158 0.000
Top reinforcement Provided 12000 1720 680 4750 7250
Along the river Upto 31.65-1.25 -5 130
Support Rods 25 4 1 4 2.750 11.00 0.000 0.042 0.000
25 3 1 3 3.000 9.00 0.000 0.035 0.000 31.65
25 11 1 11 3.200 35.20 0.000 0.136 0.000 14.44
25 34 1 34 1.200 40.80 0.000 0.157 0.000
25 37 1 37 2.500 92.50 0.000 0.356 0.000
25 30 1 30 2.100 63.00 0.000 0.243 0.000
Sub -total 0.000 13.629 0.000

Bay 13 Cut Off Trench U/s End to 0.00 to 0.00


1250

1250
9250 25 250 30 1 30 20.100 603.00 0.000 2.322 0.000
7500
Main Reinforcement Provided
on upstream 850 8.25 5.5 6.75

SD1 6000 25 250 38 1 38 6.000 228.00 0.000 0.878 0.000


Side Distribution rod Provided
from U/s End to 0.00

Side Distribution SD 6000 25 250 36 1 36 6.000 216.00 0.000 0.832 0.000


Reinforcement Provided in
Slope Section & Bottom
Bay 13( u/S End From 0.00 to 32.50)
7300
Td 450 450 25 250 131 1 131 9.600 1257.60 0.000 4.842 0.000
Top reinforcement Provided 700 700
Across the river
3690 2180 880 1250
Td1 400 25 250 30 1 30 36.000 1080.00 0.000 4.158 0.000
Top reinforcement Provided 12000 1720 680 4750 7250
Along the river Upto 31.65-1.25 -5 130
Support Rods 25 7 1 7 3.200 22.40 0.000 0.086 0.000
25 17 1 17 2.400 40.80 0.000 0.157 0.000 31.65
25 90 1 90 0.700 63.00 0.000 0.243 0.000 14.44
25 30 1 30 2.100 63.00 0.000 0.243 0.000
Sub -total 0.000 13.759 0.000

Bay 12 Cut Off Trench U/s End to 0.00 to 0.00


1250

1250
9750 25 250 30 1 30 21.100 633.00 0.000 2.437 0.000
8000
Main Reinforcement Provided
on upstream 850

SD1 7500 25 250 39 1 39 6.000 234.00 0.000 0.901 0.000


Side Distribution rod Provided
from U/s End to 0.00

Side Distribution SD 7500 25 250 37 1 37 6.000 222.00 0.000 0.855 0.000


Reinforcement Provided in
Slope Section & Bottom
Bay 12( u/S End From 0.00 to 32.50)
7300
Td 450 450 25 250 131 1 131 9.600 1257.60 0.000 4.842 0.000
Top reinforcement Provided 700 700
Across the river
3690 2180 880
1250
Td1 400 25 250 30 1 30 36.000 1080.00 0.000 4.158 0.000
Top reinforcement Provided 12000 1720 680 4750 7250
Along the river Upto 31.65-1.25
Support Rods 25 17 1 17 2.800 47.60 0.000 0.183 0.000
25 8 1 8 3.000 24.00 0.000 0.092 0.000
25 75 1 75 0.700 52.50 0.000 0.202 0.000
25 30 1 30 2.100 63.00 0.000 0.243 0.000
25 4 1 4 12.000 48.00 0.000 0.185 0.000
Sub -total 0.000 14.098 0.000

Bay 11 Cut Off Trench U/s End to 0.00 to 0.00


1250

1250
8250 25 250 31 1 31 18.100 561.10 0.000 2.160 0.000
6500
Main Reinforcement Provided
on upstream 850

SD1 7500 25 250 33 1 33 6.000 198.00 0.000 0.762 0.000


Side Distribution rod Provided
from U/s End to 0.00

Side Distribution SD 7500 25 250 31 1 31 6.000 186.00 0.000 0.716 0.000


Reinforcement Provided in
Slope Section & Bottom
Bay 11( u/S End From 0.00 to 32.50)
7300
Td 450 450 25 250 131 1 131 9.600 1257.60 0.000 4.842 0.000
Top reinforcement Provided 700 700
Across the river
3690 2180 880
400 1250
Td1 25 250 31 1 31 36.000 1116.00 0.000 4.297 0.000
Top reinforcement Provided 12000 1720 680 4750
Along the river 7250 Upto 31.65-1.25
Support Rods 25 12 1 12 12.000 144.00 0.000 0.554 0.000
25 65 1 65 0.600 39.00 0.000 0.150 0.000
25 45 1 45 0.700 31.50 0.000 0.121 0.000
Sub -total 0.000 13.603 0.000

