Discription 6 mm 8 mm 10 mm 12 mm 16 mm 20 mm 25 mm 32 mm Total
RECIEPT-
a) Reciept up to last month 0 10.16 0 15.8 274.493 0 1749.935 2177.17 4227.558
b) Reciept (this month) 0
1) TOTAL 0 10.16 0 15.8 274.493 0 1749.935 2177.17 4227.558
Consumption
c)Payable 0.34 128.037286 1550.76002 1904.23686 3583.374169
e) Non- payable (shuttering work) 0.662 79.35 12.49 0.969 93.4779
f) Lap, chair,Etc 0
h) L & T Febrication Yard 5.65 5.65
i) Theft 0
2) Total Consumption 0 0 0 1.002 213.042186 0 1563.25202 1905.20586 3682.502069
STOCK 0
j) Full Length& Cut Length 10.16 13.5 50.284 72.585 202.572 349.101
k)Fix but not measured 1.56 71.87 48.83 122.258053
l) Cut & Bend not fixed 0.2 0.5 28.76 5.305 34.765
m) Scrap 5 25 30
n) Scrap Return 0
3)Total Stock 0 10.16 0 13.7 52.340812 0 178.21129 281.711951 536.124053
o) Shortage(un accoutable) 0 0 0 1.098 9.110002 0 8.4716856 -9.7478097 8.9318779
4) Wastage % #DIV/0! 0.000% #DIV/0! 6.949% 3.319% #DIV/0! 0.484% -0.448% 0.211%
Left Bank
1 Pier -1 146 4.16 68.61 143.91 216.68 203.42 -13.26
2 Pier -2 146 2.64 68.32 145.11 216.07 199.84 -16.23
3 Pier - 3 139.3 1.88 47.51 126.86 176.25 174.77 -1.48
4 Pier -4 143.9 2.53 61.04 141.45 205.01 207.30 2.29 12 Dia 16 Dia 25 Dia 32 Dia
5 Pier - 5 130 1.24 41.53 94.90 137.67 142.67 5.00
6 Pier - 6 130 0.78 33.75 69.74 104.27 105.98 1.71 0.34 68.78888 822.9018 1093.893
7 Pier - 7 130 0.49 31.14 69.05 100.68 105.52 4.84 59.2484 727.8582 810.344
8 Pier 8 & 9 130 0.34 5.33 88.61 265.77 360.04 368.29 8.25 0.34 128.0373 1550.76 1904.237
9 Left Abutment U/s & D/s 146.50/146 1.29 81.24 13.85 96.38 94.001 -2.38
10 Left Bank FOW U/s Complete 31.50 0.00 0.00 31.50 27.647 -3.85
11 Left Bank FOW D/s 137 4.85 0.17 0.00 5.02 5.531 0.51
Stilling Basin & Bay Left Side
12 (Excluding Bay 4 Top Mate) 12.11 300.98 0.13
336.35
Rock Anchoring for Left Side Stilling
13 Basin 0.00 0.00 23.13 337.58 1.23
Dia Wise Total 0.34 68.79 822.90 1093.89 1972.55
Bank Total 1985.92
Right Bank
Reinforcement on
Hold for Lift 143.90 to
146.00 as Concrete
1 Pier -15 143.9 2.50 65.69 152.80 220.99 227.80 6.81 not Completed 11.23
2 Pier -14 143.9 2.50 65.14 157.60 225.24 225.36 0.12
3 Pier -13 143.9 2.50 72.66 169.28 244.44 243.90 -0.54
4 Pier -12 132.4 1.51 52.32 118.10 171.92 171.96 0.03
5 Pier -11 130 42.31 90.13 132.44 131.60 -0.84
6 Pier -10 130 0.78 30.87 71.62 103.27 103.25 -0.01
7 Right Abutment U/s 145.5 1.39 36.45 5.15 42.99 36.89 -6.10
