RFCL PRODUCTION INSPECTION STATUS

UPDATED UPTO 106


UPDATED LOT-28

SR.NO AREA TOTAL SCOPE COMPLETED BALANCE Dispatch Dispatch Balance


1 AREA 1 155.7 145.49 10.21 133.356 22.344

2 AREA 2 91.83 91.83 0 91.973 0

3 AREA 3 37.39 37.39 0 37.39 0

4 AREA 4 154.98 154.98 0 154.609 0.371

5 AREA 5 313.63 313.63 0 308.477 5.153

6 AREA 7 515.75 515.75 0 513.764 1.986

7 AREA-09 236.28 232.7 3.58 214.52 21.76

8 AREA 10 77.47 73.69 3.78 69.3 8.17

9 AREA-11 38.084 38.084 0 35.113 2.971

10 BR-1 72.83 72.83 0 72.83 0

11 BR-2 80.03 80.03 0 80.03 0

12 BR-3 87.6 87.6 0 87.6 0

13 BR-4 70.346 70.346 0 70.511 0

14 BR-5 64.158 62.9 1.258 57.201 6.957

15 BR-7 93.11 83.97 9.14 59.554 33.556

16 BR-8 97.6 87.5 10.1 47.154 50.446

17 BR-9 86.79 66.125 20.665 29.867 56.923

18 BR-10 39.97 23.54 16.43 0 39.97

19 BR-11 54.14 0 54.14 0 54.14

20 AREA-15 29.29 0 29.29 0 29.29

21 AREA-16/17 130.70 4.853 125.847 0 130.7

2527.678 2243.238 284.44 2063.249 179.989

OVERALL INSPECTION STATUS


* RAW MAT. CLEARED 2660
* IRN RECEIVED 2117
* PAINTING ACHIEVED 2117
* DISPATCHED 2063