Bay 10 Cut Off Trench U/s End to 0.00 to 0.00


1250

1250
6250 25 250 31 1 31 14.100 437.10 0.000 1.683 0.000
4500
Main Reinforcement Provided
on upstream 850

SD1 7500 25 250 24 1 24 6.000 144.00 0.000 0.554 0.000


Side Distribution rod Provided
from U/s End to 0.00

Side Distribution SD 7500 25 250 21 1 21 6.000 126.00 0.000 0.485 0.000


Reinforcement Provided in
Slope Section & Bottom
Bay 10( u/S End From 0.00 to 32.50)
7300
Td 450 450 25 250 131 1 131 9.600 1257.60 0.000 4.842 0.000
Top reinforcement Provided 700 700
Across the river
3690 2180 880
400 1250
Td1 25 250 31 1 31 36.000 1116.00 0.000 4.297 0.000
Top reinforcement Provided 12000 1720 680 4750
Along the river 7250 Upto 31.65-1.25
Support Rods 25 10 1 10 3.200 32.00 0.000 0.123 0.000
25 10 1 10 12.000 120.00 0.000 0.462 0.000
25 64 1 64 0.600 38.40 0.000 0.148 0.000
Sub -total 0.000 12.594 0.000

Bay 9 Cut Off Trench U/s End to 0.00 to 0.00


1250

1250
6250 25 250 33 1 33 14.100 465.30 0.000 1.791 0.000
4500
Main Reinforcement Provided
on upstream 850

SD1 8000 25 250 24 1 24 8.000 192.00 0.000 0.739 0.000


Side Distribution rod Provided
from U/s End to 0.00 8.5 1 8.5

Side Distribution SD 8000 25 250 21 1 21 8.000 168.00 0.000 0.647 0.000


Reinforcement Provided in
Slope Section & Bottom 7.5 5 37.5
Sub -total 0.000 3.177 0.000 8.75 1 8.75

Stilling Basin Top Mate Chainage 32.50 to 64.40 and north south length 102.75 M From RA upto P8&9 Zone 2 (Complete)

TD1 102.75 400 25 250 119 1 119 116.500 13863.50 0.000 53.374 0.000
Top reinforcement Provided +10 Laps 850
Across the river 32.50 to 61.90

Distribution Reinforcement TD1 102.75 1250 25 250 23 1 23 116.500 2679.50 0.000 10.316 0.000
Provided in End Sill Upto +10 Laps
128.00 including Slope 10+2+11 18.75

Distribution Reinforcement 55 + 3 Laps


Provided in End Sill from 25 250 22 1 22 60.000 1320.00 0.000 5.082 0.000
128.00 to 130.50 in The length 1.25
of 55 M from RA End
including Slope
2.75 .35
+1 Lap
31.50+ 3 Laps
5 25 250 220 1 220 49.600 10912.00 0.000 42.011 0.000
+1 Lap
Top reinforcement Provided 1.25
Along the river 32.50 to 64.40 1.95 .55
for Bay Portion 0
2.75 .35
+1 Lap
29.40+ 3 Laps
5 25 250 192 1 192 48.750 9360.00 0.000 36.036 0.000
1.25 +1 Lap
Top reinforcement Provided 1.25
Along the river 32.50 to 64.40 1.95 .55
for Pier Portion 192 #DIV/0!
Shear in Bay 10-11 25 300 8 1 8 24.000 192.00 0.000 0.739 0.000
25 300 84 1 84 3.500 294.00 0.000 1.132 0.000
25 46 1 46 29.4 1352.40 0.000 5.207 0.000 29.4 61.9 #DIV/0!
25 403 1 403 0.5 201.50 0.000 0.776 0.000 61.9
25 9 1 9 8 72.00 0.000 0.277 0.000 5.158333
16 50 1 50 0.5 25.00 0.040 0.000 0.000
25 25 1 25 2.7 67.50 0.000 0.260 0.000
25 51 1 51 3.2 163.20 0.000 0.628 0.000
25 3 1 3 12 36.00 0.000 0.139 0.000
25 20 1 20 3.6 72.00 0.000 0.277 0.000
Dowel Bars on Construction joint 16 45 16 720 1.6 1152.00 1.820 0.000 0.000
Sub -total 1.860 156.255 0.000