8 Head Regulator Footing 141.5 12.19 48.28 2.10 62.57 95.19 32.62 20
9 Right Abutment d/s 146.5 18.71 18.71 13.93 -4.78
Right Abutment U/s & D/s 130/133.5 45.46 11.5 56.96 56.96 0.00
10 RB FOW U/S Section 1 137 5.99 5.99 6.66 0.67
11 RB FOW U/S Section 2 134 4.40 4.40 5.01 0.61
12 RB FOW U/S Section 3 127 2.21 2.21 2.24 0.03
13 RB FOW U/S Section 4 131.5 4.82 4.82 4.90 0.08
14 RB FOW D/S Section 1 134.5 6.05 6.05 5.34 -0.72
Sr No. Description EL From EL To 12 Dia 16 Dia 25 dia 32 dia 12 Dia 16 Dia 25 dia 32 dia 16 Dia 25 dia 32 dia Remarks
Last Season
LEFT BANK
1 Left Abutment U/s(Up to 139.5) & D/S (Up to 138.0) 0.72 58.64 13.1
2 Pier-1 126 139.3 3.14 53.31 119.69
3 Pier-2 126 132.4 1.23 38.68 82.85
4 Pier-3 126 130 1.16 28.61 75.91
5 Pier-4 126 130 1.2 30.75 71.59
6 Bay & Stilling Basin 7.03 110.14 9.75
37.71
7 Left Flared out Walls 9.23
Right Bank
1 Right Abutment U/S & D/S 45.46 11.5
2 Pier-15 130 1.21 36.41 83.79
3 Pier-14 130 1.21 36.93 88.59
4 Pier-13 130 1.21 44.45 100.27
5 Pier-12 130 1.21 47.76 104.54
6 Bay & Stilling Basin 35.51
Reinforcement Reconciliation statement
Main Reinforcement Qty (MT) SECCPL Shuttering Reinforcement Qty Main Reinforcement Qty (MT)
Fixed but not measured
Sr No. Description EL From EL To 12 Dia 16 Dia 25 dia 32 dia 12 Dia 16 Dia 25 dia 32 dia 16 Dia 25 dia 32 dia Remarks
This Season
Right Bank
1 Right Abutment U/s 130 145.5 1.23 31.92 3.740 3.022 1.300
2 Regulator Footing 14.78 78.31 2.100 20.00 Hold
3 Right Abutment D/s 133 146.5 13.93 2.200 0.936
4 Right U/S Flared Out Wall Secc-1 123 138 6.662 1.70 0.76 0.26
5 Right U/S Flared Out Wall Secc-2 123 134 5.013 1.18 0.44 0.01
6 Right U/S Flared Out Wall Secc-3 123 130 2.24 0.15 0.05 0.758
7 Right U/S Flared Out Wall Secc-4 123 131 4.9 0.93 0.32
8 Right D/S Flared Out Wall Secc-1 123 134.4 5.335 1.28 0.29
9 Right D/S Flared Out Wall Secc-2 123 128.2 3.38 0.51
10 Pier-15 130 146 2.041 31.41 72.94 2.33 0.05 0.457812 4.41 6.357191 Hold
11 Pier-14 130 143.9 1.937 27.41 69.29 1.65 1.33 1.96
12 Pier-13 130 143.9 1.852 28.05 68.06 1.61 4.37 6.12
13 Pier-12 130 132.4 0.341 4.55 13.55 0.41 0.341 4.55 13.55
14 Pier-11 122 130 1.596 40.49 89.51
15 Pier-10 126 130 1.084 30.62 71.55 0.58 0.03
16 Stilling Basin-9 with Bay-9 Face of Pier to Centre of pier 16.32 2.71 0.038 0.40
17 Stilling Basin-10 with Bay-10 Centre of to center of Pier 1.723 38.95 3.48 0..435 0.2
