You are on page 1of 2

Annexure A - Scope Matrix Client : OQ - TA

STS Ref : Replacement of the existing BWRO Permeate Water Tank ME-5404-T-01 (bolted bottom Rev Rev 1
plate and shell body) with the new welded Tank.

Roof Type : Fixed Cone Roof Tank Details: Date: Date: 14-Aug-23
D 3.751 m x H 7.356 m, Qty-1 No., MOC-A36 / A160 Gr.B / A105N

SCOPE MATRIX

Sr. No. Description STS VENDOR Remarks

1 DESIGN

1.1 Mechanical design of tank Limited to Lifting Design only

1.2 Preparation of GA and detailed Fabrication drawings

1.3 As built drawings

2 SUPPLY OF MATERIALS

2.1 Plates for Shell, Bottom, roof, Platform etc.

2.2 Plates for flanges, plates for nozzle reinforcing pads, plates for necks of nozzles, manholes
MOC as per Datasheet as as per OQ AVME:
All Plates - SA 36.
2.3 Forged flanges, seamless pipes for nozzles, still wells as per data sheet. Nozzles - A 106 GrB / A 105
Fasteners,Gaskets - A 153
Structural Materials- S275 JR
2.4 Fasteners for nozzles, manholes as per data sheet where required.

2.5 Gaskets for manholes, and blind flanges as per data sheet where required.

2.6 Roof access handrails Like to Like as per Design ( Site Verification Required
joint visit with STS TA Team)

2.7 Cage Ladder staircases Like to Like as per Design ( Site Verification Required
joint visit with STS TA Team)

2.8 Supply of name plate, earthing bosses as per data sheet where required. Like to Like as per Design ( Site Verification Required
joint visit with STS TA Team)

As per Design to be installed at Shop


2.9 Anchor chairs ( Site Verification Required joint visit with STS TA
Team)

2.10. Supply of PVRV, PSV as per tank data sheet where required.

2.11 Supply of all other tank instruments Not Considered in BG

2.12 Mechanical works outside tank nozzle/Flanges All BOP works (Not Considered in BG )

2.13 Release Prevention Barrier (RPB) And Leak Detection System All BOP works (Not Considered in BG )

2.14 Insulation No Insulation as per DS

2.15 All welding consumable for fabrication and construction

2.16 Pipe Supports & Instrument and electrical cable supports Like to Like as per Design ( Site Verification Required
joint visit with STS TA Team)

2.17 Safety equipment and signs and signboards Not Considered in BG

2.18 Hydrotest water Supply and Disposal at Shop

2.19 Scaffolding At Shop only

2.20 Tank foundation material Not Considered in BG

3 SCOPE OF WORK - SHOP

3.1 Pre Fabrication of tanks

3.2 PWHT of Shell Manholes & Nozzles as per Code, if required Not Applicable

3.4 Site Erection & Installation of tank Unloading from Trailer at Site excluded

3.5 Hydro testing of tank as per the code Supply and Disposal at Shop

3.6 All NDT (Radiography, MPI, DP etc.) of tank as per the code Related to Tank Only

3.7 Surface preparation & Primer painting of tanks At Shop related to Tank Only ( BG Shop )

3.8 Tank Painting & Lining works As per Datasheet

3.9 All Inspection activities at Shop in compliance to ITP and OQ requirements


Annexure A - Scope Matrix Client : OQ - TA

STS Ref : Replacement of the existing BWRO Permeate Water Tank ME-5404-T-01 (bolted bottom Rev Rev 1
plate and shell body) with the new welded Tank.

Roof Type : Fixed Cone Roof Tank Details: Date: Date: 14-Aug-23
D 3.751 m x H 7.356 m, Qty-1 No., MOC-A36 / A160 Gr.B / A105N

SCOPE MATRIX

Sr. No. Description STS VENDOR Remarks

4 SCOPE OF WORK - SITE

4.1 Transportation from Shop to Site as per OPAL Compliance Only Loading at Shop by BG Fab Shop only -Tank with
required Supports & Saddles

4.2 Required Lifting Lugs / Calculations on the tank for lifting purpose Only Loading at Shop by BG Fab Shop only -Tank with
required Supports & Saddles
Crew to be deployed by vendor. If not STS Crew shall
4.3 Painting Touchup Works at Site in case of Damage due to Loading at Shop be utilised and Backcharged Price to be mutually
agreed.

5 INSURANCE

5.1 Insurance for crew, vehicles & equipment’s Crew work Insurance available( BG)

5.2 Any other insurance Not Considered in BG

6 DOCUMENTATION

6.1 Quality (QA/QC)

6.2 Progress Report (Weekly/Monthly)

7 PQR & WQT

7.1 PQR & WPS will be followed as per STS procedure BG will follow as per STS approved Procedure

7.2 Welder Deployment ( As per the Mail Confirmation STS will be provided during the Execution time Required Since Welder will be provided by STS WQT not
welders to meet the schedule) considered in BG .

You might also like