400
80
3400
13103.6
Work Done Quantity for Right Abu
SL. Bar Dia. Specing
Description of Bar Size and Shape of Bar
No Mkd. (mm) (mm)
1 2 3 4 5 6
Right Abutment D/s From EL 128.50 to 146.50

1.35
18 + 25 250
4 Laps
Main Renforcement Vertical
Provided

.50 37.60 + 3 Laps .50 25 250


Distribution Reinforcement
Frrom (128.50 to 146.50)

Deduction for Work Done in


Season 1

6 25 250
Main Renforcement Vertical
Provided

.50 37.60 + 3 Laps .50 25 250


Distribution Reinforcement
Frrom (128.50 to 133.20)

7.50.30
.30 19.70
0.80
20 .00+
+ 12Lap
Lap .30
+2 Laps
Quantity for Right Abutment D/s
No of No of Total Cut. Length Total Length Dia Wise Weight in MT
Members Remark's
Bar Bar (mtr) (mtr) 16 mm 25 mm 32 mm
7 8 9=7*8 10 11=9*10 12 = 11* Unit Weight 13

Deduction of 1.50
152 1 152 22.850 3473.20 0.000 13.372 0.000 M for
Reinforcement
from Footing

75 1 75 41.050 3078.75 0.000 11.853 0.000

-152 1 -152 6.000 -912.00 0.000 -3.511 0.000

-19 1 -19 41.050 -779.95 0.000 -3.003 0.000

Total Work Done in Season 2 18.711


18

4.75

3.789474 37.9

4.7
Work Done Quantity for Left bank Stil
SL. Bar Dia. Specing
Description of Bar Size and Shape of Bar
No Mkd. (mm) (mm)
1 2 3 4 5 6
Bay 1 Cut Off Trench U/s End to 0.00 to 0.00
1250
1250
5000 25 250
3500
Main Reinforcement Provided
on upstream 850

SD 1250
7500 25 250
Side Distribution rod Provided
from U/s End to 0.00

SD1 8650 25 250

Side Distribution SD 8500 25 250


Reinforcement Provided in
Slope Section & Bottom
Bay 1 Cut Off Trench U/s End to 0.00 to 64.40
1250

1250
5000 25 250
Main Reinforcement Provided 3500
on upstream from Chainage
0.00 to 19.50 850

1250

1250
4250 25 250
Main Reinforcement Provided 2750
on upstream from Chainage
19.90. to 24.40 850

1250

1250
3500 25 250
Main Reinforcement Provided 2000
on upstream from Chainage
24.40. to 64.40 850

Side Distribution rod Provided SD1 64.40 + 6 Laps 25 250


from U/s End to 0.00 TO 64.40
FROM EL 125.00 to 128.50

Side Distribution rod Provided SD1 22.15 + 1 Laps 25 250


from U/s End to 0.00 TO 64.40
FROM EL 128.50-130.00

Side Distribution SD 64.40 + 6 Laps 25 250


Reinforcement Provided in
Slope Section & Bottom
Side Distribution SD 22.150 + 1 Laps 25 250
Reinforcement Provided in
Slope Section & Bottom
Bay 1( u/S End From 0.00 to 32.50)
8500
Top reinforcement Provided Td 400 25 250
Across the river 500
3690 2180 880 1250
Td1 400 25 250
Top reinforcement Provided 12000 1720 680 4750 7250
Along the river
Support Rods 25
25
25
25
25
Dowel Rods on Construction 16
Joint

Bay 2 Cut Off Trench U/s End to 0.00 to 0.00


1250
1250
5000 25 250
3500
Main Reinforcement Provided
on upstream 850

SD1 6000 25 250


Side Distribution rod Provided
from U/s End to 0.00

Side Distribution SD 6000 25 250


Reinforcement Provided in
Slope Section & Bottom
Bay 2 ( u/S End From 0.00 to 32.50)
7300
Td 450 450 25 250
Top reinforcement Provided 700 700
Across the river
3690 2180 880
400 1250
Td1 25 250
Top reinforcement Provided 12000 1720 680 4750 7250
Along the river
Support Rods 25
25
25
25
25
25
Bay 3 Cut Off Trench U/s End to 0.00 to 0.00
1250