18 Stilling Basin-11 with Bay-11 Centre of to center of Pier 1.723 36.19 4.73 0.10 0.41 19.28 Hold
19 Stilling Basin-12 with Bay-12 Centre of to center of Pier 1.826 39.86 4.55 0.64
20 Stilling Basin-13 with Bay-13 Centre of to center of Pier 1.853 30.17 4.81 0.44 0.20
21 Stilling Basin-14 with Bay-14 Centre of to center of Pier 1.792 33.20 2.84 0.88
22 Stilling Basin-15 Centre of Pier to face of Abutment 34.97 3.64
23 Bay-15 0.265 16.50 1.02 0.11
24 Mould Reinforcement( SB-3 to SB-8) 1.119
LEFT BANK
1 Left Abutment U/s 139.5 146 0.253 10.555 0.739 1.19 0.61 0.11
2 Left Abutment D/s 138 146.5 9.994 1.97 0.81
3 Left U/S Flared Out Wall Secc-1 133.5 148 3.78 0.153 1.46 0.66
4 Left U/S Flared Out Wall Secc-2 132.1 148.5 4.805 0.164 1.66 0.71
5 Left U/S Flared Out Wall Secc-3 131.5 142.5 3.733 0.15 1.14 0.78
6 Left U/S Flared Out Wall Secc-4 128 136.5 5.502 0.13 1.08 0.26 0.05
7 Left D/S Flared Out Wall Secc-1 127 137 5.359 0.172 0.78 0.26
8 Pier-1 139.3 143.9 1.2 9.96 16.121 0.72 0.11 0.03 0.86846 3.88696
9 Pier-2 132.4 146.2 0.774 26.268 50.079 2.20 0.12 0.01 0.587
10 Pier-3 130 139.3 0.841 18.892 49.36 1.77 0.17 0.07 5.293 4.316
11 Pier-4 130 143.9 0.983 39.228 63.546 2.62 0.23 0.10 2.15 0.454
12 Pier-5 126 134.7 0.468 39.512 102.69 1.33 0.15 1.12
13 Pier-6 126 130 1.691 32.672 71.625 0.092 0.51 0.09 5.055 12.192
14 Pier-7 126 130 0.485 28.76 76.276 0.65 0.13 0.7
15 Pier-8 & 9 Zone-1 126 130 1.02 41.855 102.13 0.111 0.72 1.454
16 Pier-8 & 9 Zone-2 126 129.7 0.006 30.37 88.08 0.271 0.68 0.36 0.03 0.692
17 Pier-8 & 9 Zone-3 125 130 0.083 4.501 16.706 83.537 0.04 0.75 0.05 0.07
18 Stilling Basin-3 0.482 15.89 0.179 0.02 0.48 0.06
19 Stilling Basin-4 Centre of to center of Pier 0.098 29.19 0.588 0.02 0.48 0.06
20 Stilling Basin-5 Centre of to center of Pier 0.212 23.658 1.78 0.01 0.10 0.03
21 Stilling Basin-6 Centre of to center of Pier 33.302 2.981 0.02 0.48 0.06
22 Stilling Basin-7 Centre of to center of Pier
0.007 0.027 0.162 0.015
23 Stilling Basin-8 Centre of pier to Face of Pier 0.137 39.604 3.436
24 Bay-3
25 Bay-4 -19.9 12.6 3.075 1.037 0.03
26 Bay-5 -19.9 12.6 0.912 12.502 1.107 0.091 0.05
27 Bay-6 -19.9 12.6 0.972 12.85 1.031 0.122 0.04
28 Bay-7 -19.9 12.6
0.041 0.046 0.255
29 Bay-8 -19.9 12.6 23.532 2.104
30 Mould Reinforcement( SB-3 to SB-8) 0.067 1.359
0.15 130.82 1598.63 1898.53 0.66 79.35 12.49 0.97 1.56 71.87 48.83
Grand Total 3628.12 93.48 122.26
Certified Up to RAB-31 3542.29
Balance 85.83