1250
5000 25 250
3500
Main Reinforcement Provided
on upstream 850

SD1 7500 25 250


Side Distribution rod Provided
from U/s End to 0.00

Side Distribution SD 7500 25 250


Reinforcement Provided in
Slope Section & Bottom
Bay 3( u/S End From 0.00 to 32.50)
7300
Td 450 450 25 250
Top reinforcement Provided 700 700
Across the river
3690 2180 880 1250
Td1 400 25 250
Top reinforcement Provided 12000 1720 680 4750 7250
Along the river
Support Rods 25
25
25
25

Bay 4 Cut Off Trench U/s End to 0.00 to 0.00


1250

1250
5000 25 250
3500
Main Reinforcement Provided
on upstream 850

SD1 6000 25 250


Side Distribution rod Provided
from U/s End to 0.00

Side Distribution SD 6000 25 250


Reinforcement Provided in
Slope Section & Bottom
Bay 4( u/S End From 0.00 to 32.50)
7300
Td 450 450 25 250
Top reinforcement Provided 700 700
Across the river
3690 2180 880 1250
Td1 400 25 250
Top reinforcement Provided 12000 1720 680 4750 7250
Along the river
Support Rods 25
25
25
25
25

Bay 11 Cut Off Trench U/s End to 0.00 to 0.00


1250
1250
8250 25 250
6500
Main Reinforcement Provided
on upstream 850

SD1 7500 25 250


Side Distribution rod Provided
from U/s End to 0.00

Side Distribution SD 7500 25 250


Reinforcement Provided in
Slope Section & Bottom
Bay 11( u/S End From 0.00 to 32.50)
7300
Td 450 450 25 250
Top reinforcement Provided 700 700
Across the river
3690 2180 880 1250
Td1 400 25 250
Top reinforcement Provided 12000 1720 680 4750 7250
Along the river
Support Rods 25
25
25

Bay 10 Cut Off Trench U/s End to 0.00 to 0.00


1250
1250
6250 25 250
4500
Main Reinforcement Provided
on upstream 850

SD1 7500 25 250


Side Distribution rod Provided
from U/s End to 0.00

Side Distribution SD 7500 25 250


Reinforcement Provided in
Slope Section & Bottom
Bay 10( u/S End From 0.00 to 32.50)
7300
Td 450 450 25 250
Top reinforcement Provided 700 700
Across the river
3690 2180 880 1250
Td1 400 25 250
Top reinforcement Provided 12000 1720 680 4750 7250
Along the river
Support Rods 25
25
25

Bay 9 Cut Off Trench U/s End to 0.00 to 0.00


1250
1250
6250 25 250
4500
Main Reinforcement Provided
on upstream 850

SD1 8000 25 250


Side Distribution rod Provided
from U/s End to 0.00

Side Distribution SD 8000 25 250


Reinforcement Provided in
Slope Section & Bottom

Stilling Basin Top Mate Chainage 32.50 to 64.40 and north south length 102.75 M From RA upto P8&9 Zone 2 (Co

TD1 102.75 400 25 250


Top reinforcement Provided +10 Laps 850
Across the river 32.50 to 61.90

Distribution Reinforcement TD1 102.75 1250 25 250


Provided in End Sill Upto +10 Laps
128.00 including Slope

Distribution Reinforcement 55 + 3 Laps


Provided in End Sill from 25 250
128.00 to 130.50 in The length 1.25
of 55 M from RA End
including Slope
2.75 .35
+1 Lap
31.50+ 3 Laps
5 25 250
+1 Lap
Top reinforcement Provided 1.25
Along the river 32.50 to 64.40 1.95 .55
for Bay Portion
2.75 .35
+1 Lap
29.40+ 3 Laps
5 25 250
1.25 +1 Lap
Top reinforcement Provided 1.25
Along the river 32.50 to 64.40 1.95 .55
for Pier Portion
25
25
25
16
25
25
25
25
Dowel Bars on Construction joint 16

400
80
3400
13103.6
y for Left bank Stilling basin Complete
No of No of Total Cut. Length Total Length Dia Wise Weight in MT
Bar Members Bar (mtr) (mtr) 16 mm 25 mm 32 mm
7 8 9=7*8 10 11=9*10 12 = 11* Unit Weight

35 1 35 11.850 414.75 0.000 1.597 0.000

10 1 10 8.750 87.50 0.000 0.337 0.000

10 1 10 8.650 86.50 0.000 0.333 0.000

21 1 21 8.500 178.50 0.000 0.687 0.000

74 1 74 11.850 876.90 0.000 3.376 0.000

18 1 18 10.350 186.30 0.000 0.717 0.000

159 1 159 8.850 1407.15 0.000 5.418 0.000

10 1 10 71.500 715.00 0.000 2.753 0.000

6 1 6 23.400 140.40 0.000 0.541 0.000

12 1 12 71.500 858.00 0.000 3.303 0.000


6 1 6 23.400 140.40 0.000 0.541 0.000

131 1 131 9.400 1231.40 0.000 4.741 0.000

35 1 35 36.000 1260.00 0.000 4.851 0.000

8 1 8 3.700 29.60 0.000 0.114 0.000


24 1 24 3.300 79.20 0.000 0.305 0.000
5 1 5 3.200 16.00 0.000 0.062 0.000
35 1 35 2.200 77.00 0.000 0.296 0.000
9 1 9 2.500 22.50 0.000 0.087 0.000

100 1 100 1.600 160.00 0.253 0.000 0.000

Sub -total 0.253 30.057 0.000

30 1 30 11.850 355.50 0.000 1.369 0.000

20 1 20 6.000 120.00 0.000 0.462 0.000

21 1 21 6.000 126.00 0.000 0.485 0.000

131 1 131 9.600 1257.60 0.000 4.842 0.000

30 1 30 36.000 1080.00 0.000 4.158 0.000

4 1 4 2.750 11.00 0.000 0.042 0.000


3 1 3 3.000 9.00 0.000 0.035 0.000
11 1 11 3.200 35.20 0.000 0.136 0.000
34 1 34 1.200 40.80 0.000 0.157 0.000
37 1 37 2.500 92.50 0.000 0.356 0.000
30 1 30 2.100 63.00 0.000 0.243 0.000
Sub -total 0.000 12.284 0.000
30 1 30 11.850 355.50 0.000 1.369 0.000

38 1 38 7.500 285.00 0.000 1.097 0.000

36 1 36 7.500 270.00 0.000 1.040 0.000

131 1 131 9.600 1257.60 0.000 4.842 0.000

30 1 30 36.000 1080.00 0.000 4.158 0.000

7 1 7 3.200 22.40 0.000 0.086 0.000


17 1 17 2.400 40.80 0.000 0.157 0.000
90 1 90 0.700 63.00 0.000 0.243 0.000
30 1 30 2.100 63.00 0.000 0.243 0.000
Sub -total 0.000 13.234 0.000

30 1 30 11.850 355.50 0.000 1.369 0.000

20 1 20 6.000 120.00 0.000 0.462 0.000

21 1 21 6.000 126.00 0.000 0.485 0.000

131 1 131 9.600 1257.60 0.000 4.842 0.000

30 1 30 36.000 1080.00 0.000 4.158 0.000


17 1 17 2.800 47.60 0.000 0.183 0.000
8 1 8 3.000 24.00 0.000 0.092 0.000
75 1 75 0.700 52.50 0.000 0.202 0.000
30 1 30 2.100 63.00 0.000 0.243 0.000
4 1 4 12.000 48.00 0.000 0.185 0.000
Sub -total 0.000 12.221 0.000

31 1 31 18.100 561.10 0.000 2.160 0.000

33 1 33 7.500 247.50 0.000 0.953 0.000

31 1 31 7.500 232.50 0.000 0.895 0.000

131 1 131 9.600 1257.60 0.000 4.842 0.000

31 1 31 36.000 1116.00 0.000 4.297 0.000

12 1 12 12.000 144.00 0.000 0.554 0.000


65 1 65 0.600 39.00 0.000 0.150 0.000
45 1 45 0.700 31.50 0.000 0.121 0.000
Sub -total 0.000 13.972 0.000

31 1 31 14.100 437.10 0.000 1.683 0.000

24 1 24 7.500 180.00 0.000 0.693 0.000

21 1 21 7.500 157.50 0.000 0.606 0.000


131 1 131 9.600 1257.60 0.000 4.842 0.000

31 1 31 36.000 1116.00 0.000 4.297 0.000

10 1 10 3.200 32.00 0.000 0.123 0.000


10 1 10 12.000 120.00 0.000 0.462 0.000
64 1 64 0.600 38.40 0.000 0.148 0.000
Sub -total 0.000 12.854 0.000

33 1 33 14.100 465.30 0.000 1.791 0.000

24 1 24 8.000 192.00 0.000 0.739 0.000

21 1 21 8.000 168.00 0.000 0.647 0.000

Sub -total 0.000 3.177 0.000

m RA upto P8&9 Zone 2 (Complete)

119 1 119 116.500 13863.50 0.000 53.374 0.000

23 1 23 116.500 2679.50 0.000 10.316 0.000

22 1 22 60.000 1320.00 0.000 5.082 0.000

220 1 220 49.600 10912.00 0.000 42.011 0.000


192 1 192 48.750 9360.00 0.000 36.036 0.000

46 1 46 29.4 1352.40 0.000 5.207 0.000


403 1 403 0.5 201.50 0.000 0.776 0.000
9 1 9 8 72.00 0.000 0.277 0.000
50 1 50 0.5 25.00 0.040 0.000 0.000
25 1 25 2.7 67.50 0.000 0.260 0.000
51 1 51 3.2 163.20 0.000 0.628 0.000
3 1 3 12 36.00 0.000 0.139 0.000
20 1 20 3.6 72.00 0.000 0.277 0.000
45 8 360 1.6 576.00 0.910 0.000 0.000
Sub -total 0.950 154.383 0.000
Remark's

13

8.25 5.5 6.75

33 132

19

60 11.5

8.5 18

4.25 6.75

6 0.75 22

6.375 40
6.375 40 44.3

Upto 31.65-1.25 -5 130

31.65
14.44

8.25 5.5 6.75

Upto 31.65-1.25 -5 130

31.65
14.44
8.25 5.5 6.75

Upto 31.65-1.25 -5 130

31.65
14.44

Upto 31.65-1.25
Upto 31.65-1.25
Upto 31.65-1.25

8.5 1 8.5

7.5 5 37.5
8.75 1 8.75

31.9 -29.4

10+2+11 -117.6 18.75

60

0
#DIV/0!
29.4 61.9 #DIV/0!
61.9
5.158333
Work Done quantity for Piers
SL. Bar Dia. Specing No of
Description of Bar Size and Shape of Bar
No Mkd. (mm) (mm) Bar
1 2 3 4 5 6 7
Pier 2 (EL 130.00 to 140.50)

Main Reinforcement Vertical


Provided From EL 130.00 to 140.50
in Downstream
antity for Piers
No of Total Cut. Length
Total Length Dia Wise Weight in MT
Members Remark's
Bar (mtr) (mtr) 16 mm 25 mm 32 mm
8 9=7*8 10 11=9*10 12 = 11* Unit Weight 13
Work Done Quantity for Right Abu
SL. Bar Dia. Specing
Description of Bar Size and Shape of Bar
No Mkd. (mm) (mm)
1 2 3 4 5 6
Left Abutment D/s From EL 138.00 to 146.50

1.35
18 + 25 250
4 Laps
Main Renforcement Vertical
Provided

.50 37.60 + 3 Laps .50 25 250


Distribution Reinforcement
Frrom (128.50 to 146.50)
25
25

25
Left Abutment Us 139.50 to
146.50
25
25
25
25
Shear Reinforcement 139.50 to 141.00 32
141.00-146.00 16
16
Abutment Verticals 25
25

Left Flared Out Wall U/s Section 1


1400
A 1850 16 250
800
Main Reinforcement Provided 2100
in from EL 127.50 850

Distribution Reinforcement in .50 19.70 + 2 Laps 16 250


Footing

1.40
19.50 + 5 Laps 16 250
Main Reinforcement Provided 0.80
in from EL 129.50
.50 20.10 + 1 Laps .50
Distribution Reinforcement 16 250
Frrom (129.50 to 148.50)
inclined Average Length 19.50

Left Flared Out Wall U/s Section 2


1400
A 1850 16 250
800
Main Reinforcement Provided 2100
in from EL 127.50 850

Distribution Reinforcement in 20 + 2 Laps 16 250


Footing

1.40
23.30 + 6 Laps 16 250
Main Reinforcement Provided 0.80
in from EL 129.50

Distribution Reinforcement .50 20.40 + 1 Laps .50


Frrom (129.50 to 148.50) 16 250
inclined average length 23.30
M

Left Flared Out Wall U/s Section 3


1400
A 1850 16 250
800
Main Reinforcement Provided 2100
in from EL 127.50 850

Distribution Reinforcement in 20 + 2 Laps 16 250


Footing

1.40
20.10 + 5 Laps 16 250
Main Reinforcement Provided 0.80
in from EL 129.50

Distribution Reinforcement .50 20.50 + 1 Laps .50


Frrom (129.50 to 142.50) 16 250
inclined average length 23.30
M

Left Flared Out Wall U/s Section 4


1400
A 1850 16 250
800
Main Reinforcement Provided 2100
in from EL 127.50 850

Distribution Reinforcement in .50 20 + 1 Laps 16 250


Footing

1.40
12.85 + 4 Laps 16 250
Main Reinforcement Provided 0.80
in from EL 129.50

Distribution Reinforcement .50 20.80 + 1 Laps .50


Frrom (129.50 to 142.50) 16 250
inclined average length 23.30
M
Quantity for Right Abutment D/s
No of No of Total Cut. Length Total Length Dia Wise Weight in MT
Members Remark's
Bar Bar (mtr) (mtr) 16 mm 25 mm 32 mm
7 8 9=7*8 10 11=9*10 12 = 11* Unit Weight 13

Deduction of 1.50
75 1 75 6.000 450.00 0.000 1.733 0.000 M for
Reinforcement
from Footing

40 1 40 41.050 1642.00 0.000 6.322 0.000

5 1 5 6.700 33.50 0.000 0.129 0.000


1 1 1 710.680 710.68 0.000 2.736 0.000
Total Work Done in Season 2 0.000 10.919 0.000

28 7.500 210.00 0.000 0.809 0.000


28 1
28 2 56 2.500 140.00 0.000 0.539 0.000
28 2 56 6.000 336.00 0.000 1.294 0.000
28 2 56 4.000 224.00 0.000 0.862 0.000
28 1 28 22.400 627.20 0.000 2.415 0.000
7 10 70 1.700 119.00 0.000 0.000 0.751
20 10 200 1.000 200.00 0.316 0.000 0.000
39 1 39 4.100 159.90 0.253 0.000 0.000
162 1 162 6.000 972.00 0.000 3.742 0.000
1 1 1 525.567 525.57 0.000 2.023 0.000
Total Work Done in Season 2 0.569 11.684 0.751

80 1 80 7.000 560.00 0.885 0.000 0.000

24 1 24 22.300 535.20 0.846 0.000 0.000

82 1 82 25.700 2107.40 3.330 0.000 0.000


84 1 84 21.900 1839.60 2.907 0.000 0.000

Total Work Done in Season 2 7.967 0.000 0.000

80 1 80 7.000 560.00 0.885 0.000 0.000

24 1 24 21.600 518.40 0.819 0.000 0.000

83 1 83 30.300 2514.90 3.974 0.000 0.000

100 1 100 22.200 2220.00 3.508 0.000 0.000

Total Work Done in Season 2 9.185 0.000 0.000

80 1 80 7.000 560.00 0.885 0.000 0.000

24 1 24 21.600 518.40 0.819 0.000 0.000

84 1 84 26.300 2209.20 3.491 0.000 0.000

87 1 87 22.200 1931.40 3.052 0.000 0.000

Total Work Done in Season 2 8.246 0.000 0.000


80 1 80 7.000 560.00 0.885 0.000 0.000

24 1 24 21.000 504.00 0.796 0.000 0.000

84 1 84 18.250 1533.00 2.422 0.000 0.000

56 1 56 22.600 1265.60 2.000 0.000 0.000

Total Work Done in Season 2 6.103 0.000 0.000


8.5 18

4.75

Left Abutment U/s & Downstream Footing 18.87

1.5
6.5
26
22.4

20

39.18 4.875
46.84

23.42

5.855

93.6 41.3
20.65

40.2

82 41.7
20.85
80.4
26.24

13.12